Letter of compliance | | | 7/7/1999 | | PASS |
|
|
|
Letter of Compliance #16613 issued 7-7-99.
|
Code Occupancy Approval | | | 6/4/1999 | | PASS |
|
|
|
ALL CONDITIONS OF DRH98-0150 HAVE BEEN MET, FINAL OCCUPANCY SIGNED OFF.
|
Code Occupancy Approval | | | 6/3/1999 | | |
|
|
|
Final Occupancy requested by Gene ###-####
|
INSP-Final Inspection | 5/27/1999 | 5/27/1999 | 5/27/1999 | A | PASS |
Rick Jackson
|
|
|
occ approved
|
INSP - Final | 5/26/1999 | 5/26/1999 | 5/27/1999 | P | FAIL |
Jim Storey
|
|
|
05/26/99 301 - fire stop 1 hr walls
|
INSP-Final Inspection | 5/24/1999 | 5/25/1999 | 5/25/1999 | P | |
Rick Jackson
|
|
|
Gene ###-#### call first to meet
|
INSP-Final Inspection | 5/19/1999 | 5/21/1999 | 5/21/1999 | A | FAIL |
Rick Jackson
|
|
|
###-#### GENE//CALL B4 GOING TO MEET U 4 ACCESS no phone lines for monitoring sprinklers; smoke detector too low in riser room; address; knox box
|
INSP-Supply line flush | 4/29/1999 | 4/29/1999 | 4/29/1999 | A | PASS |
Rick Jackson
|
|
|
FLUSH OKAY
|
INSP - Framing/Rough-in | 3/8/1999 | 3/8/1999 | 3/8/1999 | | PASS |
Jim Storey
|
|
|
03/08/99 301 - FRAM-OK FRAMING pending ele
|
INSP-Conference | 3/8/1999 | 3/8/1999 | 3/8/1999 | P | PART |
Rick Jackson
|
|
|
with gen. and #301
|
INSP - Framing/Rough-in | 3/5/1999 | 3/8/1999 | 3/8/1999 | A | PASS |
Jim Storey
|
|
|
03/08/99 301 - FRAM-OK FRAMING
|
INSP - Concrete | 3/2/1999 | 3/2/1999 | 3/2/1999 | P | CANC |
Russ Owen
|
|
|
03/02/99 407 - canc.
|
INSP - Concrete | 2/26/1999 | 2/26/1999 | 2/26/1999 | P | PASS |
Jim Storey
|
|
|
02/26/99 301 - grouting columns ###-#### Gene ok
|
INSP - Framing/Rough-in | 2/18/1999 | 2/18/1999 | 2/18/1999 | | PASS |
Jim Storey
|
|
|
02/12/99 301 - roof framing ok
|
INSP - Foundation | 2/9/1999 | 2/10/1999 | 2/10/1999 | P | PART |
Jim Storey
|
|
|
02/10/99 301 - placed w/special insp. pending report.
|
INSP - Framing/Rough-in | 2/5/1999 | 2/9/1999 | 2/9/1999 | A | NR |
Jim Storey
|
|
|
02/09/99 301 - NO ACESS TO ROOF
|
INSP - Concrete | 2/5/1999 | 2/8/1999 | 2/8/1999 | A | PART |
Jim Storey
|
|
|
02/08/99 301 - placed w/special insp. pending report.
|
INSP - Concrete | 2/4/1999 | 2/5/1999 | 2/5/1999 | A | FAIL |
Carl Dependahl
|
|
|
02/05/99 340 - JEAN ###-#### nr gave to 301
|
INSP - Foundation | 2/5/1999 | 2/5/1999 | 2/5/1999 | | NR |
Jim Storey
|
|
|
/ / 301 - CANCLED TIL MONDAY
|
INSP - Framing/Rough-in | 2/1/1999 | 2/2/1999 | 2/2/1999 | P | PART |
Jim Storey
|
|
|
02/02/99 301 - JEAN ###-#### WELDING ON ROOF no acess to roof- panal footing corection per-eng detail.
|
INSP - Foundation | 1/27/1999 | 1/27/1999 | 1/28/1999 | P | FAIL |
Jim Storey
|
|
|
01/27/99 301 - gene- ###-#### foun welding insp-or richard on site ENGIN
|
INSP - Framing/Rough-in | 1/27/1999 | 1/27/1999 | 1/27/1999 | P | FAIL |
Carl Dependahl
|
|
|
01/27/99 340 - gene- ###-#### -welding insp-corner connect. 301 area, pe
|
INSP - Framing/Rough-in | 1/5/1999 | 1/6/1999 | 1/6/1999 | A | PART |
Jim Storey
|
|
|
01/06/99 301 - HAROLD ###-#### CONCRETE WALL...resent to 301 covered wit
|
INSP - Wall cover | 12/30/1998 | 12/30/1998 | 12/30/1998 | | PART |
Jim Storey
|
|
|
/ / 301 - OK PENDING REPORT FROM STRATA
|
INSP - Concrete | 12/29/1998 | 12/30/1998 | 12/30/1998 | A | FAIL |
Wes Worcester
|
|
|
12/30/98 342 - harold ###-#### no answer, 2 attempts, not on my map
|
INSP - Foundation | 12/16/1998 | 12/17/1998 | 12/18/1998 | A | FAIL |
Wes Worcester
|
|
|
12/17/98 342 - ###-#### HAROLD TRIED # FOR TWO DAYS, NOT ON MY MAP, NO O
|
INSP - Foundation | 12/1/1998 | 12/1/1998 | 12/10/1998 | P | FAIL |
Carl Dependahl
|
|
|
HAROLD ###-#### unable to contact...
|
INSP - Foundation | 12/1/1998 | 12/1/1998 | 12/2/1998 | P | PART |
Russ Owen
|
|
|
12/01/98 407 - special inspection required 4 interior peires ready to po
|
(F) Reprint permit | | | 12/1/1998 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 11/30/1998 | | |
|
|
|
|
Inspection Record Card- Bld | | | 11/2/1998 | | |
|
|
|
|
Print Occupancy Form | | | 11/2/1998 | | |
|
|
|
|
Telephone call | | | 11/2/1998 | | |
|
|
|
CALLED AND TALKED TO PHIL TOLD HIM THAT HE NEEDS VERIFICATION FROM ACHD FOR IMPACT FEES
|
Plan assigned to (JCM) | 9/25/1998 | | 10/30/1998 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/30/1998 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 10/7/1998 | | 10/30/1998 | | |
|
|
|
RECEIVED STRUCTURAL REVIEW FOR RESUB NO. 1 RECEIVED 10-07-98 AND STRUCTURAL REVIEW LETTER BY CH2MHILL DATED 10-30-98. ROUTED TO JOHN M. KMM
|
Routing - FIRE | 10/12/1998 | | 10/14/1998 | | PASS |
|
|
|
smoke and heat vents may be deleted, need heat for sprinklers for approval.
|
Plan Review Completed(1st rev) | | | 10/14/1998 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 10/5/1998 | | 10/12/1998 | | |
|
|
|
|
Plan Reviewer's activity | | | 10/12/1998 | | PASS |
|
|
|
PLANS REVIEWED AND APPROVED WITH ATTACHED REQUIREMENT LIST.
|
Plan resubmittals received | | | 10/7/1998 | | PASS |
|
|
|
1. revised sheet S1.3 to reflect the 6inch floor slab 2. revised sheets S2.1 and S2.2 to reflect the correct joist
|
Routing - PUBLIC WORKS | 9/30/1998 | | 10/5/1998 | | PASS |
|
|
|
|
Plan resubmittals received | | | 10/2/1998 | | PASS |
|
|
|
STRUCTURAL REVIEW LETTER BY CH2M HILL
|
Routing - PLUMBING | 9/29/1998 | | 9/30/1998 | | PASS |
|
|
|
|
Routing - PLANNING | 9/25/1998 | | 9/29/1998 | | PASS |
|
|
|
approved per DRH98-0150.
|
Routing Off Site - STRUCTURAL | 9/25/1998 | | 9/25/1998 | | |
|
|
|
CONTACTED PDQ TO TAKE PLANS OUT TO CH2MHILL
|
Plans ACCEPTED BY PLAN TECH | | | 9/25/1998 | | PASS |
|
|
|
|
Received Certificate of Value | | | 9/25/1998 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 9/25/1998 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/25/1998 | | |
|
|
|
|
Plan assigned to (MYS) | 9/25/1998 | | 9/25/1998 | | PASS |
Marlene Southard
|
|
|
|
Application received | | | 9/25/1998 | | |
|
|
|
|
INSP - Foundation | 11/30/1998 | 12/1/1998 | 12/19/1980 | A | PART |
Jim Storey
|
|
|
12/01/98 301 - slab s/e site ok for cover 2500 psi design.
|