Information based on query as of Sunday, August 18, 2024.
Permit Information
Permit NumberBLD98-03628
StatusFinaled
Name VIEW POINTE BLDG (2ND FLR)
Site Address 1501 S FEDERAL WAY
Project NameVIEW POINT
Customer Number 
ePlanReviewNo
Description
(VIEW POINTE BLDG. - 2ND FLOOR) This building is not fire sprinkled. To remodel the 2nd floor (7,064 square feet) of an existing building for office use. Work includes modifying 2 existing restrooms to be accessible to the disabled, constructing interior nonbearing walls, installing a folding partition, and installing a suspended ceiling system all per approved drawings, engineering, and plan review conditions on file. PC-797-98 **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Letter of compliance  4/5/2001 DONE
Letter of Compliance #21460 issued 4-5-01.
FIRE-Final Inspection4/4/20014/4/20014/4/2001PPASS
DetailsRick Jackson
tammy ###-#### structural is also going out today exit to rear of building complete 4/4/2001 3:34:18 PM
BLD-Final4/4/20014/4/20014/4/2001PCANC
DetailsJoe Tawney
Canceltammy ###-#### fire is also going out today 4/5/2001 8:29:11 AM
Print Occupancy Form  3/30/2001 DONE
Fee Review-notes12/18/1998 8/24/1999
SUPER- Supervisor's review4/1/19994/1/19994/1/1999
finish still in progress. story ok partial. and rick jackson finishing up
SUPER- Supervisor's review2/16/19992/16/19992/16/1999
finish still in progress, mec duct dampers smoke fire in corridor walls ok
INSP - Final1/29/19991/29/19992/1/1999PPART
DetailsJim Storey
01/29/99 301 - TEMP OCC OK
INSP-Final Inspection1/29/19991/29/19991/29/1999PPART
DetailsRick Jackson
KEN ###-#### temp occ approved, complete exit out rear
INSP-Alarm Testing1/28/19991/28/19991/28/1999APASS
DetailsRick Jackson
verified duct detector/AHU shut down/damper operation - all installed per plans. this is a local alarm only
INSP-Alarm Testing1/25/19991/26/19991/26/1999ACANC
DetailsRick Jackson
01/26/99 409 - JAMIE...###-#### cancelled by general contractor - will reschedule
SUPER- Supervisor's review1/26/19991/26/19991/26/1999
fire damper locations reviewd with mec contractor and structural inspector. smoke fire required
INSP - Framing/Rough-in1/25/19991/25/19991/25/1999PPASS
DetailsJim Storey
01/25/99 301 - FRAM-OK FRAMING c/n on ceilling 2nd floor.
SUPER- Supervisor's review1/20/19991/20/19991/20/1999
demo in mechanical area and drains in ok
INSP - Framing/Rough-in1/14/19991/15/19991/15/1999APART
DetailsTom Arcoraci
01/15/99 408 - KEN ###-#### 2nd floor shafts ok to cover
SUPER- Supervisor's review1/12/19991/12/19991/12/1999
new exit way (passage) to include ceiling for fire resistive, current ceiling will not meet requirements
SUPER- Supervisor's review1/11/19991/11/19991/11/1999
walk through jerry teal carl westfall jim storey dave lightfoot. reviewed construction and new exit installation pattern
SUPER- Supervisor's review1/8/19991/8/19991/8/1999 PEND
Review of 2hr shaft.
INSP-Conference1/8/19991/8/19991/8/1999APART
DetailsRick Jackson
discussed/reviewed items for 2nd floor occ. requested alarm plans from general contractor.
INSP - Framing/Rough-in12/21/199812/21/199812/22/1998PPART
DetailsJim Storey
12/21/98 301 - partion walls ok for cover pending ele approval.
Plan assigned to (CJW)11/24/1998 12/18/1998 PASS
DetailsCarl Westfall
12/18/98 12:58:37 CJW - this action updated by action script from <<>> in Case No. BLD98-3628
Routing - PLAN CHECK12/8/1998 12/18/1998 PASS
Print permit w/o conditions  12/18/1998
testing condition printout  12/18/1998
Plan Reviewer's activity  12/18/1998 PASS
Drawings approved, with conditions, after resubmittal review.
PLANS/APPL TAKEN TO FRONT DESK  12/18/1998 PASS
Issue PAID IN FULL permit  12/18/1998
Telephone call  12/18/1998
CALLED PERMIT READY
Print Occupancy Form  12/18/1998
Inspection Record Card- Bld  12/18/1998
Plan resubmittals received  12/16/1998 PEND
RECEIVED RESUBMITTALS AND FORWARDED SAME TO CARL WESTFALL DAR. 12/16/98
Routing - FIRE12/3/1998 12/7/1998 PASS
Plan Review Completed(1st rev)  12/7/1998 FAIL
UBC issues
Plan resubmittals received  12/7/1998 PEND
RECEIVED RESUBMITTALS FROM JERRY TEAL. FORWARDED SAME TO CARL WESTFALL. DAR 12/07/98
Routing - PLAN CHECK11/30/1998 12/3/1998
Plan Reviewer's activity  12/1/1998
UBC plan review started December 1, 1998 and finished December 3, 1998. A response from the architect is required. See the conditions list.
Routing - PUBLIC WORKS11/24/1998 11/30/1998 PASS
Plan routing begun/TENANTS  11/24/1998
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
Plan assigned to (MYS)11/20/1998 11/24/1998
DetailsMarlene Southard
Recd Pcfee & Taken To Pln CK  11/20/1998
Application received  11/20/1998 PASS
Plans ACCEPTED BY PLAN TECH  11/20/1998 PASS