Fee Review-notes | 11/23/1999 | 11/23/1999 | 5/2/2000 | | DONE |
|
|
|
|
BLD-Final | 4/18/2000 | 4/20/2000 | 4/20/2000 | A | PASS |
Alan Hauser
|
|
|
Mark, ###-#### - please call 1st so he can unlock the bldg. : ) Done #316 4/20/00 1:26:29 PM Ok for perm. occ. 4/20/00 1:33:22 PM
|
Letter of compliance | | | 4/20/2000 | | DONE |
|
|
|
Letter of Compliance #18482 issued 4-20-00.
|
FIRE-Final Inspection | 4/5/2000 | 4/10/2000 | 4/10/2000 | A | PASS |
Rick Jackson
|
|
|
mark ###-#### 331 - ###-####
|
BLD-Final | 4/3/2000 | 4/5/2000 | 4/5/2000 | A | FAIL |
Jim Sly
|
|
|
Mark, ###-#### - please call 1st so he can meet you there : ) Need occupancy req. card & all signatures 4/5/00 1:22:28 PM
|
Print Occupancy Form | | | 4/5/2000 | | DONE |
|
|
|
|
BLD-Final | 3/29/2000 | 3/31/2000 | 3/31/2000 | A | FAIL |
Jim Sly
|
|
|
Mark Dooley, ###-#### - please call 1st so he can meet you there. Recall insp. 3/31/00 2:14:26 PM
|
Fee Review-notes | 4/1/1999 | | 1/25/2000 | | DONE |
|
|
|
|
(F) Reprint permit | | | 11/23/1999 | | DONE |
|
|
|
|
SUPER- Supervisor's review | 7/9/1999 | 7/9/1999 | 7/9/1999 | | PEND |
|
|
|
CN issued on requirements for use.
|
Print Occupancy Form | | | 7/9/1999 | | |
|
|
|
|
Inspection Record Card- Bld | | | 7/9/1999 | | |
|
|
|
|
INSP - Framing/Rough-in | 7/8/1999 | 7/9/1999 | 7/8/1999 | A | FAIL |
Jim Sly
|
|
|
07/09/99 316 - Talked about temp occ
|
INSP - Framing/Rough-in | 5/6/1999 | 5/6/1999 | 5/6/1999 | P | FAIL |
Jim Sly
|
|
|
05/06/99 316 - Conf....C/N...Plans call for Spec insp of masonry..Need a
|
INSP - Foundation | 12/21/1998 | 12/21/1998 | 12/21/1998 | | PART |
Jim Sly
|
|
|
/ / 316 - FOUND OK PENDING SPECIAL INSPECTION APPROVALS.
|
INSP - Framing/Rough-in | 12/18/1998 | 12/18/1998 | 12/18/1998 | P | FAIL |
Jim Sly
|
|
|
12/18/98 316 - Not ready for frame
|
INSP - Foundation | 12/16/1998 | 12/17/1998 | 12/17/1998 | P | PART |
Jim Sly
|
|
|
12/17/98 316 - Foot OK pending compaction, compression,& bar special ins
|
INSP - Foundation | 12/15/1998 | 12/16/1998 | 12/16/1998 | A | FAIL |
Jim Sly
|
|
|
12/16/98 316 - Builderr cancelled
|
INSP - Foundation | 12/10/1998 | 12/10/1998 | 12/10/1998 | | PART |
Jim Sly
|
|
|
12/10/98 316 - Foot/found OK pending letter of approval from Engineer of
|
Plan Reviewer's activity | | | 12/2/1998 | | PASS |
|
|
|
Review of plan alteration at request of the inspector: Two feet was added to the 16 foot dimension of the building (now 18 feet) and glass block is deleted.
|
Plan resubmittals received | | | 11/24/1998 | | PEND |
|
|
|
Received resubmittals from CSHQA, Steve Benner, forwarded same to Arlan Smith. DAR 11/24/98
|
INSP - Foundation | 11/20/1998 | 11/23/1998 | 11/23/1998 | P | PART |
Jim Sly
|
|
|
11/23/98 316 - Footings OK pending special insp appr.
|
(F) Reprint permit | | | 10/29/1998 | | |
|
|
|
|
Plan assigned to (ADS) | 10/14/1998 | | 10/28/1998 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 10/28/1998 | | 10/28/1998 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 10/28/1998 | | |
|
|
|
|
Routing - PUBLIC WORKS | 10/28/1998 | | 10/28/1998 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/28/1998 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 10/28/1998 | | |
|
|
|
|
Print Occupancy Form | | | 10/28/1998 | | |
|
|
|
|
Routing - FIRE | 10/23/1998 | | 10/27/1998 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 10/27/1998 | | FAIL |
|
|
|
pw and UBC
|
Routing - PLANNING | 10/22/1998 | | 10/23/1998 | | PASS |
|
|
|
|
Routing - PLUMBING | 10/23/1998 | | 10/23/1998 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 10/23/1998 | | 10/23/1998 | | PASS |
|
|
|
structural calculation recieved.
|
Routing - PUBLIC WORKS | 10/16/1998 | | 10/22/1998 | | FAIL |
|
|
|
STREET LIGHTS ARE REQUIRED. A STREET LIGHT PLAN MUST BE SUBMITTED. HENRY ALARCON. 10/22/98 DAR
|
Plan resubmittals received | | | 10/20/1998 | | PEND |
|
|
|
RECEIVED RESUBMITTALS FROM CSHQA, STEVE BENNER, FORWARDED SAME TO ARLAN SMITH.
|
Plan resubmittals requested | | | 10/16/1998 | | |
|
|
|
Asked for cmu lintel detail, calculation, and if food is to be served from this building. Sent by fax & mail to architect.
|
Routing - PLAN CHECK | 10/14/1998 | | 10/16/1998 | | FAIL |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 10/14/1998 | | |
|
|
|
|
Plan resubmittals received | | | 10/14/1998 | | |
|
|
|
RECEIVED THREE COPIES OF SITE PLAN. ROUTED TO ARLAN S.
|
Received Certificate of Value | | | 10/14/1998 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/13/1998 | | PEND |
|
|
|
REQUIRES SITE PLAN. SPOKE TO ALLEN QUINTIERI ABOUT THIS NEED. HAVE A CALL INTO BRIAN M. ABOUT GRADING AND DRAINAGE. ALSO NEED DECLARATION FORM. 10-14-98 RECEIVED DECLARATION FORM. ROUTED TO ARLAN S. 10-14-98 RECEIVED THREE COPIES OF SITE PLAN ROUTED TO ARLAN S.
|
Application received | | | 10/13/1998 | | |
|
|
|
|