Fee Review-notes | 12/17/1998 | | 6/28/1999 | | |
|
|
|
|
INSP - Final | 6/9/1999 | 6/10/1999 | 6/10/1999 | A | PASS |
Jim Storey
|
|
|
06/10/99 301 - Jackson's Food Store
|
Permanent Occupancy | | 6/9/1999 | 6/9/1999 | | DONE |
|
|
|
|
Permanent occupancy | | | 6/9/1999 | | PASS |
|
|
|
Perm. Occ. Cert. #7790 issued 6-9-99 to Jackson's Food Store.
|
Code Occupancy Approval | | | 5/12/1999 | | PASS |
|
|
|
ALL REQUIREMENTS HAVE BEEN MET INCLUDING PARKING AND LANDSCAPE, FINAL OCCUPANCY SIGNED OFF AND ALSO RELEASE OF BOND.
|
Code Occupancy Approval | | | 5/11/1999 | | |
|
|
|
|
Temporary occupancy | | | 1/28/1999 | | PASS |
|
|
|
Temp. Occ. Cert. #3782 issued 1-28-99 to Jackson's Food Stores.
|
INSP - Final | 1/26/1999 | 1/27/1999 | 1/27/1999 | P | PART |
Jim Storey
|
|
|
01/27/99 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED unlock signage
|
INSP-Final Inspection | 1/25/1999 | 1/26/1999 | 1/26/1999 | P | PASS |
Rick Jackson
|
|
|
01/26/99 409 - chuck- ###-#### fn fire occ approved per plans
|
Code Occupancy Approval | | | 1/26/1999 | | FAIL |
|
|
|
LANDSCAPE AND OTHER IMPROVEMENTS NOT COMPLETE (PARKING STRIPING), BID TO COMPLETE WAS FOR $11,010 WITH THE CITY'S 10 0/0 THE TOTAL BOND AMOUNT WILL BE FOR $12,111. BOND POSTED WITH CATHY FOR THE REQUIRED $12,111, TEMPORARY SIGNED OFF.
|
INSP - Framing/Rough-in | 1/22/1999 | 1/25/1999 | 1/25/1999 | A | PASS |
Jim Storey
|
|
|
01/25/99 301 - CLG -OK CEILING COVER
|
INSP - Framing/Rough-in | 1/4/1999 | 1/5/1999 | 1/5/1999 | A | PASS |
Jim Storey
|
|
|
01/05/99 301 - FRAM-OK FRAMING NAILLING OF GYP OK
|
INSP - Framing/Rough-in | 12/28/1998 | 12/29/1998 | 12/29/1998 | P | PART |
Jim Storey
|
|
|
12/29/98 301 - pending mech
|
INSP-Conference | 12/22/1998 | 12/22/1998 | 12/22/1998 | A | PART |
Rick Jackson
|
|
|
approved fuel shut off location
|
INSP - Framing/Rough-in | 12/16/1998 | 12/16/1998 | 12/16/1998 | | FAIL |
Jim Storey
|
|
|
12/16/98 301 - sheer ok fire wall need arch. resolve submital
|
INSP - Foundation | 11/4/1998 | 11/4/1998 | 11/4/1998 | P | PASS |
Russ Owen
|
|
|
stem walls.
|
INSP - Foundation | 11/3/1998 | 11/3/1998 | 11/3/1998 | P | PASS |
Russ Owen
|
|
|
JED ###-####
|
(F) Reprint permit | | | 10/9/1998 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 10/8/1998 | | |
|
|
|
|
Telephone call | | | 10/6/1998 | | PASS |
|
|
|
talked to dale binning-will pick up plans
|
Routing - PLAN CHECK | 9/22/1998 | | 9/25/1998 | | PASS |
|
|
|
|
Print Occupancy Form | | | 9/25/1998 | | |
|
|
|
|
Plan resubmittals received | | | 9/25/1998 | | PEND |
|
|
|
RECEIVED RESUBMITTALS FROM DALE BINNING, FORWARDED SAME TO ARLAN SMITH
|
Inspection Record Card- Bld | | | 9/25/1998 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/25/1998 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 9/25/1998 | | |
|
|
|
|
Plan Review Completed(1st rev) | | | 9/22/1998 | | FAIL |
|
|
|
fail ubc and PW
|
Routing - PUBLIC WORKS | 9/22/1998 | | 9/22/1998 | | PASS |
|
|
|
|
Routing - FIRE | 9/18/1998 | | 9/22/1998 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 9/18/1998 | | FAIL |
|
|
|
Corrections faxed & mailed to architect.
|
Routing - PLAN CHECK | 9/17/1998 | | 9/18/1998 | | FAIL |
|
|
|
|
Routing - PLANNING | 9/15/1998 | | 9/17/1998 | | PASS |
|
|
|
CVA98-003 APPROVED WITH SPECIFIC CONDITION THAT THE APPLICANT REMOVE EXISTING TEXACO SIGN (BILLBOARD I THINK) PLANS ON TO DESIGN REVIEW DRH98-0111. Plans approved for Design Review per DRH98-0111.
|
Routing - PUBLIC WORKS | 9/4/1998 | | 9/15/1998 | | FAIL |
|
|
|
DALE BINNING CALLED AND WILL HAVE DRAWING ASAP..FAXED CHECK SHEET OVER ON 9-8-98 TO ###-####..BAD
|
Routing - PLUMBING | 9/15/1998 | | 9/15/1998 | | PASS |
|
|
|
|
Routing Off Site - C.D.H | 8/26/1998 | | 9/4/1998 | | PASS |
|
|
|
CONTACED DALE BINNING TO TAKE PLANS OUT TO CDH.
|
Plan assigned to (MYS) | 8/25/1998 | | 8/26/1998 | | PASS |
Marlene Southard
|
|
|
|
Received Certificate of Value | | | 8/26/1998 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 8/26/1998 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/26/1998 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 8/26/1998 | | 8/26/1998 | | |
|
|
|
IN HOUSE
|
Recd Pcfee & Taken To Pln CK | | | 8/25/1998 | | |
|
|
|
|
Application received | | | 8/25/1998 | | |
|
|
|
|
Plan assigned to (ADS) | 8/26/1998 | | 9/25/1996 | | PASS |
|
|
|
|