Receive PAYMENT IN FULL | | | 11/17/1999 | | DONE |
|
|
|
|
Fee Review-notes | 9/18/1998 | | 4/23/1999 | | DONE |
|
|
|
ADDITIONAL VALUES FROM SUB
|
INSP-Final Inspection | 4/5/1999 | 4/6/1999 | 4/6/1999 | P | PASS |
Rick Jackson
|
|
|
###-#### occ approved
|
Letter of compliance | | | 4/6/1999 | | PASS |
|
|
|
Letter of Compliance #16546 issued 4-6-99.
|
INSP-Final Inspection | 3/3/1999 | 3/5/1999 | 3/5/1999 | P | FAIL |
Rick Jackson
|
|
|
###-#### Dick call before going reschedule from 3/04 strobe not right cd; t-tapped wiring
|
INSP-Conference | 1/13/1999 | 1/13/1999 | 1/13/1999 | A | PART |
Rick Jackson
|
|
|
told contractor (Dick) to complete alarm notification circuits as shown on plans
|
INSP-Final Inspection | 1/11/1999 | 1/11/1999 | 1/11/1999 | A | FAIL |
Rick Jackson
|
|
|
alarms not complete; recheck dampers
|
INSP - Final | 1/8/1999 | 1/8/1999 | 1/8/1999 | P | PASS |
|
|
|
01/08/99 333 - fianll ok
|
INSP-Final Inspection | 1/8/1999 | 1/8/1999 | 1/8/1999 | P | PASS |
|
|
|
01/08/99 333 - ffinal ik
|
INSP - Framing/Rough-in | 10/19/1998 | 10/19/1998 | 10/19/1998 | A | PASS |
|
|
|
10/19/98 333 - 1ST FLOOR--DICK ###-#### FRAM-OK FRAMING
|
INSP - Framing/Rough-in | 10/16/1998 | 10/19/1998 | 10/19/1998 | A | CANC |
Dave Lightfoot
|
|
|
10/19/98 337 - dick ###-#### fr insp
|
Issue PAID IN FULL permit | | | 10/2/1998 | | |
|
|
|
|
Plan assigned to (DRS) | 8/21/1998 | | 10/1/1998 | | PASS |
Dan Stuart
|
|
|
|
Print Occupancy Form | | | 10/1/1998 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/1/1998 | | |
|
|
|
|
Telephone call | | | 10/1/1998 | | |
|
|
|
called talked to bob smith ###-#### gave dollar amount
|
Print Pending Permit.LaserJet4 | | | 10/1/1998 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/1/1998 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 9/22/1998 | | 10/1/1998 | | PASS |
|
|
|
|
Routing - FIRE | 9/29/1998 | | 9/30/1998 | | PASS |
|
|
|
alarm system requires plans - not in compliance on bld set
|
Plan resubmittals received | | | 9/28/1998 | | PASS |
|
|
|
Received response from architect, Bob Smith. Reviewed comments & plans with him at city office. Smoke detection & alarm system to comply with Fire Department regulations. Mr.Smith met with Floyd Varley to review plan deficiencies noted on F.D. plan review. Routing plans back to F. D. for second review.
|
Meeting | | | 9/28/1998 | | |
|
|
|
Met with Bob Smith, Architect to review his response to plan review and his field analysis.
|
Routing - FIRE | 9/17/1998 | | 9/22/1998 | | FAIL |
|
|
|
|
Plan Review Completed(1st rev) | | | 9/22/1998 | | FAIL |
|
|
|
UBC & UFC issues
|
Plan resubmittals requested | | | 9/17/1998 | | PEND |
|
|
|
Faxed and mailed preliminary plan review comments to architect for response prior to issuance of permit. Forwarding plan to Fire Dept for their review and approval.
|
Print permit w/o conditions | | | 9/17/1998 | | PEND |
|
|
|
|
Routing - PLAN CHECK | 9/16/1998 | | 9/17/1998 | | PEND |
|
|
|
Plans sent to Fire Dept. while waiting for architects response.
|
Routing - PLAN CHECK | 8/21/1998 | | 9/16/1998 | | |
|
|
|
Started plan review. Resubmittals required.
|
Plan routing begun/TENANTS | | | 8/21/1998 | | |
|
|
|
Route to PLAN CHECK and FIRE.
|
Plan assigned to (MYS) | 8/19/1998 | | 8/21/1998 | | |
Marlene Southard
|
|
|
|
Application received | | | 8/19/1998 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/19/1998 | | |
|
|
|
|
CHANGE STATUS TO (F) | | | | | |
|
|
|
|