INSP - Final | 12/29/1998 | 12/30/1998 | 12/30/1998 | P | FAIL |
Wes Worcester
|
|
|
12/30/98 342 - TIM ###-#### given back to Carl
|
INSP - Final | 12/30/1998 | 12/30/1998 | 12/30/1998 | P | PASS |
Carl Dependahl
|
|
|
tim 3838384, lc issued.
|
INSP - Energy code compliance | 12/3/1998 | 12/3/1998 | 12/3/1998 | P | PART |
Carl Dependahl
|
|
|
need check underfloor for insul at final.
|
INSP - Framing/Rough-in | 12/3/1998 | 12/3/1998 | 12/3/1998 | A | PART |
Carl Dependahl
|
|
|
REPAIRS MADE, CHECK UNDERFLOOR AT FINAL (INSUL & BLOCKING.) OK TO COVER
|
INSP - Framing/Rough-in | 11/27/1998 | 11/27/1998 | 11/27/1998 | P | PART |
Carl Dependahl
|
|
|
tim ###-####; add'l c/n, header missed at brg wall, add rotation & squash blocks at brg pony wall. header installed while onsite...ok to cover, check under floor at final.
|
INSP - Energy code compliance | 11/27/1998 | 11/27/1998 | 11/27/1998 | P | PART |
Carl Dependahl
|
|
|
tim ###-####...ok to cover, has frame c/n. check floor insul at final.
|
INSP - Framing/Rough-in | 11/25/1998 | 11/25/1998 | 11/25/1998 | | FAIL |
Tom Arcoraci
|
|
|
/ / 408 - cn issued no plans on site
|
INSP - Framing/Rough-in | 11/24/1998 | 11/25/1998 | 11/25/1998 | A | FAIL |
Wes Worcester
|
|
|
11/25/98 342 - not even close to being ready pt lds, shr, stairs not brn tji's, brng of trusses, not nailed off, etc
|
INSP - Framing/Rough-in | 11/24/1998 | 11/24/1998 | 11/24/1998 | P | CANC |
Jim Sly
|
|
|
11/24/98 316 - Done by Tom A.
|
INSP - Foundation | 10/26/1998 | 10/27/1998 | 10/27/1998 | A | PART |
Carl Dependahl
|
|
|
DANE ###-#### poured looks ok
|
Issue PAID IN FULL permit | | | 9/24/1998 | | |
|
|
|
|
Plan assigned to (R_H) | 9/22/1998 | | 9/23/1998 | | PASS |
|
|
|
09/23/98 09:57:30 R_H - this action updated by action script from <<>> in Case No. BLD98-2697
|
Inspection Record Card- Bld | | | 9/23/1998 | | |
|
|
|
|
Telephone call | | | 9/23/1998 | | |
|
|
|
phoned permit ready
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/23/1998 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 9/23/1998 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 9/4/1998 | | 9/23/1998 | | PEND |
|
|
|
|
Plan assigned to (DJO) | 9/2/1998 | | 9/22/1998 | | PEND |
Dan Overy
|
|
|
|
Routing - PLANNING | 9/2/1998 | | 9/3/1998 | | PASS |
|
|
|
|
Office Staff conference/action | | | 9/3/1998 | | PASS |
|
|
|
LEFT MESS THAT E.S. IS READY TO COME IN & SIGN
|
Routing - PUBLIC WORKS | 9/3/1998 | | 9/3/1998 | | PASS |
|
|
|
|
Application received | | | 9/2/1998 | | |
|
|
|
|