Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD98-03661
StatusFinaled
Name Y M C A
Site Address 1050 W STATE ST
Project NameYMCA
Customer Number 
ePlanReviewNo
Description
ADDITIONS AND MODIFICATIONS TO THE EXISTING PARKING SITE AND YMCA BUILDING. WORK TO INCLUDE A REMODEL OF THE EXISTING BUILDING AND TO CONSTRUCT TWO ADDTITIONS TO THE EXISTING BUILDING WHICH INCLUDES NEW SWIMMING POOL, EXCERCISE ROOMS, MECHANICAL ROOMS, CONFERENCE ROOM AND LOCKER ROOM. THE UPGRADE TO THE EXISTING BUILDING WILL CHANGE THE TYPE OF CONSTRUCTION TO TYPE III-1HR. ALL WORK IS PER APPROVED PLANS AND ATTACHMENTS. DRH98-0136, CUP98-72, PC#802-98 THIS BUILDING IS FULLY FIRE SPRINKLERED FOR AN AREA INCREASE. STATE ST. ADDITION WILL BE ONE STORY WITH A BASEMENT AND MEZZANINE, WASHINGTON ST. WILL BE TWO STORY WITH AN OCCUPIED ROOF.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  12/11/2009 DONE
Case Summary (BLD)  6/15/2009 DONE
Case Summary (BLD)  6/4/2004  
Fee Review-notes6/20/20036/20/20036/20/2003 DONE
Permanent occupancy  8/3/2001 DONE
Perm. Occ. Cert. #8780 issued 8-3-01 to the YMCA.
Permanent Occupancy 8/2/20018/2/2001 DONE
Details
BLD-Conference6/7/20016/7/20016/7/2001APASS
DetailsCarl Dependahl
Added by Inspector: 340 On 6/7/2001 8:34:40 AM ok to delete panic at activity rm... floor area is marginal & largely occupied by semi-fixed tables; consulted w/ Mike Otto. Also rec'd eng's & spec. insps reports ok. 6/7/2001 8:35:15 AM
BLD-Final6/6/20016/7/20016/7/2001APASS
DetailsCarl Dependahl
###-####
BLD-Conference6/6/20016/6/20016/6/2001PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 6/6/2001 3:53:49 PM w/ Jordan Wilcomb re final
BLD-Conference5/21/20015/21/20015/21/2001PPASS
DetailsCarl Dependahl
Added by Inspector: 340 On 5/21/2001 3:57:25 PM no final til eng's letters approved
BLD-Conference5/1/20015/1/20015/1/2001PPART
DetailsCarl Dependahl
Added by Inspector: 340 On 5/1/2001 4:39:07 PM w/ arch re c/n
BLD-Final4/24/20014/25/20014/25/2001AFAIL
DetailsCarl Dependahl
###-####; c/n, need panic at doors from rm 107 & eng's /spec insp's affidavits. 4/25/2001 2:01:42 PM
Code Occupancy Approval  4/24/2001 PASS
Passed today. Jim (Jordan Wilcomb) ###-####
FIRE-Final Inspection2/14/20012/16/20012/16/2001APASS
DetailsRick Jackson
###-####
FIRE-Final Inspection10/23/200010/31/200010/31/2000AFAIL
DetailsRick Jackson
FIRE FN -JIM ###-#### c/n issued 10/31/2000 11:13:41 AM
Code Occupancy Approval  10/4/2000 FAIL
Still need to complete: 2 planters at NE cor. (10th St) neaar trailer. Concrete at north end of parking along 11th st.Gate (screening) at area being used as "dumpster enclosure" and screen gas mec. at the wast side of bldg. (10th St.).
BLD-Framing/Rough-in9/18/20009/19/20009/19/2000APART
Details
###-#### ceiling grid ceiling. rated ok on the 2nd floor rated 9/19/2000 9:58:38 AM
FIRE-Conference9/13/20009/14/20009/14/2000APART
DetailsRick Jackson
###-#### okay to occupy the womens locker and roof playground. 9/14/2000 9:48:45 AM
Additional plans submitted  9/13/2000  
RECEIVED SMALL DOCUMENTS FROM ROBERT HOWARD, HOSFORD, LARSON, RUDEEN, FORWARDED SAME TO PERRY PAINE. 9/13/00 DAR
BLD-Framing/Rough-in9/8/20009/11/20009/11/2000AFAIL
Details
###-#### 2nd floor rated ceiling, must follow eng to the letter, c/n issued 9/12/2000 10:01:54 AM
BLD-Other12/15/200012/15/20009/9/2000 DONE
After consult with m otto I approved 81/2 by 11 submittals for the area "b" classroo 183 through old storage room closing off exist 2nd exit etc..pep 12/15/2K
BLD-Conference9/6/20009/7/20009/7/2000APART
Details
FOR CONF JIM-- ###-#### must review with m otto 9/7/2000 3:13:30 PM
FIRE-Conference9/1/20009/1/20009/1/2000PPART
DetailsRick Jackson
###-#### Jim checked life safety for the new pool area; exits and alarms okay. gave approval to use the pool effective 9/5/00 9/1/2000 2:41:49 PM
BLD-Conference8/28/20009/1/20009/1/2000APART
Details
###-#### madeok to occ upy the pool area 9/1/2000 4:05:52 PM
FIRE-Conference8/28/20008/31/20008/31/2000APART
DetailsRick Jackson
###-#### diwscussed requireements of opening pool area 8/31/2000 10:54:13 AM
BLD-Framing/Rough-in8/23/20008/24/20008/24/2000APART
Details
JIM ###-#### CEILING GRID ceiling room adj to the pool 8/24/2000 10:15:17 AM
BLD-Framing/Rough-in8/1/20008/2/20008/2/2000APART
Details
Jim ###-#### on the type of assy to use on the 2nd floor corridor assy 8/2/2000 10:41:16 AM
FIRE-Conference7/31/20008/2/20008/1/2000APART
DetailsRick Jackson
###-#### Jim okay to occupy basement offices 8/1/2000 3:36:06 PM
Plan resubmittals received  7/27/2000 DONE
RECEIVED ONE COPY OF PROPOSAL REQUEST FOR A NEW RATED GYPSUM SHAFTWALL CEILING IN CORRIDOR 203. ROUTED TO PERRY. KMM
BLD-Framing/Rough-in7/25/20007/26/20007/26/2000APART
Details
JIM ###-#### FR on the stair rated ceiling system. 7/26/00 11:13:10 AM
BLD-Framing/Rough-in7/17/20007/18/20007/18/2000PCANC
DetailsRuss Owen
###-####
FIRE-Conference7/17/20007/18/20007/18/2000PPART
DetailsRick Jackson
###-#### Do not occupy basement until 1hr corridor is complete 7/19/00 10:07:22 AM
FIRE-Conference7/17/20007/18/20007/18/2000PPART
DetailsRick Jackson
###-####
FIRE-Conference7/13/20007/14/20007/14/2000APART
DetailsRick Jackson
###-####; okay to occupy the cardio vascular room
FIRE-Conference7/7/20007/10/20007/10/2000APART
DetailsRick Jackson
Jim ###-#### REquirements to open cardio room- exit sign; proper stores; exit path unobstructed; C/N issued. 7/11/00 11:38:38 AM
BLD-Framing/Rough-in6/30/20007/3/20007/3/2000APART
Details
###-#### ceiling grid ceiling made ok to drop in tiles igh ceiling adj to the pool 7/6/00 2:00:20 PM
BLD-Framing/Rough-in6/26/20006/26/20006/26/2000PPART
Details
###-#### ceiling grid ceilings in the 1st and bsmt verbal need to confirm all slack wireing 6/27/00 4:31:18 PM
BLD-Framing/Rough-in6/19/20006/19/20006/19/2000APART
Details
Scheduled by Inspector: 338 On 6/19/00 ceiling grid jim made ok with other agencies approvals 6/20/00 10:19:01 AM
BLD-Framing/Rough-in6/14/20006/15/20006/15/2000ACANC
Details
jim ###-#### ceiling grid insp out of time 6/19/00 6:50:08 AM
BLD-Framing/Rough-in5/31/20005/31/20005/31/2000PPASS
Details
CEILING GRID--- JIM ###-#### ok to drop in the tiles 5/31/00 4:41:24 PM
FIRE-Conference5/17/20005/18/20005/18/2000PPART
DetailsRick Jackson
jim ###-#### fire conf--around 1:00 Okay to occupy front lobby office area. 5/22/00 9:01:08 AM
BLD-Framing/Rough-in4/24/20004/24/20004/24/2000PPART
Details
ceiling grid jim ###-#### ok to dropin the tiles for the new gymnewhall ok 4/24/00 2:35:50 PM
FIRE-Final Inspection4/24/20004/24/20004/24/2000PFAIL
DetailsRick Jackson
reinspection jim ###-#### Conference to determine criteria to use new gymnasium. 4/26/00 11:58:05 AM
BLD-Framing/Rough-in4/20/20004/21/20004/21/2000APART
Details
ceiling grid---jim ###-#### c/n issued slack wires required on diffusers or attach positively to the main runner or crosstee that is supported by wires 04/21/2000 10:33:48 AM
BLD-Framing/Rough-in4/11/20004/12/20004/12/2000PPART
Details
###-#### ceiling oktto drop in tiles with secure of the diffusers (no caddy clips) gym ceiling 04/12/2000
BLD-Conference3/28/20003/29/20003/29/2000APART
Details
###-#### with jim (jw) robert (hlr) and myself conf on the occupancy of the new 2nd floor gym for the temp exercise room, will be ok to use if there are two complete exits. also.discussed the use of existing doors in rated walls, if doors are moved they must be replaced; all doors are to have approved hardware aemblies; all glazing is to be in proper frames... 3/30/00 10:04:22 AM
FIRE-Final Inspection3/28/20003/29/20003/29/2000PFAIL
DetailsRick Jackson
###-#### Not a final- ok to occupy west activity room. 3/30/00 11:02:29 AM
Telephone call  3/23/2000 DONE
left message with bob and Perry
BLD-Framing/Rough-in3/21/20003/22/20003/22/2000APART
Details
ceiling grid Jim ###-#### ceiling grid at main level entry 03/22/2000 2:00:14 PM
FIRE-Final Inspection3/16/20003/17/20003/17/2000AFAIL
DetailsRick Jackson
JIM ###-#### FIRE FN Not a final inspection- conferencce. 3/20/00 10:27:52 AM
BLD-Framing/Rough-in3/9/20003/9/20003/9/2000PFAIL
Details
jim ###-#### c/n issued confirn F R of the display cabinets in wall between RR-163 and corridor158...stasir 143 ..94ubc sec 1009.3 pp 1no piping other than standpipe etc allowed. 3/9/00 10:41:08 AM
FIRE-Conference3/7/20003/7/20003/7/2000PPART
DetailsRick Jackson
jim ###-#### fire conf fire extinguisher placement with architect. 3/8/00 10:09:19 AM
BLD-Framing/Rough-in3/2/20003/2/20003/2/2000PPART
Details
jim ###-#### fr ok to cover behind ele mech and plmg this area 3/2/00 3:48:54 PM
BLD-Framing/Rough-in2/24/20002/25/20002/25/2000PPART
Details
###-####
FIRE-Sprinkler Rough-in2/10/20002/11/20002/11/2000PPART
DetailsRick Jackson
jim ###-#### ; need 1 hour corridor to use north addition
BLD-Framing/Rough-in2/2/20002/3/20002/3/2000APART
Details
jim ###-#### made ok to cover tis selected area 2/14/00 11:13:01 AM
FIRE-Conference2/3/20002/3/20002/3/2000 PART
DetailsRick Jackson
discussed location of annunciator panel
BLD-Framing/Rough-in1/26/20001/27/20001/27/2000PPART
Details
ceiling grid \###-#### made ok to drop in tiles this area 1/27/00 6:33:47 PM
BLD-Other1/6/20001/11/20001/11/2000APASS
Details
jobsitewalkthrough with arch and contr.about handrails and fire resistive req for saunas
BLD-Conference1/6/20001/11/20001/11/2000APASS
Details
###-####- jim for conf with architects and the contractor on stairrails and for combustability of cedar in saunas
BLD-Conference1/6/20001/6/20001/6/2000APASS
Details
with john larsen to set up time for walk through an tues 1/11/00 with all parties involved.
BLD-Framing/Rough-in12/21/199912/22/199912/23/1999PPART
Details
jim ###-####. Ok to cover.
FIRE-Sprinkler Rough-in12/22/199912/22/199912/22/1999PPART
DetailsRick Jackson
special needs and janitor closet okay to cover
FIRE-Conference12/14/199912/14/199912/14/1999PPART
DetailsRick Jackson
jim ###-#### conf To use new locker room- exiting requirements must be required before using.
BLD-Conference12/9/199912/9/199912/9/1999PPART
Details
jim ###-#### Received plan schedule for phased occupancy.
Telephone call  11/22/1999 DONE
called ###-####3. Left message with receptionist for Bob Howard.
Routing - PLAN CHECK11/10/1999 11/19/1999 PASS
plan modifications ok.
Plan Reviewer's activity  11/19/1999 PASS
memo sent to inspector regarding approval of modifications and that four hour column protection at exterior columns at entrance walk-way has been eliminated in accordance with board of appeals ruling of 9-22-1999. mlo
BLD-Framing/Rough-in11/16/199911/17/199911/17/1999PPART
Details
JIM ###-#### made ok for 2nd floor ceiling frame around elevator shaft.
Routing - PLUMBING10/25/1999 11/10/1999 PASS
PLAN MODIFICATION PLAN REVIEW
BLD-Framing/Rough-in11/9/199911/9/199911/9/1999PPART
Details
JIM-- ###-#### -CEILING GRID INSP Ok to drop in ceiling tiles basement room ok to cover outside of Ele. Shaft @ W side.
BLD-Foundation11/2/199911/3/199911/3/1999APART
Details
grid line A 7-3 made ok w/sp insp approval.
Routing - PUBLIC WORKS10/15/199910/15/199910/25/1999 PEND
PLAN MODIFICATION PLAN REVIEW
Plans ACCEPTED BY PLAN TECH  10/15/1999 PEND
PLAN MODIFICATION PREPARED FOR ROUTING. 10/15/99 DAR
Plans ACCEPTED BY PLAN TECH  10/15/1999  
BLD-Conference10/12/199910/14/199910/14/1999APART
Details
at 9 am Jim ###-#### Smoke conf. Post poned until 10/18/99
Plan resubmittals received  10/14/1999 PEND
RECEIVED PLAN RESUBMITTALS FROM HOSFORD LARSON RUDEEN, FORWARDED SAME TO PERRY PAINE. 10/14/99 DAR
Plan resubmittals received  10/14/1999 PEND
RECEIVED PLAN MODIFICATION APPLICATION AND PLANS FROM HOSFORD LARSON RUDEEN,FORWARDED SAME TO PERRY PAINE. 10/14/99 DAR
Plan Modification Accepted  10/14/1999 PASS
modification completed on 11/19/1999. mlo
CHANGE STATUS TO (F)  10/13/1999 DONE
Appeal filed and lost by applicant - appeal fee of $50.00 added 10/13/99.
Receive PAYMENT IN FULL  10/13/1999 DONE
MISC ACTIONS  10/12/1999 DONE
added a plan modification fee $500.00
BLD-Concrete9/27/19999/27/19999/27/1999PPART
Details
JIM-- ###-####--REBAR & CONCRETE--GRID LINE A LINE FROM 12 TO 7 Made ok with sp. Msp. Approval
BLD-Conference9/23/19999/24/19999/24/1999APART
Details
JIM-- ###-#### CONF Jim/JW Bob H/Larson stair #172 A2.15 address light box penetration
INSP - Conference9/8/19999/10/19999/10/1999APART
Details
ONSITE CONFERANCE, JIM and moke otto walked jobsite and discusses lifesafety and exiting requirements and for the protection of the building occupants during construction ###-####
INSP - Foundation9/8/19999/9/19999/9/1999APART
Details
REBAR AND CONCRETE, GRID LINE 12, D-A, JIM ###-#### sp insp made ok
SUPER- Supervisor's review9/3/19999/3/19999/3/1999
perry is watching this no constuction on walkway at this time
SUPER- Supervisor's review9/1/19999/1/19999/1/1999
support colums for exterior overhang are to be 4 hour per plan contractor is apealing
INSP - Concrete8/30/19998/31/19998/31/1999APART
Details
08/31/99 338 - REBAR POUR GRID LINE 12 D TO A JIM ###-#### SP INSP APP
Fee Review-notes4/2/1999 8/24/1999
AS PER MIKE OTTO PLEASE REVIEW FEES FOR MECH/PLUMBING 4/8/99 per jordan-wilcomb new cert. project value 5,659,963.00 lh
INSP - Concrete8/20/19998/20/19998/20/1999PPART
DetailsJim Storey
08/20/99 301 - JIM ###-####. GRID LINE 2 FROM D-C. covered by special in
Plan resubmittals received  8/20/1999 PEND
PLAN RESUBMITTALS RECEIVED FROM ROBERT HOWARD OF HOSFORD LARSON RUDEEN ARCHITECT, FORWARDED SAME TO DAVID LIGHTFOOT. 8/20/99 DAR DAVE LIGHTFOOT RETURNED PLANS STATING THE CHANGE WAS BEYOND WHAT HE HAD TALKED TO THE CONTRACTOR ABOUT. FORWARDED PLANS TO MIKE OTTO FOR A DETERMINATION ON HOW TO HANDLE THE RESUBMITTAL. 8/23/99 DAR
INSP - Concrete8/9/19998/10/19998/10/1999PPART
Details
08/10/99 338 - JIM ###-####. ENTERY WALLS OF NORTH ADDITION-SHEET F2 C ON S14. r-bar placed sp insp on site
INSP-Conference8/4/19998/4/19998/4/1999 PART
Received letter of transmittal from arch on the project for an appeal on fire protection rating of exterior columns. Per supervisor an appeal shall be taken to the appeals board. This paperwork is delivered to M. Southard.
INSP - Concrete7/28/19997/29/19997/29/1999PPART
Details
07/29/99 338 - MADE OK WITH SP INSP APPROVALS
Plan resubmittals received  7/28/1999 PASS
RECEIVED PLUMBING PLAN RESUBMITTALS FROM ELKHORN ENGINEERS. THEY WERE APPROVED BY GARY ZIEGLER. THEN ONE SET TO RECORD AREA AND ONE SET TO JOB SET TO JOB SITE VIA HOSFORD LARSON AND RUDEEN. 7/28/99 DAR DS
INSP - Foundation7/20/19997/21/19997/21/1999PPART
Details
07/21/99 338 - BEAMS AND FOUNDATION NORTH ADDITION JIM ###-#### made ok
INSP-Conference7/21/19997/21/19997/21/1999 PART
With Bob Howard, recieved details of the proposed tempory stairs from the natatorium when the doors at the southwest corner are made unsafe to use. Wood is allowed in this type of construction as long as it is of 2" nom thickness. All other requirements for the stairs must comply with ubc chap. 10. will relay answer on the forms submitted by fax and return by fax to arch. see file.
INSP-Conference7/21/19997/21/19997/21/1999PPART
Details
bob with the Arch, firm of Hosford-Larson-Rudeen with questions on the temp stairs at the pool area near the new elevator shaft. wood framing is acceptable as long as all codes for rise run, rails and landings comply. also confirmed that two (2) exits are required for the pool area if it is in use. Covered walkway protection may be required for the main exit from the pool area.
INSP - Foundation7/7/19997/8/19997/7/1999PPART
Details
REBAR JIM ###-#### COLUMN PADS 11.3 12 LINE AND N SP INSP MADE OK 338
INSP - Concrete6/28/19996/29/19996/28/1999PPART
Details
06/29/99 338 - grid line N and 8 and 9 made ok with sp insp approvals
Plan resubmittals received  6/24/1999 PEND
Received plan resubmittals from Hosford Larson Rudeen, forwarded same to Gary Ziegler. DAR 6/24/99
INSP - Foundation6/18/19996/21/19996/21/1999APART
Details
06/21/99 338 - Grid Line L and 6 Jim ###-#### ok with sp insp
Routing - FIRE6/11/1999 6/11/1999 FAIL
FIRE ALARM PLAN REVIEW ISSUES
INSP - Concrete6/9/19996/10/19996/10/1999APART
DetailsWes Worcester
06/10/99 342 - JIM ###-#### no answer, still tying bar,spec insp??? FOUN
INSP - Foundation6/3/19996/4/19996/4/1999APART
Details
06/04/99 338 - madeok to pour with sp insp approvals
INSP - Foundation6/2/19996/3/19996/3/1999APART
Details
06/03/99 338 - ###-####//REBAR FOOTING & WALL ON GRID 6 & L sp insp made
INSP - Foundation6/2/19996/2/19996/2/1999 PART
Details
06/02/99 338 - madeok conf with sp insp eng ctr and arch on concrete sch
INSP - Foundation6/2/19996/2/19996/2/1999 PART
Details
06/02/99 338 - conf on the concrete design placement and insp with arch,
Issue PAID IN FULL permit  4/9/1999
PLANS/APPL TAKEN TO FRONT DESK  4/2/1999 PASS
Print Occupancy Form  4/2/1999
Inspection Record Card- Bld  4/2/1999
Telephone call  4/2/1999
CALLED TALKED TO BOB GAVE DOLLAR AMOUNT TOLD HIM ABOUT ACHD
Plan assigned to (MLO)12/1/1998 4/2/1999 PASS
DetailsMike Otto
Routing - FIRE3/29/1999 4/1/1999 PASS
FIRE ALARMS ON DELAYED - NO ROUGH IN
Routing - PLAN CHECK3/29/1999 3/29/1999 PASS
Plan resubmittals received  3/26/1999 PEND
resubmittals for plan review received late PM.
Routing - FIRE3/24/1999 3/25/1999 FAIL
no or incomplete response to all 4 resubmittals
Routing Off Site - STRUCTURAL12/11/1998 3/24/1999 PASS
12-11-98 RECEIVED ONE COPY OF PLANS FOR OUTSIDE ENG. WITH ONE COPY OF PROJECT MANUAL. CONTACTED PDQ TO TAKE PLANS OUT TO ATWOOD, HINZMAN, AND JONES PER MIKE O. KMM
Plan resubmittals requested  3/24/1999 FAIL
CORRECTIONS MAILED AND FAXED TO ARCHITECT. MLO
Routing - PLAN CHECK3/17/1999 3/24/1999 FAIL
Plan resubmittals received  3/17/1999
RECEIVED THREE COPIES OF REVISED ARCHITECTURAL DRAWINGS THREE COPIES OF REVISED STRUCTURAL DRAWINGS THREE COPIES OF REVISED POOL DRAWINGS THREE COPIES OF REVISED MECH., PLUMB., AND ELECT. DRAWINGS ONE COPY OF ARCHITECTURAL RESPONSE LETTER ONE COPY OF MECH. RESPONSE LETTER ONE COPY OF ELECT. RESPPONSE LETTER ROUTED TO MIKE OTTO. KMM
Routing - FIRE3/2/1999 3/4/1999 FAIL
Plan Review Completed(1st rev)  3/4/1999 FAIL
ubc & UFC issues
Routing - PLAN CHECK2/12/1999 3/2/1999 FAIL
Plan resubmittals requested  3/2/1999 FAIL
CORRECTIONS MAILED TO ARCHITECT. MLO
Routing - PLANNING2/4/1999 2/12/1999 PASS
x-ref. DRH98-0136. Also subject to submittal of a revised landscape plan including landscaping along 11th Street and Forestry's comments per Design Review approval.
Routing - PLANNING2/4/1900 2/8/1999 PASS
Revised landscaping plan needs to be submitted reflecting Conditional Use Permit conditions, particularly sidewalk locations and landscaping along sidewalks. TAC 2/8/99
Routing - PLUMBING2/3/1999 2/4/1999 PASS
Routing - PUBLIC WORKS1/19/1999 2/3/1999 PASS
Routing Off Site - C.D.H11/27/1998 1/15/1999 PASS
12-11-98 RECEIVED A CALL FROM MR. LARSON ABOUT GETTING ADD. PLANS TO CDH SO WE COULD ROUTE ORIGINAL SET TO PW. I HAD MR. LARSON SPEAK WITH MIKE. MIKE STATED THAT WAS NOT OUR PROCEDURE. WE WILL KEEP AS IS. KMM
Received Certificate of Value  1/11/1999 PASS
Plan assigned to (JCM)11/24/1998 11/30/1998 PASS
DetailsJohn Menard
Plans ACCEPTED BY PLAN TECH11/27/1998 11/27/1998
Application received  11/24/1998
Plan assigned to (MYS)11/24/1998 11/24/1998 PASS
DetailsMarlene Southard
Recd Pcfee & Taken To Pln CK  11/24/1998