Fee Review-notes | 11/23/1998 | | 11/22/1999 | | DONE |
|
|
|
|
Receive PAYMENT IN FULL | | | 10/5/1999 | | DONE |
|
|
|
|
INSP - Final | 6/1/1999 | 6/2/1999 | 6/2/1999 | P | PASS |
Carl Dependahl
|
|
|
06/02/99 340 - ryan ###-####; ok, card tocont.
|
Code Occupancy Approval | | | 6/2/1999 | | PASS |
|
|
|
aLL CONDITIONS OF OLD DR HAVE BEEN MET, FINAL SIGNED OFF.
|
Letter of compliance | | | 6/2/1999 | | PASS |
|
|
|
Letter of Compliance #16585 issued 6-2-99.
|
Code Occupancy Approval | | | 6/1/1999 | | |
|
|
|
Final requested by Ryan Smith 870=0362
|
INSP-Final Inspection | 5/27/1999 | 5/27/1999 | 5/27/1999 | P | PASS |
Joe Tawney
|
|
|
05/27/99 406 - REINSP OK FOR CERT OF COMPLETION
|
INSP-Conference | 3/22/1999 | 3/22/1999 | 3/22/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - CONF ABOUT ALARM SYSTEM FOR S/F DAMPERS
|
INSP-Conference | 3/22/1999 | 3/22/1999 | 3/22/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - CONF ABOUT ALARM SYSTEM FOR S/F DAMPERS
|
INSP-Conference | 3/22/1999 | 3/22/1999 | 3/22/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - CONF ABOUT ALARM SYSTEM FOR S/F DAMPERS
|
INSP-Conference | 3/22/1999 | 3/22/1999 | 3/22/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - CONF ABOUT ALARM SYSTEM FOR S/F DAMPERS
|
INSP-Alarm Testing | 3/4/1999 | 3/4/1999 | 3/4/1999 | | FAIL |
Joe Tawney
|
|
|
03/04/99 406 - FINAL FAIL ALARM SUBM, ADDRESS, FIRE EXT,AL TEST
|
INSP - Wall cover | 2/15/1999 | 2/17/1999 | 2/17/1999 | A | FAIL |
Carl Dependahl
|
|
|
02/17/99 340 - Scheduled by Hello!. fail, seal 1hr pen's, wrap cols, etc
|
INSP - Conference | 1/6/1999 | 1/6/1999 | 1/6/1999 | | PART |
|
|
|
/ / 338 - ON SKYLIGHTS AD THE RECESSED LIGHTING IN THE TUNNEL CORRIDOR
|
INSP - Wall cover | 12/30/1998 | 12/31/1998 | 12/31/1998 | A | PART |
Russ Owen
|
|
|
12/31/98 407 - partial inspection of hallway ceiling recess construction
|
INSP - Wall cover | 12/17/1998 | 12/18/1998 | 12/18/1998 | A | PART |
|
|
|
12/18/98 338 - conf on the light fixture penetration of the corridor cei
|
INSP - Wall cover | 12/14/1998 | 12/15/1998 | 12/15/1998 | P | PART |
|
|
|
12/15/98 338 - made ok to cover with other agencies approval
|
Plan resubmittals received | | | 11/30/1998 | | PEND |
|
|
|
RECEIVED RESUBMITTALS FROM HUMMEL ARCHITECTSPASSED SAME TO PERRY PAINE. DAR 11/30/98
|
INSP - Framing/Rough-in | 11/23/1998 | 11/23/1998 | 11/23/1998 | P | PART |
|
|
|
11/23/98 338 - rob sower- ###-#### -insp walls & lighting madeok need wo
|
Telephone call | | | 11/12/1998 | | |
|
|
|
CALLED DEBBIE GAVE DOLLAR AMOUNT
|
Inspection Record Card- Bld | | | 11/12/1998 | | |
|
|
|
|
Print Occupancy Form | | | 11/12/1998 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 11/12/1998 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/10/1998 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 11/9/1998 | | 11/10/1998 | | PASS |
|
|
|
|
Plan assigned to (CJW) | 10/21/1998 | | 11/10/1998 | | PASS |
Carl Westfall
|
|
|
11/10/98 16:48:08 CJW - this action updated by action script from <<>> in Case No. BLD98-3241
|
Plan Review Completed(1st rev) | | | 11/9/1998 | | PASS |
|
|
|
|
Routing - FIRE | 11/5/1998 | | 11/9/1998 | | PASS |
|
|
|
need alarms
|
Print permit w/o conditions | | | 11/4/1998 | | |
|
|
|
|
testing condition printout | | | 11/4/1998 | | |
|
|
|
|
Routing - PLAN CHECK | 10/22/1998 | | 11/4/1998 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 10/28/1998 | | PASS |
|
|
|
UBC plan review started October 28, 1998 and finished November 4, 1998. The drawings were approved with conditions. See conditions list.
|
Routing - PUBLIC WORKS | 10/21/1998 | | 10/22/1998 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 10/21/1998 | | |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Application received | | | 10/19/1998 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/19/1998 | | PEND |
|
|
|
|