INSP - Letter of compliance | 2/17/1999 | 2/17/1999 | 2/17/1999 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - lc17585
|
INSP - Letter of compliance | 2/17/1999 | 2/17/1999 | 2/17/1999 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - lc17585
|
INSP - Final | 2/12/1999 | 2/12/1999 | 2/12/1999 | | FAIL |
Carl Dependahl
|
|
|
02/12/99 340 - ###-#### Jack fail, need elec ok
|
INSP - Energy code compliance | 1/20/1999 | 1/20/1999 | 1/20/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - insul. ok, chk underfloor at final
|
INSP - Framing/Rough-in | 1/19/1999 | 1/19/1999 | 1/19/1999 | P | PASS |
Carl Dependahl
|
|
|
01/19/99 340 - REINSP JACK ###-#### cn ok
|
INSP - Framing/Rough-in | 1/15/1999 | 1/15/1999 | 1/15/1999 | | FAIL |
Carl Dependahl
|
|
|
/ / 340 - keep c/n, ok to insul.
|
INSP - Framing/Rough-in | 1/11/1999 | 1/12/1999 | 1/12/1999 | P | FAIL |
Carl Dependahl
|
|
|
01/12/99 340 - JACK ###-#### REINSPECT...2nd c/n, install eng'd fix at i wall(s), ok to ins. only.
|
INSP - Energy code compliance | 1/7/1999 | 1/7/1999 | 1/7/1999 | A | PART |
Carl Dependahl
|
|
|
check underfloor at final, remainder ok.
|
INSP - Framing/Rough-in | 1/6/1999 | 1/6/1999 | 1/6/1999 | P | FAIL |
Wes Worcester
|
|
|
01/06/99 342 - jack- ###-#### fr insp
|
INSP - Framing/Rough-in | 1/6/1999 | 1/6/1999 | 1/6/1999 | P | PART |
Carl Dependahl
|
|
|
wood thru penetrations removed from 1hr wall; still need to nail off all 1hr gypsum; to be done by drywallers per Jack Barber. will reinspect. ok to begin cover...plbg vents moved> 5' from commn wall at roof.
|
Issue PAID IN FULL permit | | | 9/18/1998 | | |
|
|
|
|
Inspection Record Card- Bld | | | 9/14/1998 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 9/14/1998 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/14/1998 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 9/14/1998 | | PASS |
|
|
|
|
Plan assigned to (M_P) | 9/1/1998 | | 9/14/1998 | | PASS |
Mike Phillips
|
|
|
09/14/98 11:10:40 M_P - this action updated by action script from <<>> in Case No. BLD98-2690
|
Routing - PLANNING | 9/4/1998 | | 9/8/1998 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 9/2/1998 | | 9/3/1998 | | PASS |
|
|
|
|
Application received | | | 9/1/1998 | | |
|
|
|
|
Routing - PLAN CHECK | 9/8/1998 | | | | PEND |
|
|
|
|