HENDERSON CORPORATION WAREHOUSE BUILDING * TO CONSTRUCT A NEW 3750 SQUARE FOOT BUILDING (50' X 75'), ONE STORY, PRE-ENGINEERED STEEL WAREHOUSE BUILDING AND SITE IMPROVEMENTS. ALL CONSTRUCTION PER APPROVED PLANS AND ATTACHED REQUIREMENT LIST. A SEPARATE REVIEW AND PERMIT WILL BE REQUIRED BEFORE CONSTRUCTION OF THE PROPOSED FUTURE TOILET ROOM. PC#588-98/JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Receive PAYMENT IN FULL  6/7/1999
Fee Review-notes10/27/1998 4/28/1999 DONE
from subs
INSP-Final Inspection12/2/199812/3/199812/3/1998APASS
DetailsRick Jackson
12/03/98 409 - KIRK...###-####
INSP - Foundation10/19/199810/20/199810/20/1998APASS
DetailsJim Storey
10/20/98 301 - kurt ###-#### for fd insp FDN -OK FOUNDATION
INSP - Foundation10/13/199810/14/199810/14/1998APART
DetailsRuss Owen
10/14/98 407 - left correction pour at own risk subject to engineer appr
INSP - Foundation10/12/199810/13/199810/13/1998PNR
DetailsRuss Owen
10/13/98 407 - not ready.713 ì
(F) Reprint permit  10/7/1998
Issue PAID IN FULL permit  10/6/1998
Telephone call  10/2/1998 PASS
TALKED TO PAT AT ###-####
PLANS/APPL TAKEN TO FRONT DESK  10/1/1998 PASS
Print Occupancy Form  10/1/1998
Inspection Record Card- Bld  10/1/1998
Routing - PLAN CHECK9/25/1998 10/1/1998 PASS
Plan assigned to (JCM)8/20/1998 10/1/1998 PASS
DetailsJohn Menard
Plan resubmittals received  9/30/1998 PASS
Routing - PUBLIC WORKS9/23/1998 9/25/1998 PASS
Routing - PLAN CHECK9/16/1998 9/23/1998 PEND
Plan Review Completed(1st rev)  9/15/1998 FAIL
public works
Routing - FIRE9/14/1998 9/15/1998 PASS
Plan resubmittals requested  9/14/1998 PEND
MAILED JIM GLANCEY A COPY OF THE COMMENT LIST REQUESTING REVISIONS.
Routing - PLANNING9/10/1998 9/10/1998 PASS
See telephone call under actions.
Telephone call  9/9/1998
Discussed project with Jim Glancey's office and found out that a the parking area had already been constructed under a previous building permit, so DR-100-96 would still be valid.
Routing - PLUMBING9/8/1998 9/9/1998 PASS
Routing - PLANNING9/3/1998 9/8/1998 FAIL
The design review application (DR-100-96) has expired. The applicant will need to resubmit for staff level review.
Routing - PUBLIC WORKS8/25/1998 9/3/1998 FAIL
REQUIRES NEW DRAINAGE PLAN. BM
Plans ACCEPTED BY PLAN TECH  8/31/1998 PASS
received letter stating soils bearing
Plan routing begun/NEW & ADDTN  8/26/1998
Plans ACCEPTED BY PLAN TECH  8/25/1998 PEND
CONTACTED KIRK REILLY TO LET HIM KNOW THAT A SOILS REPORT IS REQUIRED. HE WILL HAVE A LETTER BY ENG. FAXED OVER STATING WAS DESIGNED UNDER 1500 PSF.
Received Certificate of Value  8/25/1998 PASS
Plan assigned to (MYS)8/17/1998 8/20/1998
DetailsMarlene Southard
Application received  8/17/1998
Recd Pcfee & Taken To Pln CK  8/17/1998