Permit Information
Permit NumberBLD98-02142
StatusExpired
Name ROPER'S MEN'S STORE
Site Address 120 N 8TH ST
Project NameCAPITAL TERRACE
Customer Number 
ePlanReviewNo
Description
(ROPER'S MEN'S STORE) Fire sprinklers used to meet high-rise requirements. To reduce the size of an existing retail sales tenant space to 3,319 square feet. Work is to include interior non-bearing walls, 1-hr tenant demising wall, an existing restroom modified to be accessible to the disabled, and new exterior entrance doors all per approved drawings and plan review conditions on file. The fire sprinkler system shall comply with NFPA 13 as regulated by the Fire Department. PC-490-98 **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Receive PAYMENT IN FULL  7/1/1999
INSP - Final3/5/19993/5/19993/5/1999 FAIL
Details
03/04/99 338 - NEED FIRE SIGNOFF
INSP-Final Inspection3/5/19993/5/19993/5/1999PPART
DetailsRick Jackson
head within 6 feet and head obstructed by track lighting
Fee Review-notes9/24/1998 2/25/1999
INSP - Framing/Rough-in9/8/19989/8/19989/8/1998 PASS
Details
09/08/98 333 - FRAM-OK FRAMING
INSP - Framing/Rough-in9/4/19989/8/19989/8/1998APASS
Details
09/08/98 333 - FRAM-OK FRAMING
Inspection Record Card- Bld  9/4/1998
Issue PAID IN FULL permit  9/4/1998
PLANS/APPL TAKEN TO FRONT DESK  9/4/1998 PASS
Print Occupancy Form  9/4/1998
Routing - PLAN CHECK9/4/1998 9/4/1998
Plan assigned to (CJW)7/22/1998 9/4/1998 PASS
DetailsCarl Westfall
09/04/98 08:19:01 CJW - this action updated by action script from <<>> in Case No. BLD98-2142
Plan Reviewer's activity  9/3/1998 PASS
Drawings approved, with conditions, after resubmittal review.
Print permit w/o conditions  9/3/1998
Routing - FIRE9/3/1998 9/3/1998 PASS
testing condition printout  9/3/1998
Routing - PLAN CHECK8/26/1998 9/3/1998
Plan Review Completed(1st rev)  8/26/1998 FAIL
Routing - FIRE8/20/1998 8/26/1998 FAIL
Routing - PLAN CHECK7/28/1998 8/20/1998
Plan Reviewer's activity  8/19/1998
UBC plan review started August 19, 1998 and finished the same day. One item requires a response from the Architect. See the conditions list.
Routing - PLANNING7/27/1998 7/28/1998 PASS
Routing - PUBLIC WORKS7/23/1998 7/27/1998 PASS
Plan assigned to (MYS)7/16/1998 7/22/1998
DetailsMarlene Southard
Plan routing begun/TENANTS  7/22/1998
Route to PUBLIC WORKS, PLANNING, PLAN CHECK and FIRE.
Application received  7/16/1998
Recd Pcfee & Taken To Pln CK  7/16/1998