Permit Information
Permit NumberBLD98-02529
StatusFinaled
Name BOISE CITY
Site Address 3754 ORCHARD
Project NameBOI T HANGAR B
Customer Number 
ePlanReviewNo
Description
T-HANGAR DEVELOPMENT (HANGAR "B") * TO CONSTRUCT A NEW 11,500 SQUARE FOOT, ONE STORY, 10 BAY AIRCRAFT HANGAR AND RELATED SITE IMPROVEMENTS. CONSTRUCTED OF A PRE-ENGINEERED METAL BUILDING ON A CONCRETE FOUNDATION. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED REQUIREMENT LIST. PC#574-98/JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes9/18/1998 1/20/1999 OK
Permanent occupancy  1/20/1999 PASS
Perm. Occ. Cert. #7595 issued 1-20-99 to Boise City Hangar B.
INSP-Final Inspection1/19/19991/19/19991/19/1999PPASS
DetailsJoe Tawney
01/19/99 406 - jack ###-#### FINAL OK FOR PERM OCC ì
INSP - Final1/19/19991/19/19991/19/1999PPASS
DetailsJim Storey
01/19/99 301 - FNL -OK FINAL card left on site.
Permanent Occupancy 1/19/19991/19/1999 DONE
Details
Code Occupancy Approval  1/19/1999 PASS
SITE INSPECTION SHOWED ALL P&Z REQUIREMENTS COMPLETED FOR THIS HANGER, FINAL OCCUPANCY SIGNED OFF.
INSP - Foundation10/20/199810/21/199810/21/1998APART
DetailsJim Storey
10/21/98 301 - JACK ###-#### colum steel on first bld ok, third bldg footings steel ok special insp. on site pending report.
(F) Reprint permit  10/15/1998
(F) Reprint permit  10/9/1998
Issue PAID IN FULL permit  10/8/1998
Telephone call  10/8/1998
called left message on machine
Plan assigned to (JCM)8/19/1998 10/7/1998 PASS
DetailsJohn Menard
Routing - PLAN CHECK10/7/1998 10/7/1998 PASS
Inspection Record Card- Bld  10/7/1998
Inspection Record Card- Bld  10/7/1998
Print Occupancy Form  10/7/1998
Print Occupancy Form  10/7/1998
PLANS/APPL TAKEN TO FRONT DESK  10/7/1998 PASS
Routing - FIRE10/5/1998 10/6/1998 PASS
changed to II-N
Plan resubmittals received  10/6/1998 PASS
received 4 copies of sheets 5 and 11
Routing - PLAN CHECK9/15/1998 10/5/1998
Plan resubmittals received  9/29/1998 PASS
received 4 t-hanger project sheet 2, grading, drainage and utility plan 1 t-hangar project sheet 5, floor plan 1 t-hangar project sheet 6, foundation plan 10-02-98 ROUTED TO JOHN M.
Routing Off Site - STRUCTURAL9/14/1998 9/22/1998 PASS
SENT RESUBS TO RILEY MAHAFFEY AT ATWOOD, HINZMAN, JONES
Plan Review Completed(1st rev)  9/14/1998 FAIL
UFC issue
Routing - FIRE9/11/1998 9/14/1998 FAIL
need II-N const
Plan resubmittals received  9/11/1998
RECEIVED RESUBMITTALS AND TAKEN TO JOHN M.
Plan resubmittals received  9/11/1998
RECEIVED RESUBMITTALS AND TAKEN TO JOHN M.
Plan resubmittals requested  9/11/1998 PEND
MAILED KEN NICHOLS A COPY OF THE COMMENT LIST REQUESTING REVISIONS.
Routing - PLAN CHECK9/10/1998 9/11/1998
Routing - PLUMBING9/9/1998 9/10/1998 PASS
Routing - PLANNING9/1/1998 9/9/1998 PASS
Routing Off Site - STRUCTURAL8/17/1998 9/2/1998
RECEIVED ONE LETTER AND ONE ATTACHED PLANS, CALCS. & SPECS. FROM ATWOOD. ROUTED TO JOHN M
Routing - PUBLIC WORKS8/20/1998 9/1/1998 PASS
Routing - AIRPORT8/28/1998 8/28/1998 PASS
Application received  8/17/1998