INSP - Final | 6/30/1999 | 7/1/1999 | 7/1/1999 | P | PASS |
Russ Owen
|
|
|
07/01/99 407 - tempered glass april ###-####
|
SUPER- Supervisor's review | 6/15/1999 | 6/15/1999 | 6/15/1999 | | PASS |
|
|
|
Received and approved letter from glazer.
|
DOC - L/C Approved | 6/15/1999 | 6/15/1999 | 6/15/1999 | | PASS |
Russ Owen
|
|
|
/ / 407 - 16810
|
INSP - Final | 6/15/1999 | 6/15/1999 | 6/15/1999 | P | PASS |
Russ Owen
|
|
|
06/15/99 407 - ###-####//FINAL
|
SUPER- Supervisor's review | 6/14/1999 | 6/14/1999 | 6/14/1999 | | PEND |
|
|
|
Handrail approved. Requested letter on glazing.
|
INSP - Final | 6/10/1999 | 6/11/1999 | 6/11/1999 | A | FAIL |
Russ Owen
|
|
|
06/11/99 407 - temp glass handrail.
|
INSP - Framing/Rough-in | 12/8/1998 | 12/8/1998 | 12/8/1998 | P | PASS |
Russ Owen
|
|
|
12/08/98 407 - PHIL ###-#### SHEAR WALL INSP-FOR SHEET ROCK
|
INSP - Framing/Rough-in | 12/3/1998 | 12/3/1998 | 12/3/1998 | P | PASS |
Russ Owen
|
|
|
12/04/98 407 - phil ###-#### re-insp fr insp
|
INSP - Framing/Rough-in | 12/1/1998 | 12/2/1998 | 12/2/1998 | A | PART |
Russ Owen
|
|
|
12/02/98 407 - just have a fire block needed at the chimney upper floor
|
INSP - Energy code compliance | 12/1/1998 | 12/2/1998 | 12/2/1998 | A | PASS |
Russ Owen
|
|
|
12/02/98 407 - phil ###-#### energy code insp
|
INSP - Framing/Rough-in | 11/25/1998 | 11/27/1998 | 11/27/1998 | P | FAIL |
Russ Owen
|
|
|
11/27/98 407 - left correcrtions.
|
INSP - Framing/Rough-in | 10/20/1998 | 10/20/1998 | 10/20/1998 | P | PART |
Jim Storey
|
|
|
10/20/98 301 - phil ###-#### shear wall carpentry insp sheer ok
|
INSP - Foundation | 9/2/1998 | 9/3/1998 | 9/3/1998 | A | PASS |
Jim Storey
|
|
|
09/03/98 301 - ###-#### donny footing FDN -OK FOUNDATION
|
INSP - Foundation | 9/1/1998 | 9/1/1998 | 9/1/1998 | | PASS |
Jim Storey
|
|
|
09/01/98 301 - footing donnie ###-#### FTG -OK FOOTING
|
Issue PAID IN FULL permit | | | 8/25/1998 | | |
|
|
|
|
Telephone call | | | 8/20/1998 | | PASS |
|
|
|
called harris to let them know the permit is ready
|
Plan Reviewer's activity | | | 8/13/1998 | | PASS |
|
|
|
SPECED OUT (3) 2 X 8 OR EQUIV. FOR TYP. HDR.
|
Inspection Record Card- Bld | | | 8/13/1998 | | |
|
|
|
|
Telephone call | | | 8/13/1998 | | |
|
|
|
CALLED HARRIS PERMIT READY
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/13/1998 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 8/13/1998 | | PASS |
|
|
|
|
Plan assigned to (DJO) | 8/13/1998 | | 8/13/1998 | | PASS |
Dan Overy
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 8/12/1998 | | PEND |
|
|
|
NEED ADDITIONAL INFORMATION ON HEADER/BEAM SIZES.
|
Routing - PLANNING | 7/28/1998 | | 7/29/1998 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 7/28/1998 | | 7/28/1998 | | PASS |
|
|
|
|
Application received | | | 7/27/1998 | | |
|
|
|
|
Routing - PLAN CHECK | 7/29/1998 | | | | PEND |
|
|
|
|