Case Summary (BLD) | | | 5/22/2003 | | |
|
|
|
|
Letter of compliance | | | 8/6/1999 | | PASS |
|
|
|
Letter of Compliance #17890 issued 8-6-99.
|
INSP-Final Inspection | 8/4/1999 | 8/5/1999 | 8/5/1999 | P | PASS |
Joe Tawney
|
|
|
08/05/99 406 - FINAL OK FOR CERT OF COMPLETION ON SHELL
|
INSP - Final | 8/4/1999 | 8/5/1999 | 8/5/1999 | P | PASS |
Carl Dependahl
|
|
|
08/05/99 340 - shell ok for l/c Scheduled by Hello!. Contact phone is [
|
PLACE HOLD ON JOB | | 12/24/1998 | 7/21/1999 | | |
|
|
|
HARDY PLM PAST DUE
|
Code Occupancy Approval | | | 7/21/1999 | | PASS |
|
|
|
Meets compliance with Design Review- PASS
|
INSP-Sprinkler Rough-in/Hydro | 12/14/1998 | 12/14/1998 | 12/14/1998 | P | CANC |
Joe Tawney
|
|
|
12/14/98 406 - RICH ###-#### CANCEL UNDERGROUND INSP NOT REQ UNTIL 1/1/99 ì
|
INSP - Foundation | 12/1/1998 | 12/1/1998 | 12/2/1998 | P | PART |
|
|
|
12/02/98 338 - madeok with sp insp approval
|
(F) Reprint permit | | | 11/4/1998 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 11/2/1998 | | |
|
|
|
|
Print Occupancy Form | | | 10/14/1998 | | |
|
|
|
|
Telephone call | | | 10/14/1998 | | FAIL |
|
|
|
DO NOT ISSUE UNTIL GARY ISENMAN OKAYS FEES BEEN PAID/MPS
|
Inspection Record Card- Bld | | | 10/14/1998 | | |
|
|
|
|
Plan assigned to (JCM) | 8/24/1998 | | 10/13/1998 | | PASS |
John Menard
|
|
|
|
Routing - PLAN CHECK | 10/9/1998 | | 10/13/1998 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/13/1998 | | PASS |
|
|
|
|
Plan resubmittals received | | | 10/13/1998 | | PASS |
|
|
|
RECEIVED REQUESTED REVISED A-1 PLAN SHEETS.
|
Routing - PLUMBING | 10/7/1998 | | 10/8/1998 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 10/8/1998 | | PEND |
|
|
|
TALKED TO PAT AT STEED CONSTRUCTION AND REQUESTED (3) ADDITIONAL A-1 PLAN SHEETS SHOWING ALL REQUIRED REVISIONS
|
Plan resubmittals received | | | 10/8/1998 | | |
|
|
|
RECEIVED 2 COPIES OF REVISED SHEETS A-1, A-3, CIVIL SHEETS. ROUTED TO JOHN M. KMM
|
Plan Reviewer's activity | | | 10/7/1998 | | PASS |
|
|
|
RESUBMITALS APPROVED WITH RED LINED NOTES.
|
Routing - FIRE | 10/6/1998 | | 10/7/1998 | | PASS |
|
|
|
not sprinklered, new hydrant required see A1
|
Routing - PLAN CHECK | 10/7/1998 | | 10/7/1998 | | |
|
|
|
|
Routing - PLAN CHECK | 10/2/1998 | | 10/6/1998 | | |
|
|
|
|
Routing - PLANNING | 10/2/1998 | | 10/2/1998 | | PASS |
|
|
|
x-ref. DRH98-0084 and 0164. Approved per revised plans dated received 9/17/98.
|
Plan resubmittals received | | | 10/2/1998 | | PASS |
|
|
|
THE FOLLOWING WAS RECEIVED REVISED SO.O SHOWING 2500 PSF ALLOWABLE SOIL PRESSURE BASED ON THE SOIL REPORT PLEASE NOTE THAT ALL ORIGINAL CALCULATIONS ARE BASED ON 2500 PSF ALLOWABLE SOIL BEARING PRESSURE. S2.0 DETAILS 7/S430 AND 19/S4.0, S1.0. BOTH CONDITION EXIST REVISED S2.0, ATTACHED CALCS.
|
Routing - PUBLIC WORKS | 9/28/1998 | | 10/2/1998 | | PASS |
|
|
|
|
Routing - PLUMBING | 10/2/1998 | | 10/2/1998 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 9/9/1998 | | 9/28/1998 | | |
|
|
|
|
Plan resubmittals received | | | 9/22/1998 | | PEND |
|
|
|
RECEIVED RESUBMITTALS FROM GORDON McDONALD, FORWARDED SAME TO JOHN MENARD.
|
Plan resubmittals requested | | | 9/16/1998 | | PEND |
|
|
|
FAXED GORDON MCDONALD A COPY OF THE COMMENT LIST FROM THE CONSULTING ENGINEER REQUESTING REVISIONS.
|
Routing Off Site - STRUCTURAL | 8/25/1998 | | 9/16/1998 | | |
|
|
|
CONTACTED PDQ TO TAKE PLANS OUT TO CH2MHILL FOR OUTSIDE ENG.
|
Plan resubmittals received | | | 9/14/1998 | | PEND |
|
|
|
RECEIVED RESUBMITALS FROM HABITEC, FORWARDED SAME TO JOHN MENARD. SENT TWO PAPERS TO FLOYD VARLEY.
|
Plan Review Completed(1st rev) | | | 9/9/1998 | | FAIL |
|
|
|
all agencies fail
|
Routing - FIRE | 9/8/1998 | | 9/9/1998 | | FAIL |
|
|
|
need hydrant
|
Plan resubmittals requested | | | 9/8/1998 | | PEND |
|
|
|
MAILED GORDON MCDONALD A LETTER REQUESTING CLARIFICATION ON PROPOSED OCCUPANCY GROUPS AND SPRINKLER SYSTEM.
|
Routing - PLAN CHECK | 9/2/1998 | | 9/8/1998 | | PEND |
|
|
|
|
Routing - PLUMBING | 9/1/1998 | | 9/2/1998 | | FAIL |
|
|
|
|
Routing - PUBLIC WORKS | 8/26/1998 | | 9/1/1998 | | FAIL |
|
|
|
REQUIRES SEWER PLAN BE SUBMITTED FOR PUBLIC LINE. JJ REQUIRES DRAINAGE PLAN REVISION.BM
|
Routing - PLANNING | 8/25/1998 | | 8/26/1998 | | FAIL |
|
|
|
need to do modification to DRH98-0084
|
Plan routing begun/NEW & ADDTN | | | 8/25/1998 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/25/1998 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 8/17/1998 | | 8/25/1998 | | |
Marlene Southard
|
|
|
|
Received Certificate of Value | | | 8/17/1998 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/17/1998 | | |
|
|
|
|
Application received | | | 8/17/1998 | | |
|
|
|
|