Case Summary (BLD) | | | 9/18/2014 | | DONE |
|
|
|
|
INSP - Foundation | 8/16/1999 | 8/17/1999 | 8/17/1999 | A | PASS |
Alan Hauser
|
|
|
08/17/99 350 - as per eng'g
|
INSP - Final | 7/28/1999 | 7/28/1999 | 7/28/1999 | P | PASS |
Jim Sly
|
|
|
07/28/99 316 - OK for perm occ
|
Permanent Occupancy | | 7/28/1999 | 7/28/1999 | | DONE |
|
|
|
|
Permanent occupancy | | | 7/28/1999 | | PASS |
|
|
|
PERMANENT OCC. #7850 issued 7-28-99 to Dr. Cynthia McKim.
|
Code Occupancy Approval | | | 7/26/1999 | | PASS |
|
|
|
Meets compliance with DR-98-0151
|
INSP - Final | 7/20/1999 | 7/21/1999 | 7/21/1999 | A | CANC |
Tom Arcoraci
|
|
|
07/21/99 408 - DONE BY 316
|
INSP - Final | 7/21/1999 | 7/21/1999 | 7/21/1999 | | FAIL |
Jim Sly
|
|
|
/ / 316 - C/N....DRAINAGE AND 6" CLEARANCE SOIL...
|
Code Occupancy Approval | | | 7/21/1999 | | |
|
|
|
Temporary Occupancy Requested by Tim Wilson ###-####
|
INSP-Final Inspection | 7/19/1999 | 7/19/1999 | 7/19/1999 | P | PASS |
Joe Tawney
|
|
|
07/19/99 406 - REINSP OK FOR PERM OCC
|
INSP-Final Inspection | 7/8/1999 | 7/8/1999 | 7/8/1999 | P | FAIL |
Joe Tawney
|
|
|
07/08/99 406 - FINAL FAIL SUITE NMBR, SINK WRAP, FIRE EXT, PAINT CURB
|
INSP - Framing/Rough-in | 4/23/1999 | 4/26/1999 | 4/26/1999 | A | PASS |
Jim Sly
|
|
|
04/26/99 316 - Framing and doors in draftstop OK
|
INSP - Framing/Rough-in | 4/23/1999 | 4/23/1999 | 4/23/1999 | | PASS |
Jim Sly
|
|
|
/ / 316 -
|
INSP - Framing/Rough-in | 4/21/1999 | 4/22/1999 | 4/22/1999 | A | FAIL |
Jim Sly
|
|
|
04/22/99 316 - C/N....Misc truss, doors draftstop, Shear nailing
|
Plan resubmittals received | | | 4/9/1999 | | |
|
|
|
RECEIVED TWO COPIES OF SHEET P-1 ROUTED TO JIM SLY. KMM
|
INSP - Foundation | 3/2/1999 | 3/3/1999 | 3/3/1999 | A | PASS |
Tom Arcoraci
|
|
|
03/03/99 408 - wall\\###-#### WALL OK LETTER FROM ACRH CHANGEING TO 2500 PSI
|
INSP - Foundation | 2/23/1999 | 2/24/1999 | 2/24/1999 | P | PART |
Jim Sly
|
|
|
02/24/99 316 - C/N...Footing with bar OK per plan...Need letter Architec
|
Issue PAID IN FULL permit | | | 2/17/1999 | | |
|
|
|
|
Telephone call | | | 2/17/1999 | | PASS |
|
|
|
talked to brian wilson to verify plans are ready
|
Print Occupancy Form | | | 2/17/1999 | | |
|
|
|
|
Inspection Record Card- Bld | | | 2/17/1999 | | |
|
|
|
|
Plan assigned to (MLO) | 1/29/1999 | | 2/16/1999 | | PASS |
Mike Otto
|
|
|
PLAN MODIFICATION APPROVED 02-16-99. MLO
|
Plan resubmittals received | | | 2/16/1999 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM LARRY KNOPP, ARCHITECTS, FORWARDED SAME TO MIKE OTTO.
|
Routing - PLAN CHECK | 2/16/1999 | | 2/16/1999 | | PASS |
|
|
|
modification approved.
|
Routing - PLAN CHECK | 2/12/1999 | | 2/12/1999 | | FAIL |
|
|
|
INCORRECT FLOOR PLAN SHEETS SUBMITTED. ARCHITECT NOTIFIED. MLO
|
Plan resubmittals requested | | | 2/12/1999 | | FAIL |
|
|
|
ARCHITECT NOTIFIED BY PHONE. INCORRECT FLOOR PLAN SUBMITTED. MLO
|
Routing - FIRE | 2/8/1999 | | 2/10/1999 | | PASS |
|
|
|
|
Routing - PLANNING | 1/29/1999 | | 2/8/1999 | | PASS |
|
|
|
|
Routing - PLUMBING | 2/8/1999 | | 2/8/1999 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 2/8/1999 | | 2/8/1999 | | PASS |
|
|
|
|
Routing - PLANNING | 1/29/1999 | | 2/5/1999 | | PASS |
|
|
|
|
Plan resubmittals received | | | 2/2/1999 | | |
|
|
|
RECEIVED THREE COPIES OF REVISED SHEETS A2 AND A3. ROUTED TO MIKE O. FOR MODIFICATION. KMM
|
Plan Modification Accepted | | | 1/29/1999 | | |
|
|
|
|
SUPER- Supervisor's review | 1/15/1999 | 1/15/1999 | 1/15/1999 | | PEND |
|
|
|
Received plan resubmittals. Resumbmittal involved deletion of basement and 100sq.ft of main level. Plan review informed me this was amayor change and contractor had to see them. Informed contractor.
|
(F) Reprint permit | | | 1/7/1999 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 1/6/1999 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/14/1998 | | PASS |
|
|
|
|
Telephone call | | | 12/14/1998 | | |
|
|
|
CALLED PERMIT READY
|
Routing - PLAN CHECK | 12/11/1998 | | 12/14/1998 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 12/14/1998 | | |
|
|
|
|
Print Occupancy Form | | | 12/14/1998 | | |
|
|
|
|
Plan assigned to (MLO) | 10/22/1998 | | 12/14/1998 | | PASS |
Mike Otto
|
|
|
|
Plan resubmittals received | | | 12/11/1998 | | PASS |
|
|
|
|
Telephone call | | | 12/3/1998 | | PEND |
|
|
|
CONTACTED ARCHITECTS OFFICE REGARDING STRUCTURAL CALCS FOR FLOOR SYSTEM NOT INCLUDED WITH RESUBMITTAL. MLO
|
Plan resubmittals received | | | 11/24/1998 | | PEND |
|
|
|
Received plan resubmittals from Larry Knopps office forwarded same to Mike Otto. DAR 11/24/98
|
Routing - FIRE | 11/13/1998 | | 11/18/1998 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 11/13/1998 | | FAIL |
|
|
|
CORRECTIONS MAILED AND FAXED TO ARCHITECT. MLO
|
Routing - PLAN CHECK | 11/4/1998 | | 11/12/1998 | | FAIL |
|
|
|
|
Routing - PLUMBING | 10/30/1998 | | 11/4/1998 | | PASS |
|
|
|
|
Routing - PLANNING | 10/30/1998 | | 10/30/1998 | | PASS |
|
|
|
X-REF. DRH98-0151 and CUP###-####
|
Routing - PUBLIC WORKS | 10/22/1998 | | 10/27/1998 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 10/22/1998 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 10/22/1998 | | PASS |
|
|
|
|
Received Certificate of Value | | | 10/22/1998 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 10/22/1998 | | 10/22/1998 | | |
|
|
|
PER JOHN M. WE WILL DO ENG. IN HOUSE. KMM
|
Plan assigned to (MYS) | 10/21/1998 | | 10/22/1998 | | PASS |
Marlene Southard
|
|
|
|
Application received | | | 10/21/1998 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/21/1998 | | |
|
|
|
|