INSP - Letter of compliance | 11/6/1998 | 11/6/1998 | 11/6/1998 | | PASS |
Jim Sly
|
|
|
/ / 316 - C/C # 014834
|
INSP - Letter of compliance | 11/6/1998 | 11/6/1998 | 11/6/1998 | | PASS |
Jim Sly
|
|
|
/ / 316 - C/C # 014834
|
INSP - Final | 11/6/1998 | 11/6/1998 | 11/6/1998 | P | PASS |
Jim Sly
|
|
|
11/06/98 316 - C/C # 014834 ì
|
INSP - Energy code compliance | 10/21/1998 | 10/21/1998 | 10/22/1998 | P | PASS |
Jim Sly
|
|
|
10/22/98 316 - michael ###-####
|
INSP - Framing/Rough-in | 10/20/1998 | 10/20/1998 | 10/20/1998 | P | PASS |
Jim Sly
|
|
|
10/20/98 316 - MICHEAL ###-####
|
INSP - Framing/Rough-in | 10/19/1998 | 10/19/1998 | 10/19/1998 | P | FAIL |
Jim Sly
|
|
|
10/19/98 316 - C/N...Need appr plan for shear....Need all trade appr for
|
INSP - Foundation | 10/1/1998 | 10/1/1998 | 10/5/1998 | P | PART |
Jim Sly
|
|
|
10/05/98 316 - Check setbacks. setbk left 9'...right 8'...appears to be
|
Issue PAID IN FULL permit | | | 10/5/1998 | | |
|
|
|
|
INSP - Foundation | 10/1/1998 | 10/1/1998 | 10/1/1998 | | PART |
Jim Sly
|
|
|
10/01/98 316 - Bob A. asked to verify 10'(left) and 9'(right) side setbk
|
SUPER- Supervisor's review | 10/1/1998 | 10/1/1998 | 10/1/1998 | | PEND |
|
|
|
P&Z requires dwelling to be relocated 3'to the right. Instructed Jim Sly to check site,no actons performed this date, and tag if footings placed asked Mike Otto to phone contractor.
|
Inspection Record Card- Bld | | | 10/1/1998 | | |
|
|
|
|
Routing - PLAN CHECK | 9/18/1998 | | 10/1/1998 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/1/1998 | | PASS |
|
|
|
|
Plan assigned to (MLO) | 9/28/1998 | | 10/1/1998 | | PASS |
Mike Otto
|
|
|
|
Plan assigned to (DJO) | 9/18/1998 | | 9/28/1998 | | PEND |
Dan Overy
|
|
|
|
Routing - PLANNING | 9/18/1998 | | 9/18/1998 | | PASS |
|
|
|
|
Application received | | | 9/18/1998 | | |
|
|
|
|
Routing - PUBLIC WORKS | 9/18/1998 | | 9/18/1998 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 9/18/1998 | | |
|
|
|
|