Permit Information
Permit NumberBLD98-03679
StatusFinaled
Name ST LUKES
Site Address 100 E IDAHO ST
Project NameST LUKES-5TH FRL
Customer NumberSTL960680
ePlanReviewNo
Description
To finish the entire 27,634 sq.ft. 5th floor of the SLRMC South Tower, for occupancy use as conference rooms, library, offices, classrooms and catering per approved plans on file. Work to include non-combustible framing, fire-code sheetrock covering, fire-resistive assemblies, ceiling systems, electrical, plumbing, mechanical, alarm and upgrade of srinkler system, all as required for the specific occupancies within a Type 1-F.R. constructed building. Two of the required exits from the fith floor exit through the open stairways connecting to the fourth floor. The one hour exit corridors on both the fourth & fifth floors are required to be completed prior to any occupancy or use of the fifth floor. NOTE: This building is fully fire sprinklered. (P.C.#807-98)/drs
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes6/20/20036/20/20036/20/2003 DONE
Permanent Occupancy 5/4/20005/4/2000 DONE
Details
FIRE-Final Inspection5/1/20005/4/20005/4/2000APASS
DetailsRick Jackson
Ron ###-####
BLD-Final5/1/20005/4/20005/4/2000APASS
Details
###-#### Ron signed the perm col 5/4/00 4:34:25 PM
Permanent occupancy  5/4/2000 DONE
Perm. Occ. Cert. #8217 issued 5-4-00 to SLRMC Anderson Center on the 5th floor of the South Tower.
Receive PAYMENT IN FULL  3/30/2000 DONE
FIRE-Final Inspection3/3/20003/6/20003/6/2000AFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 03/03/2000 at 12:56:37. Contact: ###-####. Ok to use auditorium for 3/7/00 only. 3/6/00 1:49:56 PM
BLD-Final3/3/20003/6/20003/6/2000APART
Details
Scheduled by a contractor via Hello! on 03/03/2000 at 12:57:13. Contact: ###-####. made ok to occupy the fifth floor for 2-hours 3/7/00 7am to 9am 3/6/00 10:43:17 AM
FIRE-Alarm Testing3/1/20003/2/20003/2/2000PPART
DetailsRick Jackson
Scheduled by a contractor via Hello! on 03/01/2000 at 13:45:41. Contact: ###-####. Door houser relay not workin. 3/6/00 10:52:38 AM
BLD-Final3/1/20003/2/20003/2/2000PFAIL
Details
Scheduled by a contractor via Hello! on 03/01/2000 at 13:46:25. Contact: ###-####. 409 c/n in force ctr to recall when ready 3/2/00 3:49:56 PM
FIRE-Final Inspection2/25/20002/28/20002/28/2000AFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 02/25/2000 at 13:49:50. Contact: ###-####. Sprinkler r/I inspectionok to cove; miwar fire proofing. 2/28/00 2:42:46 PM
(F) Reprint permit  2/15/2000 DONE
BLD-Wall cover2/11/20002/11/20002/11/2000PPART
Details
Scheduled by a contractor via Hello! on 02/11/2000 at 10:16:35. Contact: ###-####. made ok to drop in ceiling tiles pending 409 signoff 2/11/00 5:25:09 PM
(F) Reprint permit  2/10/2000 DONE
BLD-Conference2/3/20002/7/20002/7/2000APASS
Details
Scheduled by a contractor via Hello! on 02/03/2000 at 16:17:24. Contact: ###-####. need to have all systems working 2/10/00 10:10:08 AM
FIRE-Conference2/3/20002/7/20002/7/2000A409
DetailsRick Jackson
Scheduled by a contractor via Hello! on 02/03/2000 at 16:18:06. Contact: ###-####. Discussed requirements for March 7 meeting
Fee Review-notes3/3/1999 1/28/2000 DONE
up today values will be finaled late march--will bill for part of additional value --ST LUKES CERT VALUE 3,146,212.00 LH
(F) Reprint permit  1/27/2000 DONE
BLD-Final12/29/19991/3/20001/3/2000AFAIL
Details
Scheduled by a contractor via Hello! on 12/29/1999 at 16:11:53. Contact: ###-####.this is to be a frame insp to review reqs for the ceiling system in area B north 1/2
FIRE-Final Inspection12/29/19991/3/20001/3/2000AFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 12/29/1999 at 16:12:40. Contact: ###-####. Sprinkler R/I inspection- ok to cover auditorium (North end).
BLD-Other1/3/20001/3/20001/3/2000APART
Details
MADE OK TO DROP IN TILES STILL TO RECIEVE INFO ON THE PERIMETER TRIM ON THE CLOUD AREAS
BLD-Final12/29/199912/30/199912/30/1999APASS
Details
Scheduled by a contractor via Hello! on 12/29/1999 at 13:04:20. Contact: ###-####.made ok l/c #
BLD-Framing/Rough-in11/29/199911/29/199911/29/1999PPART
Details
Scheduled by a contractor via Hello! on 11/29/1999 at 10:49:09. Contact: ###-####. Ok to cover area "B".
BLD-Framing/Rough-in11/12/199911/15/199911/15/1999APART
Details
ron--- ###-#### fr insp Ok for "C" ura coffee bar @ high ceiling.
FIRE-Sprinkler Rough-in11/10/199911/10/199911/10/1999PPART
DetailsRick Jackson
ron-- ###-#### r/I Ok to cover area by elevator.
BLD-Wall cover9/20/19999/21/19999/21/1999APART
Details
RON ###-#### made ok to cover "G"
INSP - Wall cover9/2/19999/3/19999/3/1999APART
Details
09/03/99 338 - madeok to cover "a" "g" "f"
INSP - Framing/Rough-in8/16/19998/17/19998/17/1999APART
Details
RON ###-#### made ok to cover south stair tower ceiling
INSP - Wall cover8/13/19998/13/19998/13/1999PPART
Details
08/13/99 338 - NEED RECALL FOR 08-1699
INSP - Framing/Rough-in8/9/19998/10/19998/11/1999AFAIL
Details
08/10/99 338 - verbal c/n issued
(F) Reprint permit  5/28/1999
CHANGE STATUS TO (I)  4/30/1999
Receive PAYMENT IN FULL  4/27/1999
Inspection Record Card- Bld  3/2/1999
Print Occupancy Form  3/2/1999
Issue & PRINT FEE-DUE permit  3/2/1999
Plan assigned to (DRS)11/30/1998 3/1/1999 PASS
DetailsDan Stuart
03/01/99 17:25:52 DRS - this action updated by action script from <<>> in Case No. BLD98-3679
Routing - PLAN CHECK3/1/1999 3/1/1999 PASS
Received new plans for assembly room exiting at #524 & #525 per plan review correction requirements. Inserted into plans. Processing for issuance of permit.
PLANS/APPL TAKEN TO FRONT DESK  3/1/1999 PASS
Processing to permit desk for issuance of permit.
Plan resubmittals received  3/1/1999
RECEIVED TWO COPIES OF REVISED SHEETS A2.1, A21.E, A2.1-F, A2.1-G, A3.5, A5.1, A8.1, A9.3, A9.7, AND TWO COPIES OF RESPONSE LETTER FROM TY MORRISON. ROUTED TO DAN S. KMM
Telephone call  2/19/1999
Ty called to ask if a new additional door could be installed in room 525 as well as the existing door shown that does not meet separation requirments. He will also show the door in room 524 relocated to meet separation requirements. I told him this would be ok as long as the separation was met and the exit sign was relocated to the complying exit in room 525. Ty will resubmit plans showing corrected exits.
Plan resubmittals received  2/17/1999
Received new architectural plans for project and several new electrical & mechanical sheets, from architect. Using original submittal plan cover sheet & last sheet with address and routing information and disposing of all other original sheets. Reviewed plan submittals and request additional plans for exit changes required per plan review but not included in plans. A letter was provided from the hospital stating they woulf not use rooms 523 & 524 together since the exits did not meet separation requirements. This was not acceptable since the folding doors are still shown and the rooms can be rnted for meetings and have the doors opened to combine the room areas creating a possible exit hazard. I talked with Ty Morrison and explained that I could not accept his and the hospitals proposal and the separation of exits would need to be shown on new plan sheets before a permit could be issued. Ty will review with owner and call me back.
Routing - PLAN CHECK1/27/1999 1/28/1999 PARK
Plans received back from Fire Dept. Approved with conditions. Plans parked behind desk wziting for architects response to my plan review.
Routing - FIRE1/21/1999 1/27/1999 PASS
Plan Review Completed(1st rev)  1/27/1999 FAIL
ubc exiting issues
Print Pending Permit.LaserJet4  1/20/1999 PEND
Telephone call  1/20/1999
TALKED WITH TY MORRISON OF OLSEN & ASSOC. CONCERNING THE EXITING SYSTEM FOR THE A2.1 OCCUPANCY AUDITORIUM AND PROBLEM NEEDING ADDRESSED TO SATISY CODE. WILL INCLUDE OPTIONS WITH OTHER PLAN REVIEW COMMENTS TO ARCHITECT TONIGHT.
Routing - PLAN CHECK12/30/1998 1/20/1999 PEND
COMPLETED PLAN REVIEW. RESUBMITTALS REQUIRED. COPY TO ARCHITECT BY FAX AND MAIL. ROUTING TO FIRE DEPT.
Plan resubmittals requested  1/20/1999 PEND
FAXED AND MAILED 18 PAGES OF PLAN REVIEW COMMENTS OF ITEMS NEEDING ADDRESSED BY THE ARCHITECT, ENGINEER OR OWNER AS RELATING TO THIS PROJECT AND THE PROPOSED OCCUPANCY USES.
Receive PAYMENT IN FULL  12/30/1998
Routing - PLAN CHECK12/3/1998 12/30/1998
PICKED UP PLAN TO BEGIN PLAN REVIEW
Routing - PUBLIC WORKS11/30/1998 12/2/1998 PASS
Plan routing begun/TENANTS  11/30/1998
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
Issue & PRINT FEE-DUE permit  11/24/1998
Application received  11/24/1998 PASS