Permit Information
Permit NumberBLD98-02218
StatusFinaled
Name MIKE FERY
Site Address 2141 W AIRPORT WAY
Project NameAIRPORT BUSINESS CNT
Customer Number 
ePlanReviewNo
Description
AIRPORT BUSINESS CENTER (SHELL PERMIT) TO CONSTRUCT A NEW 24,000 SQ. FT, ONE STORY OFFICE/WAREHOUSE SHELL BUILDING. CONSTRUCTED OF CONCRETE TILT-UP EXTERIOR WALLS, CONCRETE SLAB FLOOR AND STEEL ROOF JOISTS WITH METAL ROOF DECK. THERE IS NO INTERIOR FINISH INCLUDED WITH THIS PERMIT. THIS IS SHELL PERMIT ONLY AND NO OCCUPANCY IS ALLOWED UNDER THIS PERMIT. A SEPARATE TENANT IMPROVEMENT PEMRIT IS REQUIRED TO FINISH EACH PROPOSED TENANT SPACE. THIS BUILDING WILL BE FULLY FIRE SPRINKLED. THE SPRINKLERS ARE BEING USED FOR ALLOWABLE AREA INCREASE. THIS PERMIT WILL ALSO INCLUDE RELATED SITE IMPROVEMENTS. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED REQUIREMENT LIST. DR98-110/PC#504-98/JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance  10/13/1999 DONE
Letter of Compliance #17923 issued 10-13-99.
BLD-Final9/29/19999/29/19999/30/1999PPASS
DetailsJim Storey
shell & core - airport bus. cntr.
INSP - Final4/28/19994/29/19994/29/1999PNR
DetailsJim Storey
04/29/99 301 - mech fees and achd sign off required.
INSP-Final Inspection4/29/19994/29/19994/29/1999APASS
DetailsRick Jackson
OCC APPROVED
Fee Review-notes1/15/1999 4/28/1999
Code Occupancy Approval  4/21/1999 PASS
ALL CONDITIONS OF DRH98-0110 HAVE NOW BEEN COMPLETED. FINAL OCCUPANCY SIGNED OFF AND RELEASE OF BOND.
Temporary occupancy  3/25/1999 PASS
Temp. Occ. Cert. #3800 issued 3-25-99 to the Airport Business Center.
INSP - Final3/10/19993/11/19993/11/1999PPART
DetailsJim Storey
03/11/99 301 - TCO -TEMP C OF O pending others ele fire p/z
INSP-Final Inspection3/10/19993/11/19993/11/1999APART
DetailsRick Jackson
harold ###-#### temp occ approved - paint curbing; knox box keys
INSP-Final Inspection3/5/19993/5/19993/5/1999PFAIL
DetailsRick Jackson
address; FACP latches supervisory tampers; alarms tested okay; knox box; fire lanes;
Code Occupancy Approval  3/5/1999 FAIL
SMALL PARKING LOT AND ALL LANDSCAPE NOT IN AS REQUIRED, ALSO THE BUILDING HAS NOT BEEN PAINTED, BOND POSTED FOR $43,193 TEMPORARY OCCUPANCY SIGNED OFF THIS DATE.
INSP-Final Inspection3/2/19993/3/19993/3/1999APART
DetailsRick Jackson
hydro static for underground\\###-#### john not a final inspection but underground hydro only - okay
INSP - Framing/Rough-in3/2/19993/2/19993/3/1999PPASS
DetailsJim Storey
03/02/99 301 - FRAM-OK FRAMING
Code Occupancy Approval  2/25/1999 FAIL
REQUEST FOR TEMPORARY OCCUPANCY, SITE INSPECTION SHOWED NO LANDSCAPE IN, NORTH PARKING LOT NOT IN, PARKING STRIPING NOT DONE, BUILDING NOT PAINTED, FAXED BID AMOUNT TO COMPLETE RECEIVED FOR $39267, I OKED THIS BOND AMOUNT WITH THE REQUIRED 10% THE TOTAL BOND AMOUNT IS FOR $43193, WHEN RECEIVED I WILL SIGN TEMP OCCUPANCY.
INSP - Framing/Rough-in2/10/19992/10/19992/10/1999PPASS
DetailsJim Storey
02/10/99 301 - FRAM-OK FRAMING
Plan resubmittals received  2/3/1999
RECEIVED TWO COPIES OF MECH. SHEETS M-1, M-2, AND M-3. ROUTED TO DAVID LIGHTFOOT. KMM
INSP - Framing/Rough-in12/1/199812/1/199812/10/1998PFAIL
DetailsJim Storey
12/01/98 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED special insp o
(F) Reprint permit  10/20/1998
Issue PAID IN FULL permit  10/19/1998
Telephone call  9/22/1998 PASS
talked to cornell at ###-#### that plans are ready
Telephone call  9/1/1998 PASS
TALKED TO CORNELL AT ###-#### THAT PLANS ARE READY
Inspection Record Card- Bld  9/1/1998
Print Occupancy Form  9/1/1998
PLANS/APPL TAKEN TO FRONT DESK  8/31/1998 PASS
Routing Off Site - STRUCTURAL8/19/1998 8/31/1998 PASS
SENT RESUBS TO CH2MHILL
Routing - PLAN CHECK8/27/1998 8/31/1998 PASS
Plan assigned to (JCM)7/24/1998 8/31/1998 PASS
DetailsJohn Menard
Plan Review Completed(1st rev)  8/27/1998 PASS
all ok
Routing - FIRE8/13/1998 8/27/1998 PASS
Plan resubmittals received  8/20/1998 PEND
RECEIVED RESUBMITTALS FROM CORNEL LARSON, FORWARDED SAME TO JOHN MENARD
Plan resubmittals received  8/19/1998 PEND
RECEIVED RESUBMITTALS FROM PINACLE ENGINEERS AND LARSON ARCHITECTS, FORWARDED SAME TO JOHN MENARD. DAR
Plan resubmittals requested  8/18/1998 PEND
STRUCTURAL COMMENT LIST FROM CH2MHILL WAS FAXED TO CORNELL LARSON REQUESTING REVISIONS.
Routing Off Site - STRUCTURAL7/24/1998 8/17/1998 PEND
CONTACTED PDQ TO TAKE PLANS OUT TO CH2MHILL RESUBMITTALS REQUESTED.
Plan Reviewer's activity  8/13/1998 PASS
PLANS REVIEWED AND APPROVED AS SUBMITTED.
Routing - PLUMBING8/11/1998 8/11/1998 PASS
Routing - PLANNING8/6/1998 8/10/1998 PASS
approved per DRH98-0110.
Routing - AIRPORT8/4/1998 8/6/1998 PASS
CALLED KEN OUT AT THE AIRPORT TO SEE IF HE WANSTS TO SEE PLANS. I LEFT A MESSAGE FOR HIM TO CALL ME. KMM SPOKE WITH KEN AT AIRPORT HE STATED HE WOULD LIKE TO SEE PLANS. I WILL ROUTE TO HIM AFTER PLANS ARE BACK FROM PW. KMM SENT PLANS VIA INTER-OFFICE MAIL. 8/5/98 DAR
Routing - PUBLIC WORKS7/24/1998 8/4/1998 PASS
Plan assigned to (MYS)7/23/1998 7/24/1998
DetailsMarlene Southard
Plan routing begun/NEW & ADDTN  7/24/1998
Plans ACCEPTED BY PLAN CHECK  7/24/1998 PASS
Received Certificate of Value  7/24/1998 PASS
Application received  7/23/1998
Recd Pcfee & Taken To Pln CK  7/23/1998 PEND