Case Summary (BLD) | | | 1/21/2015 | | DONE |
|
|
|
|
Permanent Occupancy | | 10/11/1999 | 10/11/1999 | | DONE |
|
|
|
|
BLD-Final | 10/8/1999 | 10/11/1999 | 10/11/1999 | A | PASS |
Carl Dependahl
|
|
|
Walgreen's, final reinspect - I have the card, Carl - Cathy ok for c/o
|
Permanent occupancy | | | 10/11/1999 | | DONE |
|
|
|
Perm. Occ. Cert. #7935 issued 10-11-99 to Walgreen's.
|
FIRE-Alarm Testing | 10/5/1999 | 10/6/1999 | 10/6/1999 | P | PART |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 10/05/1999 at 15:17:04. Contact: ###-####. Ok on alarm system
|
FIRE-Final Inspection | 10/6/1999 | 10/6/1999 | 10/6/1999 | P | PASS |
Joe Tawney
|
|
|
John ###-#### reinsp ok for perm occ
|
BLD-Final | 10/6/1999 | 10/6/1999 | 10/6/1999 | P | FAIL |
Tom Arcoraci
|
|
|
final fire scheduled for this afternoon not ready for struc final
|
INSP - Final | 8/27/1999 | 8/27/1999 | 8/27/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR TEMP OCC
|
INSP-Final Inspection | 8/24/1999 | 8/25/1999 | 8/26/1999 | P | FAIL |
Joe Tawney
|
|
|
09/01/99 406 - REINSP FAIL DUCT DET
|
Temporary occupancy | | | 8/26/1999 | | PASS |
|
|
|
issued temp occ to walgreen 8/26/99- cert. #3896
|
INSP - Final | 8/25/1999 | 8/25/1999 | 8/25/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR TEMP OCC
|
INSP - Final | 8/24/1999 | 8/25/1999 | 8/25/1999 | P | FAIL |
Carl Dependahl
|
|
|
08/26/99 340 - GARY ###-####; c/n, eng's letter, grid, other agcy oks...
|
INSP-Final Inspection | 8/24/1999 | 8/24/1999 | 8/24/1999 | P | FAIL |
Joe Tawney
|
|
|
09/01/99 406 - FINAL FAIL C/N ISSUED
|
Fee Review-notes | 3/2/1999 | | 8/24/1999 | | |
|
|
|
|
INSP-Final Inspection | 8/25/1999 | 8/26/1999 | 8/23/1999 | A | PART |
Joe Tawney
|
|
|
09/01/99 406 - OK ON AG HYDRO TEST
|
INSP-Conference | 8/12/1999 | 8/12/1999 | 8/12/1999 | P | PART |
Joe Tawney
|
|
|
08/12/99 406 - CONF ON SPKLR COVERAGE OF SOFFITS OK TO COVER
|
Code Occupancy Approval | | | 8/12/1999 | | |
|
|
|
temporary requested by Gary Oliver ###-####
|
INSP - Wall cover | 7/31/1999 | 8/2/1999 | 8/2/1999 | A | FAIL |
Tom Arcoraci
|
|
|
08/02/99 408 - grid not ready
|
INSP - Wall cover | 8/2/1999 | 8/2/1999 | 8/2/1999 | P | FAIL |
Tom Arcoraci
|
|
|
08/02/99 408 - grid needs end struts on order
|
INSP - Framing/Rough-in | 7/28/1999 | 7/28/1999 | 7/28/1999 | P | FAIL |
Carl Dependahl
|
|
|
grid clg, verbal c/n...gave guidelines to supt.
|
INSP - Framing/ Rough-in | 7/27/1999 | 7/27/1999 | 7/27/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - CONF ONLY: NEED DETAIL FOR CORRIDOR AT EAST SIDE
|
INSP - Framing/ Rough-in | 7/21/1999 | 7/21/1999 | 7/21/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - NEED SURVEYOR'S STATEMENT FOR SETBACKS
|
INSP - Framing/ Rough-in | 7/20/1999 | 7/20/1999 | 7/20/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - NEED DETAIL FOR CORRIDOR
|
INSP - Framing/ Rough-in | 7/15/1999 | 7/15/1999 | 7/15/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - SPEC INSP ONSITE; MASONRY
|
INSP - Energy code compliance | 7/15/1999 | 7/15/1999 | 7/15/1999 | P | NR |
Tom Arcoraci
|
|
|
07/15/99 408 - Scheduled by Hello!. Contact phone is [6586540].
|
INSP-Conference | 6/29/1999 | 6/29/1999 | 6/29/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - CONF WITH GARY REG SPKLR PROT SOFFITS
|
INSP - Framing/ Rough-in | 6/28/1999 | 6/28/1999 | 6/28/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - OK TO CONTINUE COVER, SOFFITS, INT WALLS
|
INSP-Sprinkler Rough-in/Hydro | 6/24/1999 | 6/24/1999 | 6/24/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON UNDERGROUND HYDRO TEST
|
INSP - Framing/Rough-in | 6/9/1999 | 6/10/1999 | 6/10/1999 | A | CANC |
Jim Storey
|
|
|
06/10/99 301 - trans to carl
|
INSP - Framing/ Rough-in | 6/10/1999 | 6/10/1999 | 6/10/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - INT SOFFITS, EXT WALLS OK TO INSUL.
|
INSP-Sprinkler Rough-in/Hydro | 6/10/1999 | 6/10/1999 | 6/10/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON EXTENDED UNDERGROUND LINE
|
INSP - Framing/Rough-in | 6/7/1999 | 6/7/1999 | 6/7/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - REVIEWING RESUBFOR STRUCT CHANGES; ROOF FRAME OK; NEED ENG'S
|
INSP - Framing/Rough-in | 6/3/1999 | 6/3/1999 | 6/3/1999 | | FAIL |
Carl Dependahl
|
|
|
/ / 340 - NEED SURVEY STATEMENT; OK TO ROOF, COMPLETE MANSARDS
|
INSP - Framing/Rough-in | 6/2/1999 | 6/2/1999 | 6/2/1999 | P | PART |
Carl Dependahl
|
|
|
06/02/99 340 - ROOFING ###-####-,pend engs report for roof
|
INSP - Framing/Rough-in | 5/28/1999 | 5/28/1999 | 5/28/1999 | | FAIL |
Carl Dependahl
|
|
|
06/02/99 340 - ROOFING ###-####-, need eng's claification for straps& ot
|
INSP - Framing/Rough-in | 5/26/1999 | 5/27/1999 | 5/27/1999 | A | FAIL |
Carl Dependahl
|
|
|
05/27/99 340 - Ken ###-#### roof;need engs okfor roof as not per plan, p
|
INSP-Sprinkler Rough-in/Hydro | 5/20/1999 | 5/20/1999 | 5/20/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON UNDERGROUND PIPING
|
INSP - Framing/Rough-in | 5/6/1999 | 5/7/1999 | 5/7/1999 | A | PART |
Carl Dependahl
|
|
|
05/07/99 340 - standing structural Gary ###-####;not frame, conc slab; p
|
INSP - Foundation | 5/6/1999 | 5/6/1999 | 5/6/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - CHK'D CONC SPECS, HAS SPEC INSP. PENDING REPORT
|
INSP - Foundation | 4/16/1999 | 4/16/1999 | 4/16/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - CONF ONLY W/ ARCH RE CALCS SUBMITTED
|
INSP - Framing/Rough-in | 4/14/1999 | 4/14/1999 | 4/14/1999 | | NR |
Carl Dependahl
|
|
|
/ / 340 - QUESTION RE EXIT SIGN, REFERRED TO FIRE/ PLAN REVIEW. CONF O
|
INSP - Foundation | 4/6/1999 | 4/7/1999 | 4/7/1999 | A | PART |
Carl Dependahl
|
|
|
04/07/99 340 - GARY ###-####; masonry fnd, has spec insp, pending report
|
INSP - Foundation | 4/5/1999 | 4/5/1999 | 4/5/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - REC'D RESUBMITTAL/CLARIFICATION FOR MASONRY PILASTERS & WALL
|
INSP - Foundation | 3/31/1999 | 3/31/1999 | 3/31/1999 | | NR |
Carl Dependahl
|
|
|
/ / 340 - REC'D RESUB, NO INSP
|
Plan resubmittals received | | | 3/15/1999 | | PEND |
|
|
|
RECEIVED RESUBMITTALS FROM JMD ARCHITECTURE, ROSALINA RAMIREZ, FORWARDED SAME TO TOM ARCORACI. DAR 3/15/99
|
Plan resubmittals received | | | 3/1/1999 | | PEND |
|
|
|
RECEIVED RESUBMITTALS FROM ROSALINA RAMIREZ OF JMD ARCHITECTS, FORWARDED TWO TO TEMPRA WILSON AND TOM ARCORACI. DAR 3/01/99
|
(F) Reprint permit | | | 2/9/1999 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 2/8/1999 | | |
|
|
|
|
Plan assigned to (ADS) | 9/3/1998 | | 1/28/1999 | | PASS |
|
|
|
plan changes submitted prior to issuance of permit. need additional review. APPROVED
|
Plan Reviewer's activity | | | 1/28/1999 | | PASS |
|
|
|
Resubmittals dated 12 & 22 Jan 1999 approved. 2hr. additional plan review time charged because these changes came after plan approval (but before the permit was issued). Planning also reviewed and approved the changes. Plans returned to front desk this date.
|
CHANGE STATUS TO (R) | | | 1/28/1999 | | |
|
|
|
arlene gave plans back to me
|
Routing - PLANNING | 1/22/1999 | | 1/25/1999 | | PASS |
|
|
|
Approved column changes. Sign revisions need to be reviewed under a separate sign permit.
|
Plan resubmittals received | | | 1/22/1999 | | |
|
|
|
RECEIVED REVIESED CIVIL SHEETS C3,4,5,&6. ROUTED TO ARLAN S. KMM
|
Plan Reviewer's activity | | | 1/21/1999 | | |
|
|
|
Requested clarification on the grouting of the new full block CMU soldier courses. Letter mailed & Faxed to architect.
|
CHANGE STATUS TO (P) | | | 1/14/1999 | | |
|
|
|
GAVE PLANS BACK TO ARLEN-SAID THEY SUBMITTED A BUNCH OF RESUBMITTALS TO HIM.MPS
|
CHANGE STATUS TO (R) | | | 1/13/1999 | | |
|
|
|
|
Plan resubmittals received | | | 1/12/1999 | | |
|
|
|
plan changes submitted by architect.
|
Telephone call | | | 10/20/1998 | | |
|
|
|
TALKED TO ROSALENA..STILL WAITING ON ACHD
|
Telephone call | | | 10/9/1998 | | |
|
|
|
waiting on achd
|
Inspection Record Card- Bld | | | 10/9/1998 | | |
|
|
|
|
Print Occupancy Form | | | 10/9/1998 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/9/1998 | | |
|
|
|
|
Routing - PLAN CHECK | 9/29/1998 | | 10/8/1998 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 10/8/1998 | | 10/8/1998 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/8/1998 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 9/30/1998 | | HOLD |
|
|
|
Verify that all existing buildings required to be removed from this site have obtained all building department approvals and requirements prior to issue of this permit. JCM
|
Plan Review Completed(1st rev) | | | 9/29/1998 | | FAIL |
|
|
|
Public works for street lights and legal land description
|
Routing - FIRE | 9/28/1998 | | 9/29/1998 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 9/24/1998 | | 9/28/1998 | | PASS |
|
|
|
approved with the notes attached to the plans.
|
Routing - PLUMBING | 9/15/1998 | | 9/23/1998 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 9/9/1998 | | 9/15/1998 | | FAIL |
|
|
|
REQUIRES STREET LIGHT PLAN PER BILL C. AND INCOMPLETE LEGAL DESCRIPTION PER JRICH.
|
Routing Off Site - C.D.H | 9/11/1998 | | 9/11/1998 | | PASS |
|
|
|
|
Routing - PLANNING | 9/9/1998 | | 9/9/1998 | | PASS |
|
|
|
phase 2 includes parking and landscaping around, front and behind retail "A". One set of drawings includes all of phase I and another set has a site plan "AO.1" showing phase 2 only. Also, plans for signs are included in the sets of plans provided. Any business sign (not including signs designating handicapped stalls, etc.) requires a sign permit issued by Boise Planning Division. Approval of the grading plan is in no way approval of the included sign drawings. RIGHT-OF-WAY VACATIONS: The ACHD Commission approved the vacation on August 12, 1998 but will not sign a resolution to finalize until October, per Kathy Smith at ACHD. We have yet to receive a record of survey (a condition of approval for CUP98-20) but staff has signed the grading permit; the permit for the first building should not be signed until the vacation is complete and we have received a record of survey to reflect the vacation and consolidation of lots, etc. - M. Hall. x-ref. CUP98-20
|
Routing - PLANNING | 9/3/1998 | | 9/4/1998 | | PASS |
|
|
|
X-ref. DRH98-0089
|
Plans ACCEPTED BY PLAN TECH | | | 9/3/1998 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 9/3/1998 | | PEND |
|
|
|
WILL START ROUTING WITHOUT DRAINAGE CALCS. BECAUSE NEEDS TO GO TO CDH FIRST.
|
Received Certificate of Value | | | 9/3/1998 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 9/2/1998 | | 9/3/1998 | | |
Marlene Southard
|
|
|
|
Routing Off Site - STRUCTURAL | 9/3/1998 | | 9/3/1998 | | |
|
|
|
ENG. WILL BE DONE IN HOUSE PER JOHN M.
|
Recd Pcfee & Taken To Pln CK | | | 9/2/1998 | | |
|
|
|
|
Application received | | | 9/2/1998 | | |
|
|
|
|
Case Summary (BLD) | | | | | |
|
|
|
|
Routing - PLAN CHECK | 1/25/1999 | | | | |
|
|
|
|