Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD98-03670
StatusFinaled
Name CARIBOU FOUR CORNERS INC
Site Address 4924 W OVERLAND RD
Project NameWALGREENS
Customer Number 
ePlanReviewNo
Description
TO CONSTRUCT A NEW SINGLE STORY, C.M.U. WITH BRICK VENEER, EXTERIOR WALL, 15,546 SQUARE FOOT, FULLY FIRE SPRINKLERED, RETAIL BUILDING, WITH DRIVE UP PHARMACY. THE INSTALLATION OF THE FIRE SPRINKLER SYSTEM IS BEING USED FOR AREA INCREASE. ALL CONSTRUCTION PER THE APPROVED PLANS, ATTACHED COMMENT LIST, CABO/ANSI A117.1 AND THE 1994 EDITION OF THE UBC. MJP (P.C.# 805-98) DR#98-0128, CU#98-0088,
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes3/3/1999 6/12/2000 DONE
Permanent Occupancy 10/22/199910/22/1999 DONE
Details
Permanent occupancy  10/22/1999 DONE
Perm. Occ. Cert. #7967 issued 10-22-99 to Walgreens.
BLD-Final10/20/199910/21/199910/21/1999PPART
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 10/20/1999 at 19:57:04. Contact: ###-####. Ok for C/O; card to contractor.
FIRE-Final Inspection10/21/199910/21/199910/21/1999PPART
DetailsJoe Tawney
Scheduled by a contractor via Hello! on 10/21/1999 at 09:41:43. Contact: ###-####. Reinsp. Ok for permanent occupancy.
BLD-Final10/19/199910/20/199910/20/1999PFAIL
DetailsCarl Dependahl
late pm???-- ###-#### fn occ keith Fire, P/Z, previous correction.
FIRE-Final Inspection10/20/199910/20/199910/20/1999PFAIL
DetailsJoe Tawney
tracy ###-#### Reinsp. Fail spklr. Bracing and Int. temp. spklr. Heads
Code Occupancy Approval  10/20/1999 PASS
ALL CONDITIONS OF DRH98-0128 HAVE BEEN MET, FINAL SIGNED OFF.
BLD-Final10/18/199910/18/199910/18/1999PFAIL
DetailsJoe Tawney
Reinsp. fail new C/N issued.
BLD-Conference10/13/199910/13/199910/13/1999APASS
DetailsCarl Dependahl
Resubmittal approved (general minor changes)
FIRE-Final Inspection10/7/199910/8/199910/8/1999AFAIL
DetailsJoe Tawney
HYDRA TEST FAILED FDC PIPING NOT INCLUDED IN TESTTim ###-####
BLD-Framing/Rough-in9/21/19999/21/19999/21/1999PPART
DetailsCarl Dependahl
grid ceiling ###-#### Keep C/N grid ok to continue
BLD-Other9/16/19999/17/19999/17/1999APART
DetailsCarl Dependahl
CONF. ONLY, NEED OTHER INSPCTNS
Other9/9/19999/10/19999/10/1999AFAIL
DetailsCarl Dependahl
keep c/n
INSP - Framing/Rough-in8/16/19998/16/19998/16/1999PPART
DetailsCarl Dependahl
08/16/99 340 - need clarification for rear " passage"...rated or not. ok
INSP - Framing/ Rough-in8/11/19998/11/19998/11/1999 PART
DetailsCarl Dependahl
/ / 340 - CONF W/ BLDR; OK TO COVER INT PART'S
INSP - Framing/Rough-in8/9/19998/10/19998/10/1999APART
DetailsCarl Dependahl
08/10/99 340 - need seal mansard from attic, firestop 1hr areas. ok to b
INSP - Framing/Rough-in8/2/19998/2/19998/2/1999P
DetailsJoe Tawney
BOB ###-#### STORM DRAINS
INSP - Framing/ Rough-in7/21/19997/21/19997/21/1999 PART
DetailsCarl Dependahl
/ / 340 - NEED ALL SPEC INSP REPORTS & ENG'S OK
INSP - Framing/ Rough-in7/14/19997/14/19997/14/1999 PART
DetailsCarl Dependahl
/ / 340 - MASONRY, SPEC INSP ONSITE
Plan resubmittals received  7/6/1999
RECEIVED TWO COPIES OF REVISED SHEETS A0.O, S1.1, A1.2, A3.1, D1, M1.1, P1.1, E1.1, E1.1E, E1.2, E1.4, E1.5, E1.6 ROUTED TO CARL D. KMM
INSP-Supply line flush6/22/19996/23/19996/23/1999APART
DetailsJoe Tawney
06/23/99 406 - OK ON SUPPLY LINE FLUSH
INSP - Foundation6/22/19996/22/19996/22/1999 PART
DetailsCarl Dependahl
/ / 340 - MASONRY SPEC INSP ONSITE
INSP - Foundation6/21/19996/21/19996/21/1999 PART
DetailsCarl Dependahl
/ / 340 - MASONRY, SPEC INSP ONSITE
INSP - Concrete6/3/19996/3/19996/3/1999PPART
DetailsCarl Dependahl
06/03/99 340 - Scheduled by Hello!. Contact phone is [8502262]. mti onsite, pend reports
INSP - Concrete6/3/19996/3/19996/3/1999 PART
DetailsCarl Dependahl
06/03/99 340 - mti onsite for masonry pend reports. Contact phone is [8
INSP - Foundation6/2/19996/2/19996/2/1999 PART
DetailsCarl Dependahl
06/02/99 340 - . Contact phone is [8502262]. mti onsite
INSP - Concrete6/1/19996/2/19996/2/1999APART
DetailsCarl Dependahl
06/02/99 340 - Scheduled by Hello!. Contact phone is [8502262]. pendins
INSP - Concrete6/2/19996/2/19996/2/1999 PART
DetailsCarl Dependahl
06/02/99 340 - Scheduled by Hello!. Contact phone is [8502262]. mti ons
INSP - Foundation5/28/19995/28/19995/28/1999PPART
DetailsCarl Dependahl
Scheduled by Hello!. Contact phone is [8502262]. mti onsite
INSP-Sprinkler Rough-in/Hydro5/27/19995/27/19995/27/1999 PART
DetailsJoe Tawney
/ / 406 - OK ON UNDERGROUND PIPING OK TO COVER
Plan resubmittals received  5/27/1999
RECEIVED TWO COPIES OF REVISED PLANS. ROUTED TO CARL D. KMM
INSP - Foundation5/26/19995/26/19995/26/1999PPART
DetailsCarl Dependahl
05/26/99 340 - Scheduled by Hello!. Contact phone is [8502262]. mti ons
INSP - Foundation5/24/19995/24/19995/24/1999PPART
Details
05/24/99 338 - made ok with sp insp approvals
INSP - Foundation5/20/19995/21/19995/21/1999PPART
DetailsCarl Dependahl
Scheduled by Hello!. Contact phone is [8502262]. MTI ONSITE, PENDING REPORTS. NEED SURVEYORS STATEMENT
INSP - Foundation5/20/19995/20/19995/20/1999PPART
DetailsCarl Dependahl
05/20/99 340 - mti onsitet phone is [8502262].
INSP - Foundation5/18/19995/19/19995/19/1999PPART
DetailsCarl Dependahl
05/19/99 340 - mti onsite, pend reports [8502262].
INSP - Foundation5/17/19995/18/19995/18/1999APART
DetailsCarl Dependahl
05/18/99 340 - met w/ supt; requested surveyor's letter, MTI onsite; nee
INSP - Foundation5/14/19995/17/19995/17/1999PPART
DetailsCarl Dependahl
05/18/99 340 - pend spec insp... phone is [8502262].
(F) Reprint permit  4/13/1999
(F) Reprint permit  4/9/1999
Issue PAID IN FULL permit  4/8/1999
Plan Reviewer's activity  4/7/1999 PASS
Routing - PLAN CHECK4/5/1999 4/7/1999
PLANS/APPL TAKEN TO FRONT DESK  4/7/1999 PASS
Print Occupancy Form  4/7/1999
Inspection Record Card- Bld  4/7/1999
Print Pending Permit.LaserJet4  4/7/1999 PASS
Telephone call  4/7/1999
called talked to cathy gave dollar amount told her we needed something from achd regarding impact fees
Plan assigned to (M_P)12/1/1998 4/7/1999 PASS
DetailsMike Phillips
04/07/99 08:12:11 M_P - this action updated by action script from <<>> in Case No. BLD98-3670
Routing - PUBLIC WORKS4/2/1999 4/5/1999 PASS
Plan resubmittals received  4/1/1999 PEND
RECEIVED SOILS AND FOUNDATION REPORT FROM ESI, KATHY THOMPSON. DAR 4/1/99
Plan Reviewer's activity  3/25/1999 FAIL
WAITING FOR SUBDIVISION AND SOILS REPORT.
Routing Off Site - STRUCTURAL2/22/1999 3/12/1999 PASS
REVISED PLANS THAT WERE RECEIVED 2-17-99 SENT TO OUT SIDE ENG. CONTACTED PDQ TO TAKE PLANS OUT. Received informaiton that structural review was completed.
Plan Reviewer's activity  3/9/1999
FAXING STRUCTURAL COMMENT TO ARCHITECT.
Routing - PUBLIC WORKS3/9/1999 3/9/1999 FAIL
NEEDS PROOF OF LEGAL LAND DIVISION. PER JIM RICH. ALSOPROOF OF LEGAL LAND DIVISION DAR 3/9/99
Routing - FIRE3/1/1999 3/2/1999 PASS
Routing - PLAN CHECK2/24/1999 3/1/1999
Routing to Fire for follow up review.
Plan resubmittals received  2/25/1999
RECEIVED FIVE COPIES OF REVISED SHEETS C-3 AND C-4. ROUTED TO MIKE P. KMM
Routing - PLANNING12/31/1998 2/24/1999 PASS
As noted on the plans and per conditions of DRH98-0128.
Routing - PLAN CHECK2/18/1999 2/18/1999
Routing - PUBLIC WORKS2/17/1999 2/18/1999 FAIL
PROOF OF LEGAL LAND DIVISON PER JIM R. KMM
Routing - PLAN CHECK1/8/1999 2/17/1999
Inserted resubmittals and routed to others for follow up review.
Routing - PLAN CHECK1/5/1999 2/17/1999
Plan Reviewer's activity  2/17/1999
Received two sets of plans. Phoned at asked Randy to submit third set for out side structural review.
Plan resubmittals received  2/16/1999
RECEIVED ONE COPY OF ITEMIZED RESPONSE LETTER FOR PLAN REVIEW OF 1-5-99. TWO COPIES OF COMPLETE REVISED DRAWINGS. ONE COPY OF RESPONSE LETTER TO FLOYD'S REVIEW OF 1-7-99 KMM 2-17-99 RECEIVED ONE COPY OF REVISED PLANS FOR OUTSIDE ENG. WHICH WAS THEN SENT TO OUTSIDE ENG. VIA PDQ. 2-18-99 KMM
Plan Review Completed(1st rev)  1/7/1999 FAIL
planning,UBC,UFC
Routing - FIRE1/5/1999 1/7/1999 FAIL
entrance gate does not comply
Plan resubmittals requested  1/5/1999 FAIL
ADDITIONAL INFORMATION REQUESTED.
Routing Off Site - STRUCTURAL12/2/1998 12/31/1998 FAIL
SENT PLANS, SOILS REPORT, STRUCTURAL CALCULATIONS AND PERMIT APPLICATIONS TO CH2MHILL. 12/02/98. 12-31-98 ROUTED RESPONSE TO MIKE P. Second review required by outside engineering firm. 01-04-99.
Routing - PLANNING12/29/1998 12/31/1998 PASS
AS PER CUP98-0088
Routing - PLUMBING12/24/1998 12/29/1998 PASS
Routing - PUBLIC WORKS12/18/1998 12/24/1998 FAIL
Routing Off Site - C.D.H12/7/1998 12/18/1998 PASS
Routing - PLAN CHECK12/1/1998 12/18/1998
Plan Reviewer's activity  12/4/1998
Particial review done. Waiting for structural comment to return from outside engineering firm prior to completion of review.
Application received12/1/1998 12/1/1998
Plans ACCEPTED BY PLAN TECH12/1/1998 12/1/1998
Plan assigned to (MYS)11/24/1998 12/1/1998
DetailsMarlene Southard
Application received  11/24/1998
Recd Pcfee & Taken To Pln CK  11/24/1998
Case Summary (BLD)