Permanent Occupancy | | 4/8/1999 | 4/8/1999 | | DONE |
|
|
|
|
Permanent occupancy | | | 4/8/1999 | | PASS |
|
|
|
Perm. Occ. Cert. #7724 issued 4-8-99 to Burger King.
|
Receive PAYMENT IN FULL PRINT | | | 4/7/1999 | | |
|
|
|
|
INSP - Final | 3/30/1999 | 3/30/1999 | 3/30/1999 | P | PART |
Carl Dependahl
|
|
|
03/30/99 340 - ###-#### struct ok for perm occ, has fee due???
|
(F) Reprint permit | | | 3/30/1999 | | |
|
|
|
|
Fee Review-notes | 7/23/1998 | | 3/30/1999 | | DONE |
|
|
|
final cert from gc
|
INSP-Conference | 3/25/1999 | 3/25/1999 | 3/25/1999 | | PASS |
Joe Tawney
|
|
|
/ / 406 - GAVE CONTR APPROVAL FOR ASSEMBLY PERMIT
|
INSP-Conference | 3/25/1999 | 3/25/1999 | 3/25/1999 | | PASS |
Joe Tawney
|
|
|
/ / 406 - GAVE CONTR APPROVAL FOR ASSEMBLY PERMIT
|
INSP - Final | 3/25/1999 | 3/25/1999 | 3/25/1999 | P | FAIL |
Carl Dependahl
|
|
|
03/25/99 340 - burger king\\###-#### ty keep c/n, need eng's letter. recall
|
Code Occupancy Approval | | | 3/25/1999 | | PASS |
|
|
|
INSPECTED ON 3/23/99 - POST BOND FOR WHEEL RESTRAINTS- 14 JUNIPERS AND HANDRAIL ($1,125.) - RE-INSPECTD ON 3/24/99 - ALL COMPLETE PER DRH98-0112 - PASS
|
INSP-Final Inspection | 3/23/1999 | 3/24/1999 | 3/24/1999 | A | PASS |
Joe Tawney
|
|
|
03/24/99 406 - REINSP OK FOR PERM OCC
|
INSP - Final | 3/23/1999 | 3/24/1999 | 3/24/1999 | A | FAIL |
Carl Dependahl
|
|
|
03/24/99 340 - ###-#### TY//FINAL c/n,need plbg, c.dh.d.& eng's final acceeptance. ok for t/o card to bldr
|
Temporary occupancy | | | 3/24/1999 | | PASS |
|
|
|
Temp. Occ. Cert. #3804 issued 3-24-99 to Burger King.
|
INSP-Final Inspection | 3/22/1999 | 3/23/1999 | 3/23/1999 | A | FAIL |
Joe Tawney
|
|
|
03/23/99 406 - REINSP FAIL DUCT DET, AIR BAL FOR HOODS
|
INSP - Final | 3/22/1999 | 3/22/1999 | 3/22/1999 | P | FAIL |
Carl Dependahl
|
|
|
03/22/99 340 - need other finals, recall
|
INSP-Final Inspection | 3/19/1999 | 3/22/1999 | 3/22/1999 | A | NR |
Joe Tawney
|
|
|
03/22/99 406 - NOT READY FOR FINAL
|
INSP - Framing/Rough-in | 3/19/1999 | 3/19/1999 | 3/19/1999 | P | FAIL |
Carl Dependahl
|
|
|
03/19/99 340 - ###-#### TY//RI CEILING GRID install seismic braces, has elec cn
|
Code Occupancy Approval | | | 3/18/1999 | | |
|
|
|
Final Occupancy requested by Ty @ ###-####.
|
INSP - Framing/Rough-in | 3/11/1999 | 3/11/1999 | 3/12/1999 | P | FAIL |
Carl Dependahl
|
|
|
03/11/99 340 - SCOTT ###-#### SUSPENDED ACOUSTICAL CEILING INSPECTION need seismic braces
|
INSP - Framing/Rough-in | 2/19/1999 | 2/22/1999 | 2/24/1999 | A | FAIL |
Carl Dependahl
|
|
|
shaft for broiler hood ###-#### Ty...looks ok, need detail for 1hr const. chk w/ ISI & alan H. for his ok
|
INSP - Framing/Rough-in | 2/23/1999 | 2/23/1999 | 2/23/1999 | A | PART |
Alan Hauser
|
|
|
shaft not ready, had to change for clearances
|
INSP - Wall cover | 2/16/1999 | 2/16/1999 | 2/16/1999 | P | PART |
Carl Dependahl
|
|
|
02/16/99 340 - ###-#### Ty; part, rec'd eng's clarification, ok to cover report for steel frame (field insp onsite)
|
INSP - Framing/Rough-in | 2/16/1999 | 2/16/1999 | 2/16/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - play area, part
|
INSP - Framing/Rough-in | 2/11/1999 | 2/11/1999 | 2/12/1999 | P | PART |
Carl Dependahl
|
|
|
02/11/99 340 - PLAY GROUND\\###-####
|
INSP - Framing/Rough-in | 2/8/1999 | 2/9/1999 | 2/9/1999 | A | PART |
Carl Dependahl
|
|
|
02/09/99 340 - ###-#### TY, c/n need all other oks, spec insp for t.s. m
|
INSP - Framing/Rough-in | 2/8/1999 | 2/8/1999 | 2/8/1999 | P | CANC |
|
|
|
cover inspection tye ###-#### cant do because plumbing is not done
|
INSP - Wall cover | 2/3/1999 | 2/4/1999 | 2/4/1999 | P | FAIL |
Carl Dependahl
|
|
|
02/04/99 340 - TY ###-#### keep cn, ok to cover int wall as noted
|
INSP - Framing/Rough-in | 2/3/1999 | 2/3/1999 | 2/3/1999 | | FAIL |
Carl Dependahl
|
|
|
/ / 340 - part, 2nd cn, need fix at west wall, plate missed at trusss, walls as noted
|
INSP - Framing/Rough-in | 2/3/1999 | 2/3/1999 | 2/3/1999 | P | FAIL |
Carl Dependahl
|
|
|
TY ###-####, part, dining, kitchen only, c/n; has plbg c/n
|
INSP - Framing/Rough-in | 2/2/1999 | 2/2/1999 | 2/2/1999 | P | FAIL |
Carl Dependahl
|
|
|
###-#### Ty c/n
|
INSP - Framing/Rough-in | 2/2/1999 | 2/2/1999 | 2/2/1999 | | FAIL |
Carl Dependahl
|
|
|
/ / 340 - ext walls ...c/n , need fireblocks, detail shear panels ( en
|
INSP - Framing/Rough-in | 2/1/1999 | 2/1/1999 | 2/1/1999 | P | FAIL |
Carl Dependahl
|
|
|
02/01/99 340 - TY ###-#### COVER INSP fail, has plbg c/n
|
INSP - Framing/Rough-in | 1/29/1999 | 1/29/1999 | 1/29/1999 | P | FAIL |
Russ Owen
|
|
|
01/29/99 407 - need other inspections before a structural.
|
INSP - Framing/Rough-in | 1/21/1999 | 1/21/1999 | 1/21/1999 | P | PART |
|
|
|
ty- ###-#### fr insp-sheathing for roof & ex siding & hold downs need to tighten down the nuts on the east side shear panel.
|
INSP - Framing/Rough-in | 12/15/1998 | 12/15/1998 | 12/15/1998 | P | PART |
|
|
|
12/15/98 338 - ok to pour only signed off areas c/n in force need compac
|
INSP - Foundation | 12/10/1998 | 12/11/1998 | 12/11/1998 | A | FAIL |
|
|
|
12/11/98 338 - not ready organics in the pour area
|
Issue PAID IN FULL permit | | | 12/3/1998 | | |
|
|
|
|
Print Occupancy Form | | | 12/3/1998 | | |
|
|
|
|
Inspection Record Card- Bld | | | 12/3/1998 | | |
|
|
|
|
CHANGE STATUS TO (R) | | | 11/23/1998 | | PASS |
|
|
|
|
Issue PAID IN FULL permit | | | 10/23/1998 | | |
|
|
|
|
Print Occupancy Form | | | 10/16/1998 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/16/1998 | | |
|
|
|
|
Telephone call | | | 10/16/1998 | | |
|
|
|
CALLED PAT..NEED ACHD APPROVAL AND CALCS..DF
|
Telephone call | | | 10/16/1998 | | |
|
|
|
CALLED TALKED TO CAMILLA GAVE NEW DOLLAR AMOUNT FOR B.K.-P.W.S CHANGED FEES
|
Routing - PLAN CHECK | 10/14/1998 | | 10/15/1998 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/15/1998 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/15/1998 | | PASS |
|
|
|
|
Plan assigned to (JML) | 7/23/1998 | | 10/15/1998 | | PASS |
|
|
|
|
Routing - PLANNING | 10/14/1998 | | 10/14/1998 | | PASS |
|
|
|
APPROVED PER DRH98-0112.
|
Routing - PLANNING | 9/28/1998 | | 10/7/1998 | | PASS |
|
|
|
Site plan now includes more land to south and has parking on east side. There is a residential use next to east property line. Need fencing between service drive and residential use as per Boise City Zoning Ordinance 11-10-04.4.F.2. Need to indicate location of bike rack on site plan.
|
Routing - PLAN CHECK | 10/7/1998 | | 10/7/1998 | | PEND |
|
|
|
sent to John L
|
Routing - PLUMBING | 9/25/1998 | | 9/28/1998 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 9/28/1998 | | 9/28/1998 | | PEND |
|
|
|
NEEDS P&Z APPROVAL
|
Plan resubmittals received | | | 9/25/1998 | | PEND |
|
|
|
RECEIVED RESUBMITTALS FOR PLUMBING, FORWARDED SAME TO BILL VANDEGRIFT.
|
Routing - PLAN CHECK | 9/25/1998 | | 9/25/1998 | | |
|
|
|
|
Routing - PLUMBING | 9/24/1998 | | 9/24/1998 | | FAIL |
|
|
|
|
Plan resubmittals received | | | 9/24/1998 | | |
|
|
|
RECEIVED 2 COPIES OF REVISED SHEETS A12C AND A12D AND S-3 ROUTED TO JOHN LEVIEN.
|
Routing - PUBLIC WORKS | 9/22/1998 | | 9/23/1998 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 9/23/1998 | | 9/23/1998 | | |
|
|
|
|
Routing - FIRE | 9/21/1998 | | 9/22/1998 | | PASS |
|
|
|
second exit from each room provided
|
Telephone call | | | 9/18/1998 | | FAIL |
|
|
|
The response to the structural questions adaquately addressed them but they need to be in blueprint form. Trenton of Architects' office was informed of such. Non-structural issues are approved.
|
Plan resubmittals received | | | 9/16/1998 | | |
|
|
|
RECEIVED RESUBS AND TAKEN TO FLOYD V.
|
Routing - PLAN CHECK | 9/8/1998 | | 9/8/1998 | | PEND |
|
|
|
|
Routing - PLUMBING | 9/8/1998 | | 9/8/1998 | | FAIL |
|
|
|
STILL WAITING ON REVISIONS PER BILL V.
|
Plan Review Completed(1st rev) | | | 9/4/1998 | | FAIL |
|
|
|
all agencies except CDH failed
|
Routing - FIRE | 9/3/1998 | | 9/4/1998 | | FAIL |
|
|
|
plans look like a mixture of different buildings... doors move around, seating arrangements change, etc
|
Routing - PLAN CHECK | 8/27/1998 | | 9/2/1998 | | FAIL |
|
|
|
I Sent my plan review findings to the architect by mail and fax. Needs resubmittals.
|
Routing - FIRE | 8/14/1998 | | 8/27/1998 | | CANC |
|
|
|
ubc plan review is required before UFC plan review
|
Routing - PLAN CHECK | 8/11/1998 | | 8/11/1998 | | |
|
|
|
RECEIVED
|
Routing - PLUMBING | 8/10/1998 | | 8/11/1998 | | FAIL |
|
|
|
|
Routing - PLANNING | 8/4/1998 | | 8/10/1998 | | FAIL |
|
|
|
plans do not comply with DRH98-0112 conditions of approval.
|
Routing - PUBLIC WORKS | 7/29/1998 | | 8/7/1998 | | FAIL |
|
|
|
A LIGHTING PLAN NEEDS TO BE SUBMITTED TO BILL COLSON.
|
Routing Off Site - C.D.H | 7/22/1998 | | 7/29/1998 | | PASS |
|
|
|
CONTACTED TRENTON JONES TO TAKE PLANS OUT TO CDH (###-####)
|
Plan assigned to (JCM) | 7/22/1998 | | 7/23/1998 | | PASS |
John Menard
|
|
|
|
Received Certificate of Value | | | 7/22/1998 | | PASS |
|
|
|
|
Application received | | | 7/22/1998 | | |
|
|
|
|
Routing Off Site - STRUCTURAL | 7/22/1998 | | 7/22/1998 | | |
|
|
|
WILL ASK JOHN ON 7-23-98 IF HE WOULD LIKE PLANS TO GO TO OUTSIDE ENG. NO OUTSIDE ENG. ENG. WILL BE DONE IN HOUSE
|
Plan routing begun/NEW & ADDTN | | | 7/22/1998 | | |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 7/22/1998 | | PEND |
|
|
|
CONTACTED PAT MCKEEGAN TO LET HIM KNOW THAT I NEED 1. 3 ADDITIONAL CIVIL SHEETS 2. 1 PACKATE #2 FOR OUTSIDE ENGINEERING. I WILL ROUTE TO CDH THEN PW, PLUMBING, P&Z, PC, AND FIRE RECEIVED ON 7-23-98 3 ADDITIONAL CIVIL SHEETS AND ONE PACKAGE #2 FOR OUT SIDE ENG. ROUTED TO CDH
|
Recd Pcfee & Taken To Pln CK | | | 7/22/1998 | | PEND |
|
|
|
|
Plan assigned to (MYS) | 7/22/1998 | | 7/22/1998 | | |
Marlene Southard
|
|
|
|