INSP - Final | 2/12/1999 | 2/12/1999 | 2/12/1999 | P | PASS |
Alan Hauser
|
|
|
02/12/99 350 - reinspect ###-#### Ernest
|
INSP - Final | 1/26/1999 | 1/28/1999 | 1/28/1999 | P | FAIL |
Alan Hauser
|
|
|
01/28/99 350 - corrections posted
|
INSP - Energy code compliance | 10/6/1998 | 10/6/1998 | 10/6/1998 | | PASS |
Jim Sly
|
|
|
/ / 316 -
|
INSP - Framing/Rough-in | 10/2/1998 | 10/5/1998 | 10/5/1998 | A | PASS |
Jim Sly
|
|
|
10/05/98 316 - ERNIE ###-#### R/I AND ENERGY CODE
|
INSP - Framing/Rough-in | 9/30/1998 | 10/1/1998 | 10/5/1998 | P | FAIL |
Jim Sly
|
|
|
10/05/98 316 - C/N...Need elect appr....
|
INSP - Framing/Rough-in | 10/1/1998 | 10/1/1998 | 10/1/1998 | | FAIL |
Jim Sly
|
|
|
10/01/98 316 - C/N....Truss bracing...
|
INSP - Framing/Rough-in | 9/21/1998 | 9/21/1998 | 9/21/1998 | P | PART |
Jim Sly
|
|
|
09/21/98 316 - SHEAR NAIL OK per red line plan...Note to builder..OK per
|
INSP - Foundation | 9/8/1998 | 9/9/1998 | 9/9/1998 | A | PASS |
Jim Sly
|
|
|
09/09/98 316 - OK
|
Issue PAID IN FULL permit | | | 9/8/1998 | | |
|
|
|
|
Inspection Record Card- Bld | | | 9/3/1998 | | |
|
|
|
|
Telephone call | | | 9/3/1998 | | PASS |
|
|
|
talked to carol at ###-#### that plans are ready
|
Plan assigned to (ADS) | 8/31/1998 | | 9/2/1998 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/2/1998 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 9/2/1998 | | |
|
|
|
|
Routing - PLAN CHECK | 8/18/1998 | | 9/2/1998 | | PASS |
|
|
|
|
Plan assigned to (DJO) | 8/17/1998 | | 8/31/1998 | | PEND |
Dan Overy
|
|
|
|
INSP - Foundation | 8/26/1998 | 8/27/1998 | 8/27/1998 | A | FAIL |
Jim Sly
|
|
|
08/27/98 316 - Footing width, soil height, OK..setbks appear OK...No app
|
Print Pending Permit.LaserJet4 | | | 8/19/1998 | | |
|
|
|
|
Routing - PLANNING | 8/18/1998 | | 8/18/1998 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 8/17/1998 | | 8/18/1998 | | PASS |
|
|
|
|
Application received | | | 8/17/1998 | | |
|
|
|
|