Letter of compliance | | | 8/12/1999 | | PASS |
|
|
|
Letter of Compliance #17892 issued 8-12-99.
|
INSP - Final | 7/22/1999 | 7/22/1999 | 7/22/1999 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - SHELL FOR WINCO OFFICE...LC ONLY
|
INSP - Final | 7/7/1999 | 7/7/1999 | 7/7/1999 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR CERT OF COMPLETION
|
INSP - Final | 6/22/1999 | 6/22/1999 | 6/22/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - FILED ENG'S STATEMENT, NEED HVAC
|
INSP - Final | 5/12/1999 | 5/12/1999 | 5/12/1999 | P | PART |
Carl Dependahl
|
|
|
05/12/99 340 - Scheduled by Hello!. Contact phone is [6585232]. shell, need hvac ok
|
Temporary occupancy | | | 5/12/1999 | | PASS |
|
|
|
Temp. Occ. Cert. #3833 issued 5-12-99 to Waremart, inc. for offices.
|
INSP - Framing/Rough-in | 5/11/1999 | 5/11/1999 | 5/11/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - REC'D ENGS' LETTER OF ACCEPTANCE; NEED FINAL W/BLD98-3351
|
Code Occupancy Approval | | | 4/30/1999 | | FAIL |
|
|
|
Still need to put up fencing. Replace plate at frt. entry door - to the east and restake Pine behind the dumpster enclosure.
|
INSP-Final Inspection | 4/28/1999 | 4/29/1999 | 4/29/1999 | P | NR |
Joe Tawney
|
|
|
FINAL NOT READY ALARM SUBMITTALS NOT YET APPROVED
|
Fee Review-notes | 1/27/1999 | | 4/28/1999 | | PASS |
|
|
|
subs short
|
Fee Review-notes | 10/27/1998 | | 4/28/1999 | | |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 4/13/1999 | 4/13/1999 | 4/13/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK RI AND PREACTION HYDRO TEST
|
INSP-Sprinkler Rough-in/Hydro | 4/13/1999 | 4/13/1999 | 4/13/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK RI AND PREACTION HYDRO TEST
|
INSP-Sprinkler Rough-in/Hydro | 4/13/1999 | 4/13/1999 | 4/13/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK RI AND PREACTION HYDRO TEST
|
INSP-Sprinkler Rough-in/Hydro | 4/6/1999 | 4/6/1999 | 4/6/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON ABOVE GROUND HYDRO, OK TO COVER OK ON ROUGH IN EX 3 IT
|
INSP - Framing/Rough-in | 3/31/1999 | 3/31/1999 | 3/31/1999 | | NR |
Carl Dependahl
|
|
|
/ / 340 - SHELL, NEED ALL REPORTS
|
INSP - Framing/Rough-in | 2/1/1999 | 2/2/1999 | 2/2/1999 | A | PART |
Carl Dependahl
|
|
|
02/02/99 340 - ROGER ###-#### ROOMS #40-#42, #1-#18, #62-#63, #43-#48; p permit, need verify spec insp (338?)
|
INSP - Framing/Rough-in | 1/28/1999 | 1/29/1999 | 1/29/1999 | A | NR |
Carl Dependahl
|
|
|
01/29/99 340 - ROGER ###-#### ROOMS #62,#63,#44,#45,#30-#38,AND #1-#11, left msg
|
INSP-Supply line flush | 1/7/1999 | 1/8/1999 | 1/8/1999 | A | PART |
Joe Tawney
|
|
|
01/08/99 406 - RANDY ###-#### -FLUSHING INSP- OK ON SUPPLY LINE FLUSH
|
INSP-Sprinkler Rough-in/Hydro | 1/7/1999 | 1/7/1999 | 1/7/1999 | P | PART |
Joe Tawney
|
|
|
01/07/99 406 - RANDY ###-#### UNGERGROUND SPRINKLER OK ON UNDERGROUND HYDRO TEST
|
INSP-Sprinkler Rough-in/Hydro | 1/4/1999 | 1/6/1999 | 1/6/1999 | A | CANC |
Joe Tawney
|
|
|
01/06/99 406 - randy -debest ###-####-underground flushing TEST CANCELLED TO BE RESCHEDULED
|
INSP - Framing/Rough-in | 12/22/1998 | 12/23/1998 | 12/23/1998 | A | PART |
|
|
|
12/23/98 338 - made ok to cover front canopy and inside of thr rear wall
|
INSP - Framing/Rough-in | 12/17/1998 | 12/18/1998 | 12/18/1998 | A | PART |
|
|
|
12/18/98 338 - roger davis- ###-#### fr insp-grid line e 1.4 to 4.8 for
|
INSP - Framing/Rough-in | 12/9/1998 | 12/9/1998 | 12/9/1998 | | PART |
|
|
|
12/09/98 338 - madeok for the submittals
|
INSP - Framing/Rough-in | 12/7/1998 | 12/7/1998 | 12/7/1998 | P | PART |
|
|
|
12/07/98 333 - ROGER ###-#### MASONRY GRIDLINE 5, A TO E. GRIDLINE 1, A GRIDLINE A, 1 TO 5 ok pend spec insp report
|
INSP - Framing/Rough-in | 12/3/1998 | 12/4/1998 | 12/4/1998 | A | PART |
|
|
|
12/04/98 338 - roger ###-#### masonry gridlines 5 and 1, A to E AND GRIDLINE A, 1 TO 5 ALSO WELDING CONFERENCE MADE OK TO COVER WITH SP INSP
|
INSP - Framing/Rough-in | 11/30/1998 | 12/1/1998 | 12/2/1998 | A | PART |
|
|
|
12/02/98 338 - CHRIS ###-#### MASONARY INSP-GRID LINE 5-BETWEEN A&E GRID 1-BETWEEN A & E, GRID A BETWEEN 1&5 made ok with sp insp approval.
|
INSP - Framing/Rough-in | 11/19/1998 | 11/20/1998 | 11/20/1998 | A | PART |
|
|
|
11/20/98 338 - ok with other agencies approval.
|
INSP - Wall cover | 11/19/1998 | 11/20/1998 | 11/20/1998 | A | PART |
|
|
|
11/20/98 338 - EXTERIOR WALL AND MASONRY..ROGER ###-####..GRID A TO E GRID 2 TO 3....GRID A TO C...GRID 3 TO 4..MASONRY IS GRID LINE 1 & 5...A TO E....COOL HUH?? madeok with sp insp approval.
|
INSP - Concrete | 11/17/1998 | 11/19/1998 | 11/19/1998 | A | PART |
|
|
|
11/19/98 338 - ROGER ###-#### SLAB CONCRETE ON GRIDLINES 4 TO 5, A TO E AND GRIDLINES 1 TO 2, A TO E made ok with sp inspand other agencies approval
|
INSP - Framing/Rough-in | 11/17/1998 | 11/18/1998 | 11/19/1998 | A | PART |
|
|
|
11/19/98 338 - ROGER ###-#### MASONRY ON GRIDLINE 5, A TO E made ok with
|
INSP - Framing/Rough-in | 11/18/1998 | 11/18/1998 | 11/18/1998 | | PART |
|
|
|
11/18/98 338 - made ok with sp insp approval
|
INSP - Concrete | 11/3/1998 | 11/3/1998 | 11/3/1998 | P | PART |
|
|
|
11/03/98 338 - ROGER ###-#### GRID LINES 3 TO 4 GRID LINES C.5 TO E made
|
INSP - Foundation | 10/29/1998 | 10/30/1998 | 10/30/1998 | A | PART |
|
|
|
10/30/98 338 - roger ###-#### stem wall GRID E/TWO TO FIVE, GRID FIVE/D TO E made ok to pour with the sp inspection approval
|
INSP - Foundation | 10/29/1998 | 10/29/1998 | 10/29/1998 | P | PART |
|
|
|
10/29/98 338 - ith sp insp approval
|
INSP - Foundation | 10/28/1998 | 10/28/1998 | 10/28/1998 | | PART |
|
|
|
10/28/98 338 - ROGER ###-#### FOOTING GRID 2/B,C,D GRID3/B,C GRID 4/B,Cmade ok to pour with sp insp approval
|
INSP - Foundation | 10/26/1998 | 10/27/1998 | 10/27/1998 | A | PART |
|
|
|
10/27/98 338 - ROGER ###-####-FT INSP-GRID LINE E-1-5-GRID LINE 1-C-E-STEM WALLS-GR LN A-1-5-GR-1&5-A TO C made ok with sp insp approval
|
INSP - Foundation | 10/23/1998 | 10/26/1998 | 10/26/1998 | A | PART |
|
|
|
10/26/98 338 - roger ###-#### gridline A between 1 and 5, gridline 5 between A and D, stemwall
|
INSP - Foundation | 10/20/1998 | 10/21/1998 | 10/21/1998 | P | PART |
|
|
|
10/21/98 338 - made ok for footing pour, bob arnold eisi on site for spe
|
(F) Reprint permit | | | 10/9/1998 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 10/8/1998 | | |
|
|
|
|
Telephone call | | | 10/7/1998 | | PASS |
|
|
|
TALKED TO RHONDA-TOLD HER WE NEED ACHD APPROVAL 1ST BE ISSUING
|
Routing - PLAN CHECK | 9/15/1998 | | 10/2/1998 | | PASS |
|
|
|
|
Plan resubmittals received | | | 10/2/1998 | | PASS |
|
|
|
STRUCTURAL REVIEW LETTER BY CH2M HILL
|
Print Occupancy Form | | | 10/2/1998 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/2/1998 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/2/1998 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 9/25/1998 | | 10/2/1998 | | PASS |
|
|
|
|
Plan assigned to (JCM) | 8/17/1998 | | 10/2/1998 | | PASS |
John Menard
|
|
|
|
Plan resubmittals received | | | 9/24/1998 | | PEND |
|
|
|
|
Plan resubmittals received | | | 9/24/1998 | | |
|
|
|
RECEIVED 3 COPIES OF REVISED STRUCTURAL DRAWINGS S2.1, S2.2, AND S3.0. THREE COPIES OF REVISED STRUCTURAL CALCS. THREE COPIES OF ARCH. DRAWIGNS A5.0, A5.1, AND A-6. ONE COPY OF SOILS REPORT. ROUTED TO JOHN M.
|
Plan Review Completed(1st rev) | | | 9/15/1998 | | PASS |
|
|
|
|
Routing - FIRE | 9/10/1998 | | 9/15/1998 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 9/10/1998 | | PEND |
|
|
|
MAILED DOUG RACINE A COPY OF THE COMMENT LIST REQUESTING REVISIONS.
|
Routing Off Site - STRUCTURAL | 8/17/1998 | | 9/10/1998 | | |
|
|
|
CONTACTED PDQ TO TAKE PLANS OUT TO CH2MHILL
|
Routing - PLANNING | 9/2/1998 | | 9/8/1998 | | PASS |
|
|
|
PER DRH98-0129 AND CUP98-83
|
Received Certificate of Value | | | 9/4/1998 | | PASS |
|
|
|
REVISED CERT. OF VALUE MINUS GRADING VALUE
|
Routing - PLAN CHECK | 8/31/1998 | | 9/2/1998 | | |
|
|
|
|
Routing - PLANNING | 8/26/1998 | | 8/27/1998 | | PEND |
|
|
|
Design Review approved per DRH98-0129. Plans must also be approved by conditional use analyst.
|
Routing - PLUMBING | 8/25/1998 | | 8/25/1998 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 8/17/1998 | | 8/25/1998 | | PASS |
|
|
|
|
Received Certificate of Value | | | 8/18/1998 | | PASS |
|
|
|
RECEIVED CERTIFICATE OF VALUE, FILLED IN PROPERLY AND SIGNED. DAR
|
Plan routing begun/NEW & ADDTN | | | 8/17/1998 | | |
|
|
|
|
Plan assigned to (MYS) | 8/14/1998 | | 8/17/1998 | | |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/17/1998 | | PASS |
|
|
|
REQUIRES SOILS REPORT. RECEIVED SOILS REPORT 8/18/98
|
Received Certificate of Value | | | 8/17/1998 | | FAIL |
|
|
|
REQUIRES ELEC. PLUMB. MECH. AND FIRE SPRINKLER VALUES TO BE FILLED OUT BEFORE ISSUANCE. CONTACTED STEVE PARDEW AND TOLD HIM OF THIS NEED. KMM
|
Recd Pcfee & Taken To Pln CK | | | 8/14/1998 | | |
|
|
|
|
Application received | | | 8/14/1998 | | |
|
|
|
|