Permit Information
Permit NumberBLD98-02583
StatusFinaled
Name DAVID H NEWMAN
Site Address 1650 N HILTON ST
Project NamePRECON TECHNOLOGIES
Customer Number 
ePlanReviewNo
Description
PRECON TECHNOLOGIES * TO CONSTRUCT A NEW 2,480 SQ. FT. ONE STORY OFFICE BUILDING WITH A 2,480 SQ. FT. BASEMENT. Constructed of Diamond Snap-form eps insulation concrete forming system at the basement walls, "R-Control" insulated sandwich wall panels at the main floor and TJM Trus joist at floor and ceiling framing. South wall is to be 1hr fire resistant w/ parapet. All construction per the approved plans and attached requirement list. DR123-97 PC#/595-98/ads
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Second Notice BLD4/23/20084/23/20084/25/2008 DONE
DetailsCathy Brown
First Notice has not been responded to.
First Notice 3/31/20084/23/2008 DONE
Code Occupancy Approval3/31/20083/31/20083/31/2008PPASS
DetailsDena Gambrel
3-28-08 1430 Passed Final.
Permanent Occupancy  3/31/2008 DONE
Code Occupancy Approval1/15/20081/15/20081/15/2008PFAIL
DetailsDena Gambrel
1-15-08 1000 Failed Occupancy Inspection. Correction Notice issued.
BLD-Final1/8/20081/9/20081/9/2008APASS
DetailsTom Arcoraci
dave Phone #: ###-####
BLD-Conference4/30/20075/1/20075/1/2007APASS
DetailsTom Arcoraci
Dave ###-####
CHANGE STATUS TO (ISS)  4/30/2007 DONE
reopen permit to schedule conference and final inspection per Tom A.
BLD-Conference10/25/200610/26/200610/26/2006APASS
DetailsTom Arcoraci
dave; Phone #: ###-#### Internet Inspection Request from: Patricia Smith needs to finish items for final and provide approved plans
FIRE-Final Inspection10/4/200610/5/200610/6/2006APASS
DetailsTroy Cobbley
Life safety finaled
FIRE-Final Inspection9/29/20069/29/20069/29/2006PFAIL
DetailsTroy Cobbley
Still need plans and notes
FIRE-Conference8/23/20068/23/20068/23/2006PDONE
DetailsTroy Cobbley
I went over life safety requirements with the owner. He did not have the city approved plans or review comments.
(F) Reprint permit  8/23/2006 DONE
CHANGE STATUS TO (ISS)  7/27/2006  
Ok per George S. to put back to issue mode for final inspections.
PubWorks Occupancy Approval2/7/20052/7/20052/7/2005 DONE
Project found complete. 12/30/02 shows not complete. 2/7/05 shows project complete. Did not sign occupancy card. R.Rokovitz
(F) Reprint permit  7/21/2004  
BLD-Conference10/11/200210/11/200210/11/2002APART
DetailsBill VanDegrift
1650 n. hilton contractor called couldn't get anyone to inspect his dry well or piping for his perimiter drainage system, he'd talked to brian murphy and tom arcoraci. told him he should film it , piping, bedding, fill and filter fabric and go from there. bill vandegrift.
Plan resubmittals received  8/15/2002 DONE
Received five copies of revised sheet C-1 and one copy of cover letter and information. Routed to Brian M. kmm
8/20/02, Brian Approved. I put approved copy in records. kmm
BLD-Framing/Rough-in6/3/20026/3/20026/3/2002PPASS
DetailsTom Arcoraci
###-#### dave
BLD-Framing/Rough-in5/9/20025/10/20025/10/2002APASS
DetailsTom Arcoraci
DAVE ###-#### ok to cover 5/10/2002 11:15:41 AM
BLD-Framing/Rough-in5/9/20025/9/20025/9/2002PNR
DetailsJim Sly
dave ###-####
BLD-Conference11/1/200111/2/200111/2/2001APASS
DetailsTom Arcoraci
###-#### Dave needs arch details for change for stairs 11/1/2001 2:56:31 PM
BLD-Framing/Rough-in10/10/200110/10/200110/10/2001PNR
DetailsTom Arcoraci
###-####
BLD-Conference9/19/20019/19/20019/19/2001PPASS
DetailsTom Arcoraci
###-#### DAVE ok for 1 layer 5/8 x and 3 coat stucco at exterior 9/19/2001 2:12:56 PM
BLD-Framing/Rough-in9/14/20019/14/20019/14/2001PPASS
DetailsDave Hannah
###-#### dave first layer of sheet rock on south wall and parapet wall 9/14/2001 1:51:59 PM
BLD-Conference7/5/20017/5/20017/5/2001PPASS
DetailsTom Arcoraci
###-#### need eng detail for post connections 7/5/2001 4:56:57 AM
BLD-Framing/Rough-in5/17/20015/17/20015/17/2001PPART
DetailsTom Arcoraci
DAve ###-#### pre fab walls installed 5/17/2001 1:45:00 PM
BLD-Foundation4/9/20014/9/20014/9/2001PPART
DetailsTom Arcoraci
found insp= dave-- ###-#### -uffer ground not acceptable ufer ground 4/9/2001 1:46:27 PM
BLD-Foundation2/22/20012/23/20012/23/2001APART
DetailsRuss Owen
pouring elevator shaft ###-#### Dave Newman lower portion of elevator shaft cmu 12 foot lift poured with-out inspections,steel visible above block . 2/23/2001 12:18:28 PM
BLD-Framing/Rough-in12/6/200012/7/200012/7/2000APART
DetailsTom Arcoraci
Dave ###-#### conf on special insp for steel 12/7/2000 10:11:34 AM
BLD-Foundation10/11/200010/13/200010/13/2000APART
DetailsCarl Dependahl
Steve ###-####; 10/12/2000 4:02:32 PM walls ok pend spec insp report 10/12/2000 4:02:44 PM
BLD-Footing9/25/20009/26/20009/26/2000APART
DetailsCarl Dependahl
Steve ###-####, ftg appears ok per engs stamped modification. ok to eliminate "ice-block t 9/26/2000 10:57:11 AM ype forms 9/26/2000 10:57:17 AM
BLD-Footing9/25/20009/25/20009/25/2000PPART
DetailsTom Arcoraci
steve ###-#### need eng ok stamped 9/26/2000 8:11:28 AM
BLD-Conference9/19/20009/20/20009/20/2000APASS
DetailsTom Arcoraci
David Newman ###-#### wants to change to steal joists form wood will have 9/20/2000 11:31:31 AM eng provide details 9/20/2000 11:31:49 AM
BLD-Conference8/3/20008/7/20008/7/2000APASS
DetailsTom Arcoraci
dave --###-#### conf insp
BLD-Conference4/21/20004/24/20004/24/2000APASS
DetailsCarl Dependahl
Dave ###-#### conference on site Met w/owner re: plans, may resubmit. 4/26/00 12:14:55 PM
(F) Reprint permit  9/8/1999 DONE
Issue PAID IN FULL permit  9/7/1999 DONE
Telephone call  9/1/1999 MESS
left mess for mike fairchild at ###-#### to verify plans are ready
Fee Review-notes9/9/1998 8/20/1999
PLANS/APPL TAKEN TO FRONT DESK  6/1/1999 PASS
Print Occupancy Form  6/1/1999
Inspection Record Card- Bld  6/1/1999
Telephone call  6/1/1999 PASS
TALKED TO DOLLY TO VERIFY PLANS ARE READY
Routing - PLAN CHECK6/1/1999 6/1/1999 PASS
Routing - FIRE5/28/1999 6/1/1999 PASS
Plan assigned to (JCM)4/12/1999 6/1/1999 PASS
DetailsJohn Menard
Routing - PLAN CHECK5/27/1999 5/28/1999 PEND
Routing - PUBLIC WORKS5/27/1999 5/27/1999 PASS
Routing - FIRE5/26/1999 5/27/1999 FAIL
Hydrant location and flows not provided and had been requested previously.
Plan Reviewer's activity  5/26/1999 PASS
REVIEWED RESUBMITTALS AND APPROVED AS DRAWN WITH ATTACHED COMMENT LIST.
Routing - PLAN CHECK4/20/1999 5/26/1999 PEND
Plan resubmittals received  5/25/1999 PEND
RECEIVED RESUBMITTALS FROM MIKE FAIRCHILD, FORWARDED SAME TO JOHN MENARD. DAR 5/25/99
Routing - PLAN CHECK2/5/1999 4/19/1999 FAIL
need fire, building approval
Routing - FIRE4/19/1999 4/19/1999 FAIL
reissue conditions for approval
Plan resubmittals requested  4/16/1999 PEND
MAILED DAVID NEWMAN AT PRECON TECHNOLOGIES A LETTER INDICATING MY UNDERSTANDING OF ALL REMAINING ITEMS THAT MUST BE ADDRESSED BEFORE A BUILDING PERMIT CAN BE ISSUED.
Plan assigned to (ADS)8/26/1998 4/12/1999 PEND
Details
PLAN ASSIGNED TO JOHN MENARD TO FINISH AFTER ARLAN RESIGNED TO TAKE ANOTHER POSITION.
Telephone call  2/19/1999
discussed corrections with owner/applicant
Routing Off Site - STRUCTURAL2/5/1999 2/11/1999 PASS
CONTACTED PDQ TO TAKE REVISED PLANS TO OUTSIDE ENG. PER ARLAN. KMM
Plan resubmittals requested  2/11/1999 FAIL
faxed and mailed updated plan review report to applicant. Several items have not yet been corrected.
Routing - FIRE2/2/1999 2/5/1999 FAIL
still needs all corrections noted in first review
Routing - PLAN CHECK2/1/1999 2/2/1999
to fire
Plan resubmittals requested  2/1/1999
need 3rd set of structral plans & calculations for outside engineer review. Called architect, left message. Faxed message to applicant AM of 3 Feb.
Routing - PLUMBING1/28/1999 1/29/1999 PASS
Routing - PLAN CHECK1/27/1999 1/28/1999
route to plumbing
Routing - PUBLIC WORKS1/25/1999 1/27/1999 PASS
Plan resubmittals received  1/25/1999
RECEIVED TWO COPIES OF REVISED SHEETS C-1, S.1, S.2, S.3, AND CALCULATIONS. ROUTED TO ARLAN S. KMM
Plan resubmittals requested  10/9/1998 FAIL
faxed & mailed request for correction still outstanding.
Plan resubmittals received  9/16/1998
RECEIVED RESUBS AND TAKEN TO ARLAN Not all correction items were addressed in this resubmittal. ads
Meeting  9/15/1998
Plans examiner & Fire Plans examiner meet with owner & Architect about required corrections.
Plan Review Completed(1st rev)  9/14/1998 FAIL
ubc,ufc,pw,plumbing fails
Routing - FIRE9/9/1998 9/11/1998 FAIL
Plan resubmittals requested  9/9/1998 FAIL
correction report faxed & mailed to applicant.
Routing Off Site - STRUCTURAL8/28/1998 9/9/1998 FAIL
CONTACTED PDQ TO TAKE PLANS OUT TO ATWOOD HINZMAN AND JONES Re-review requested by PE after correction are made.
Routing - PLAN CHECK9/9/1998 9/9/1998 FAIL
Routing - PLUMBING9/4/1998 9/9/1998 FAIL
Routing - PLANNING9/4/1998 9/4/1998 PASS
approved per DRH97-0123 and as noted on plans for handicap signage and requirement for tree planting permits (per Design Review Conditions).
Routing - PUBLIC WORKS8/28/1998 9/4/1998 FAIL
REQUIRES DRAINAGE PLAN REVISIONS.
Plans ACCEPTED BY PLAN TECH  8/28/1998 PASS
MIKE FAIRCHILD CAME IN AND SIGNED SHEET A-5. READY TO ROUTE
Plans ACCEPTED BY PLAN TECH  8/26/1998 FAIL
CONTACTED MIKE FAIRCHILD TO LET HIM KNOW THAT SHEET A-5 NEEDS TO BE STAMPED. WILL ROUTE PLANS WHEN SHEET IS STAMPED.
Received Certificate of Value  8/25/1998 PASS
Application received  8/24/1998
Recd Pcfee & Taken To Pln CK  8/24/1998