Information based on query as of Friday, July 19, 2024.
Permit Information
Permit NumberBLD98-02773
StatusExpired
Name BRUCE POE
Site Address 115 W MAIN ST
Project NameARTHUR BERRY-FNDTN
Customer Number 
ePlanReviewNo
Description
ARTHUR BERRY & CO. * FOUNDATION PERMIT ONLY IN PREPRATION FOR THE FUTURE CONSTRUCTION OF A 15,300 SQUARE FOOT, 2 story BUILDING addition FOR AUTHUR BERRY AND COMPANY. NO CONSTRUCTION BEYOND THE FOUNDATION IS ALLOWED UNDER THIS PERMIT. ALL PER THE ENGINEERED PLANS ON FILE AS APPROVED BY THE PUBLIC WORKS DEPARTMENT AND PLANNING AND DEVELOPMENT SERVICES DEPARTMENT.DRH98-0126. PC# 632-98 ADS
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Foundation11/2/199811/2/199811/2/1998PPART
Details
11/02/98 333 - FDN -OK FOUNDATION
INSP - Foundation10/27/199810/30/199810/30/1998APART
Details
10/30/98 333 - ok pend spec insp rep
INSP - Foundation10/20/199810/21/199810/21/1998APASS
Details
10/21/98 333 - RICH ###-#### FDN -OK FOUNDATION ì
INSP - Foundation10/16/199810/16/199810/16/1998 PASS
Details
10/16/98 333 - FDN -OK FOUNDATION
INSP - Concrete10/13/199810/14/199810/14/1998PFAIL
DetailsJim Storey
10/14/98 301 - RICH ###-#### trans to kim ì
INSP - Foundation10/6/199810/7/199810/7/1998PPART
DetailsJim Storey
10/07/98 301 - rich ###-#### footing CORR-CORREC-CALL FOR REINSP WHEN COMPLETED bar clearance to soil, lap ba corners miss located. special insp. to verrify compliance and note in re to city. need scope of work to be done by special insp. for file.
INSP - Framing/Rough-in10/5/199810/7/199810/7/1998AFAIL
DetailsJim Storey
10/07/98 301 - RICH ###-#### this is a footing insp. not a framing insp. and was sent as a footing in the same day am.
Plan resubmittals received  10/6/1998
RECEIVED TWO COPIES OF REVISED FIG/FOUNDATION DRAWINGS AND DETAILS. TWO COPIES OF SUPPLEMENTAL STRUCTUAL CAL. TWO COPIES OF STRUCTURAL FRAMING PLANS (FOR REF.) TWO COPIES OF ARCHITCTRUAL PLANS (FOR REF.) ROUTED TO ARLAN
Plan assigned to (ADS)9/9/1998 10/2/1998 PASS
Details
Issue PAID IN FULL permit  10/2/1998
Routing - PLAN CHECK10/1/1998 10/2/1998 PASS
Inspection Record Card- Bld  10/2/1998
PLANS/APPL TAKEN TO FRONT DESK  10/2/1998 PASS
Telephone call  10/2/1998 PASS
talked to rich-will pick up plans
Plan resubmittals received  10/1/1998
soils report recieved today after 4:30pm.
Plan resubmittals requested  10/1/1998 FAIL
Asked for copy of soils report. Request made by phone to achitect & project super.
Routing - FIRE9/30/1998 9/30/1998 PASS
Routing - PLUMBING9/29/1998 9/30/1998 PASS
PASSED BY BILL
Plan resubmittals received  9/30/1998
RECEIVED TWO COPIES OF BASEMENT PLUMBING LAYOUT AND ROUTED TO BILL V.
Plan Review Completed(1st rev)  9/30/1998 PASS
Plan resubmittals received  9/24/1998 PEND
RECEIVED RESUBMITTALS FROM BRUCE POE, FORWARDED SAME TO ARLAN SMITH.
Routing - PUBLIC WORKS9/15/1998 9/15/1998 PASS
signed by bev
Routing - PLANNING9/11/1998 9/14/1998 PASS
approved for foundation permit only.
Plans ACCEPTED BY PLAN TECH9/11/1998 9/9/1998 PASS
RECEIVED CERTIFICATE OF VALUE FROM BRUCE POE
Application received  9/8/1998