Fee Review-notes | 9/18/1998 | | 4/23/1999 | | DONE |
|
|
|
ADDITIONAL VALUE FROM ELECT
|
(F) Reprint permit | | | 4/23/1999 | | |
|
|
|
|
INSP - Final | 1/19/1999 | 1/20/1999 | 1/20/1999 | A | PASS |
Jim Storey
|
|
|
01/20/99 301 - FNL -OK FINAL
|
Permanent Occupancy | | 1/20/1999 | 1/20/1999 | | DONE |
|
|
|
|
Permanent occupancy | | | 1/20/1999 | | PASS |
|
|
|
Perm. Occ. Cert. #7596 issued 1-20-99 to Boise City Hangar C.
|
Temporary occupancy | | | 1/11/1999 | | PASS |
|
|
|
Temp. Occ. Cert. #3774 issued 1-11-99 to Boise City Hangar C.
|
INSP - Final | 1/6/1999 | 1/7/1999 | 1/8/1999 | A | PART |
Jim Storey
|
|
|
01/07/99 301 - TCO -TEMP C OF O ISSUED
|
INSP-Final Inspection | 1/5/1999 | 1/6/1999 | 1/7/1999 | A | PASS |
Joe Tawney
|
|
|
01/06/99 406 - JACK ###-#### FINAL OK FOR PERM OCC ì
|
INSP - Final | 1/5/1999 | 1/6/1999 | 1/6/1999 | P | NR |
Jim Storey
|
|
|
01/06/99 301 - JACK ###-#### called annd canc.
|
INSP-Final Inspection | 1/4/1999 | 1/5/1999 | 1/5/1999 | A | NR |
Joe Tawney
|
|
|
01/05/99 406 - Jack Young ###-#### FINAL NOT READY
|
Code Occupancy Approval | | | 1/5/1999 | | PASS |
|
|
|
RECEIVED REQUEST FOR OCCUPANCY ON BUILDING C, THERE ARE NO REQUIREMENTS PERTAINING TO P&Z AS THIS IS LOCATED AT THE END OF THE RUNWAY AND LAND SCAPE IS NOT ALLOWED DUE TO LOW FLYING PLANES, OCCUPANCY SIGNED OFF AS HANGER LOOKS OK AND PAVING IN.
|
INSP - Framing/Rough-in | 12/31/1998 | 1/4/1999 | 1/4/1999 | A | FAIL |
Jim Storey
|
|
|
01/04/99 301 - c/n 4 idems to have engineer justifacation
|
INSP - Foundation | 10/26/1998 | 10/27/1998 | 10/27/1998 | A | PART |
Jim Storey
|
|
|
10/27/98 301 - jack ###-#### footing covered w/special insp pending report.
|
INSP - Foundation | 10/23/1998 | 10/23/1998 | 10/23/1998 | P | PART |
Jim Storey
|
|
|
10/23/98 301 - jack ###-#### around 1:00 if possible placed with special insp. pending report.
|
(F) Reprint permit | | | 10/15/1998 | | |
|
|
|
|
(F) Reprint permit | | | 10/9/1998 | | |
|
|
|
|
Telephone call | | | 10/8/1998 | | |
|
|
|
called left message on machine plans are ready
|
Issue PAID IN FULL permit | | | 10/8/1998 | | |
|
|
|
|
Plan assigned to (JCM) | 8/19/1998 | | 10/7/1998 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/7/1998 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 10/7/1998 | | 10/7/1998 | | PASS |
|
|
|
|
Print Occupancy Form | | | 10/7/1998 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/7/1998 | | |
|
|
|
|
Routing - FIRE | 10/5/1998 | | 10/6/1998 | | PASS |
|
|
|
changed to II-N
|
Routing - PLAN CHECK | 9/15/1998 | | 10/5/1998 | | |
|
|
|
|
Plan resubmittals received | | | 9/29/1998 | | |
|
|
|
RECEIVED ONE COPY OF SHEET #2,5,&6 TWO COPIES OF STRUT. CALCS. ONE COPY OF LETTER TO JOHN M. AND ONE LETTER TO BOISE FIRE DEPARTMENT. ROUTED TO JOHN M.
|
Routing Off Site - STRUCTURAL | 9/14/1998 | | 9/22/1998 | | PASS |
|
|
|
RESUBMITTALS SENT TO RILEY MAHAFFEY, ATWOOD, HINZMAN, JONES
|
Plan Review Completed(1st rev) | | | 9/14/1998 | | FAIL |
|
|
|
UFC issue
|
Routing - FIRE | 9/11/1998 | | 9/14/1998 | | FAIL |
|
|
|
need II-N const.
|
Plan resubmittals requested | | | 9/11/1998 | | PEND |
|
|
|
MAILED KEN NICHOLS A COPY OF THE COMMENT LIST REQUESTING REVISIONS.
|
Routing - PLAN CHECK | 9/10/1998 | | 9/11/1998 | | PEND |
|
|
|
|
Routing - PLUMBING | 9/9/1998 | | 9/10/1998 | | PASS |
|
|
|
|
Routing - PLANNING | 9/1/1998 | | 9/9/1998 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 8/17/1998 | | 9/2/1998 | | |
|
|
|
RECEIVED ONE COPY OF LETTER, ATTACHED PLANS, CALCS. AND SPEC. ROUTED TO JOHN M.
|
Routing - PUBLIC WORKS | 8/20/1998 | | 9/1/1998 | | PASS |
|
|
|
|
Routing - AIRPORT | 8/28/1998 | | 8/28/1998 | | PASS |
|
|
|
|
Application received | | | 8/19/1998 | | |
|
|
|
|