Permanent occupancy | | | 10/18/1999 | | DONE |
|
|
|
Perm. Occ. Cert. #7949 issued 10-18-99 to the Owens Ave. Apts.
|
Permanent Occupancy | | 9/29/1999 | 9/29/1999 | | DONE |
|
|
|
|
BLD-Final | 9/29/1999 | 9/29/1999 | 9/29/1999 | | PART |
|
|
|
occ req card signoff Signed
|
Temporary occupancy | | | 4/6/1999 | | PASS |
|
|
|
Temp. Occ. cert. #3821 issued 4-6-99 to the Owens Avenue Apts.
|
INSP - Final | 1/29/1999 | 1/29/1999 | 1/29/1999 | | FAIL |
Carl Dependahl
|
|
|
/ / 340 - 3713951 devin c/n, ok for t/o. card to cont.
|
INSP - Final | 1/28/1999 | 1/29/1999 | 1/29/1999 | A | NR |
Carl Dependahl
|
|
|
01/29/99 340 - DEVIN- ###-#### FN OCC INSP unable to contact
|
INSP-Final Inspection | 1/27/1999 | 1/28/1999 | 1/28/1999 | A | PASS |
Joe Tawney
|
|
|
01/28/99 406 - DEVIN ###-#### FINAL OK FOR PERM OCC
|
INSP - Framing/Rough-in | 12/17/1998 | 12/18/1998 | 12/18/1998 | A | PART |
|
|
|
12/18/98 338 - made ok to insulate only
|
INSP - Framing/Rough-in | 12/9/1998 | 12/9/1998 | 12/9/1998 | | PART |
|
|
|
12/09/98 338 - madeok to cover
|
INSP - Framing/Rough-in | 12/3/1998 | 12/4/1998 | 12/4/1998 | A | PART |
|
|
|
12/04/98 338 - made ok to insulate
|
INSP - Framing/Rough-in | 12/2/1998 | 12/3/1998 | 12/3/1998 | A | FAIL |
|
|
|
12/03/98 333 - GIVEN TO PERRY
|
INSP - Framing/Rough-in | 10/7/1998 | 10/8/1998 | 10/8/1998 | A | PART |
|
|
|
10/08/98 338 - made ok to pour r-bar is placed
|
SUPER- Supervisor's review | 10/7/1998 | 10/7/1998 | 10/7/1998 | | PEND |
|
|
|
Review of rated construction requirements at tubs. Instructed builder to obtain detail from architect for perry's review and approval prior to comencing w/fix.
|
SUPER- Supervisor's review | 10/6/1998 | 10/6/1998 | 10/6/1998 | | PEND |
|
|
|
Review of requirements.
|
INSP - Foundation | 10/5/1998 | 10/5/1998 | 10/5/1998 | P | PART |
|
|
|
10/05/98 338 - made ok to pour r-bar is placed footings only
|
Inspection Record Card- Bld | | | 10/5/1998 | | |
|
|
|
|
Print Occupancy Form | | | 10/5/1998 | | |
|
|
|
|
Telephone call | | | 10/5/1998 | | |
|
|
|
CALLED BRIAN PERMIT READY
|
Print Occupancy Form | | | 10/5/1998 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 10/5/1998 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/2/1998 | | PASS |
|
|
|
|
Plan assigned to (M_P) | 9/29/1998 | | 10/2/1998 | | PASS |
Mike Phillips
|
|
|
10/02/98 16:28:53 M_P - this action updated by action script from <<>> in Case No. BLD98-2977
|
Plan Reviewer's activity | | | 10/2/1998 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/2/1998 | | PASS |
|
|
|
|
Routing - FIRE | 10/2/1998 | | 10/2/1998 | | PASS |
|
|
|
hydrant must be installed prior to framing, landscaping must be 3 ft from hydrant
|
Application received | | | 9/29/1998 | | |
|
|
|
|