Print Pending Permit.LaserJet4 | | | 11/4/1999 | | DONE |
|
|
|
|
INSP - Final | 2/8/1999 | 2/9/1999 | 2/9/1999 | A | PASS |
Jim Storey
|
|
|
02/09/99 301 - FNL -OK FINAL
|
INSP - Final | 2/5/1999 | 2/8/1999 | 2/8/1999 | A | FAIL |
Jim Storey
|
|
|
02/08/99 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Framing/Rough-in | 1/6/1999 | 1/6/1999 | 1/6/1999 | P | PASS |
Jim Storey
|
|
|
01/06/99 301 - FRAM-OK FRAMING
|
INSP - Framing/Rough-in | 12/30/1998 | 12/30/1998 | 12/30/1998 | P | FAIL |
Jim Storey
|
|
|
12/30/98 301 - joist repair and fire stopping required under stairs.
|
INSP - Framing/Rough-in | 12/28/1998 | 12/29/1998 | 12/30/1998 | A | FAIL |
Jim Storey
|
|
|
12/30/98 301 - JEFF ###-####
|
INSP - Energy code compliance | 12/28/1998 | 12/29/1998 | 12/30/1998 | A | FAIL |
Jim Storey
|
|
|
12/30/98 301 - JEFF ###-####
|
INSP - Framing/Rough-in | 12/23/1998 | 12/23/1998 | 12/23/1998 | P | PART |
Jim Storey
|
|
|
12/23/98 301 - JEFF ###-#### REINSPECT
|
INSP - Framing/Rough-in | 12/21/1998 | 12/22/1998 | 12/22/1998 | A | CANC |
Russ Owen
|
|
|
12/22/98 407 - TRANS TO 301.
|
INSP - Framing/Rough-in | 12/17/1998 | 12/18/1998 | 12/18/1998 | A | FAIL |
Jim Storey
|
|
|
12/18/98 301 - REINSP...JEFF..###-####
|
INSP - Framing/Rough-in | 12/11/1998 | 12/14/1998 | 12/14/1998 | A | FAIL |
Jim Storey
|
|
|
12/14/98 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Foundation | 10/28/1998 | 10/28/1998 | 10/28/1998 | P | PART |
Jim Storey
|
|
|
10/28/98 301 - footing ok need compaction report
|
INSP - Foundation | 10/12/1998 | 10/12/1998 | 10/12/1998 | P | FAIL |
Jim Storey
|
|
|
10/12/98 301 - jerry ###-#### for ft insp CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
Inspection Record Card- Bld | | | 10/8/1998 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 10/8/1998 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/7/1998 | | PASS |
|
|
|
|
Plan resubmittals received | | | 10/7/1998 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/7/1998 | | PASS |
|
|
|
|
Plan assigned to (M_P) | 8/14/1998 | | 10/7/1998 | | PASS |
Mike Phillips
|
|
|
10/07/98 15:34:04 M_P - this action updated by action script from <<>> in Case No. BLD98-2470
|
Plan resubmittals received | | | 10/6/1998 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 10/2/1998 | | FAIL |
|
|
|
|
Routing - FIRE | 9/24/1998 | | 9/24/1998 | | PASS |
|
|
|
Lot 50 approved for building by DS MILLER 9/18/98
|
Routing - PLANNING | 8/17/1998 | | 9/22/1998 | | PASS |
|
|
|
approved per DRH98-0137.
|
Office Staff conference/action | | | 8/17/1998 | | PEND |
|
|
|
PUT IN REJECT DRAWER/PER ROGER NEEDS MORE INFO
|
Routing - PUBLIC WORKS | 8/14/1998 | | 8/17/1998 | | PASS |
|
|
|
|
Application received | | | 8/14/1998 | | |
|
|
|
|