Fee Review-notes | 6/20/2003 | 6/20/2003 | 6/20/2003 | | DONE |
|
|
|
|
Permanent Occupancy | | 5/4/2000 | 5/4/2000 | | DONE |
|
|
|
|
FIRE-Final Inspection | 5/1/2000 | 5/4/2000 | 5/4/2000 | A | PASS |
Rick Jackson
|
|
|
Ron ###-####
|
BLD-Final | 5/1/2000 | 5/4/2000 | 5/4/2000 | A | PASS |
|
|
|
###-#### Ron signed the perm col 5/4/00 4:34:25 PM
|
Permanent occupancy | | | 5/4/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8217 issued 5-4-00 to SLRMC Anderson Center on the 5th floor of the South Tower.
|
Receive PAYMENT IN FULL | | | 3/30/2000 | | DONE |
|
|
|
|
FIRE-Final Inspection | 3/3/2000 | 3/6/2000 | 3/6/2000 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 03/03/2000 at 12:56:37. Contact: ###-####. Ok to use auditorium for 3/7/00 only. 3/6/00 1:49:56 PM
|
BLD-Final | 3/3/2000 | 3/6/2000 | 3/6/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 03/03/2000 at 12:57:13. Contact: ###-####. made ok to occupy the fifth floor for 2-hours 3/7/00 7am to 9am 3/6/00 10:43:17 AM
|
FIRE-Alarm Testing | 3/1/2000 | 3/2/2000 | 3/2/2000 | P | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 03/01/2000 at 13:45:41. Contact: ###-####. Door houser relay not workin. 3/6/00 10:52:38 AM
|
BLD-Final | 3/1/2000 | 3/2/2000 | 3/2/2000 | P | FAIL |
|
|
|
Scheduled by a contractor via Hello! on 03/01/2000 at 13:46:25. Contact: ###-####. 409 c/n in force ctr to recall when ready 3/2/00 3:49:56 PM
|
FIRE-Final Inspection | 2/25/2000 | 2/28/2000 | 2/28/2000 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 02/25/2000 at 13:49:50. Contact: ###-####. Sprinkler r/I inspectionok to cove; miwar fire proofing. 2/28/00 2:42:46 PM
|
(F) Reprint permit | | | 2/15/2000 | | DONE |
|
|
|
|
BLD-Wall cover | 2/11/2000 | 2/11/2000 | 2/11/2000 | P | PART |
|
|
|
Scheduled by a contractor via Hello! on 02/11/2000 at 10:16:35. Contact: ###-####. made ok to drop in ceiling tiles pending 409 signoff 2/11/00 5:25:09 PM
|
(F) Reprint permit | | | 2/10/2000 | | DONE |
|
|
|
|
BLD-Conference | 2/3/2000 | 2/7/2000 | 2/7/2000 | A | PASS |
|
|
|
Scheduled by a contractor via Hello! on 02/03/2000 at 16:17:24. Contact: ###-####. need to have all systems working 2/10/00 10:10:08 AM
|
FIRE-Conference | 2/3/2000 | 2/7/2000 | 2/7/2000 | A | 409 |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 02/03/2000 at 16:18:06. Contact: ###-####. Discussed requirements for March 7 meeting
|
Fee Review-notes | 3/3/1999 | | 1/28/2000 | | DONE |
|
|
|
up today values will be finaled late march--will bill for part of additional value --ST LUKES CERT VALUE 3,146,212.00 LH
|
(F) Reprint permit | | | 1/27/2000 | | DONE |
|
|
|
|
BLD-Final | 12/29/1999 | 1/3/2000 | 1/3/2000 | A | FAIL |
|
|
|
Scheduled by a contractor via Hello! on 12/29/1999 at 16:11:53. Contact: ###-####.this is to be a frame insp to review reqs for the ceiling system in area B north 1/2
|
FIRE-Final Inspection | 12/29/1999 | 1/3/2000 | 1/3/2000 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/29/1999 at 16:12:40. Contact: ###-####. Sprinkler R/I inspection- ok to cover auditorium (North end).
|
BLD-Other | 1/3/2000 | 1/3/2000 | 1/3/2000 | A | PART |
|
|
|
MADE OK TO DROP IN TILES STILL TO RECIEVE INFO ON THE PERIMETER TRIM ON THE CLOUD AREAS
|
BLD-Final | 12/29/1999 | 12/30/1999 | 12/30/1999 | A | PASS |
|
|
|
Scheduled by a contractor via Hello! on 12/29/1999 at 13:04:20. Contact: ###-####.made ok l/c #
|
BLD-Framing/Rough-in | 11/29/1999 | 11/29/1999 | 11/29/1999 | P | PART |
|
|
|
Scheduled by a contractor via Hello! on 11/29/1999 at 10:49:09. Contact: ###-####. Ok to cover area "B".
|
BLD-Framing/Rough-in | 11/12/1999 | 11/15/1999 | 11/15/1999 | A | PART |
|
|
|
ron--- ###-#### fr insp Ok for "C" ura coffee bar @ high ceiling.
|
FIRE-Sprinkler Rough-in | 11/10/1999 | 11/10/1999 | 11/10/1999 | P | PART |
Rick Jackson
|
|
|
ron-- ###-#### r/I Ok to cover area by elevator.
|
BLD-Wall cover | 9/20/1999 | 9/21/1999 | 9/21/1999 | A | PART |
|
|
|
RON ###-#### made ok to cover "G"
|
INSP - Wall cover | 9/2/1999 | 9/3/1999 | 9/3/1999 | A | PART |
|
|
|
09/03/99 338 - madeok to cover "a" "g" "f"
|
INSP - Framing/Rough-in | 8/16/1999 | 8/17/1999 | 8/17/1999 | A | PART |
|
|
|
RON ###-#### made ok to cover south stair tower ceiling
|
INSP - Wall cover | 8/13/1999 | 8/13/1999 | 8/13/1999 | P | PART |
|
|
|
08/13/99 338 - NEED RECALL FOR 08-1699
|
INSP - Framing/Rough-in | 8/9/1999 | 8/10/1999 | 8/11/1999 | A | FAIL |
|
|
|
08/10/99 338 - verbal c/n issued
|
(F) Reprint permit | | | 5/28/1999 | | |
|
|
|
|
CHANGE STATUS TO (I) | | | 4/30/1999 | | |
|
|
|
|
Receive PAYMENT IN FULL | | | 4/27/1999 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/2/1999 | | |
|
|
|
|
Print Occupancy Form | | | 3/2/1999 | | |
|
|
|
|
Issue & PRINT FEE-DUE permit | | | 3/2/1999 | | |
|
|
|
|
Plan assigned to (DRS) | 11/30/1998 | | 3/1/1999 | | PASS |
Dan Stuart
|
|
|
03/01/99 17:25:52 DRS - this action updated by action script from <<>> in Case No. BLD98-3679
|
Routing - PLAN CHECK | 3/1/1999 | | 3/1/1999 | | PASS |
|
|
|
Received new plans for assembly room exiting at #524 & #525 per plan review correction requirements. Inserted into plans. Processing for issuance of permit.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/1/1999 | | PASS |
|
|
|
Processing to permit desk for issuance of permit.
|
Plan resubmittals received | | | 3/1/1999 | | |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEETS A2.1, A21.E, A2.1-F, A2.1-G, A3.5, A5.1, A8.1, A9.3, A9.7, AND TWO COPIES OF RESPONSE LETTER FROM TY MORRISON. ROUTED TO DAN S. KMM
|
Telephone call | | | 2/19/1999 | | |
|
|
|
Ty called to ask if a new additional door could be installed in room 525 as well as the existing door shown that does not meet separation requirments. He will also show the door in room 524 relocated to meet separation requirements. I told him this would be ok as long as the separation was met and the exit sign was relocated to the complying exit in room 525. Ty will resubmit plans showing corrected exits.
|
Plan resubmittals received | | | 2/17/1999 | | |
|
|
|
Received new architectural plans for project and several new electrical & mechanical sheets, from architect. Using original submittal plan cover sheet & last sheet with address and routing information and disposing of all other original sheets. Reviewed plan submittals and request additional plans for exit changes required per plan review but not included in plans. A letter was provided from the hospital stating they woulf not use rooms 523 & 524 together since the exits did not meet separation requirements. This was not acceptable since the folding doors are still shown and the rooms can be rnted for meetings and have the doors opened to combine the room areas creating a possible exit hazard. I talked with Ty Morrison and explained that I could not accept his and the hospitals proposal and the separation of exits would need to be shown on new plan sheets before a permit could be issued. Ty will review with owner and call me back.
|
Routing - PLAN CHECK | 1/27/1999 | | 1/28/1999 | | PARK |
|
|
|
Plans received back from Fire Dept. Approved with conditions. Plans parked behind desk wziting for architects response to my plan review.
|
Routing - FIRE | 1/21/1999 | | 1/27/1999 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 1/27/1999 | | FAIL |
|
|
|
ubc exiting issues
|
Print Pending Permit.LaserJet4 | | | 1/20/1999 | | PEND |
|
|
|
|
Telephone call | | | 1/20/1999 | | |
|
|
|
TALKED WITH TY MORRISON OF OLSEN & ASSOC. CONCERNING THE EXITING SYSTEM FOR THE A2.1 OCCUPANCY AUDITORIUM AND PROBLEM NEEDING ADDRESSED TO SATISY CODE. WILL INCLUDE OPTIONS WITH OTHER PLAN REVIEW COMMENTS TO ARCHITECT TONIGHT.
|
Routing - PLAN CHECK | 12/30/1998 | | 1/20/1999 | | PEND |
|
|
|
COMPLETED PLAN REVIEW. RESUBMITTALS REQUIRED. COPY TO ARCHITECT BY FAX AND MAIL. ROUTING TO FIRE DEPT.
|
Plan resubmittals requested | | | 1/20/1999 | | PEND |
|
|
|
FAXED AND MAILED 18 PAGES OF PLAN REVIEW COMMENTS OF ITEMS NEEDING ADDRESSED BY THE ARCHITECT, ENGINEER OR OWNER AS RELATING TO THIS PROJECT AND THE PROPOSED OCCUPANCY USES.
|
Receive PAYMENT IN FULL | | | 12/30/1998 | | |
|
|
|
|
Routing - PLAN CHECK | 12/3/1998 | | 12/30/1998 | | |
|
|
|
PICKED UP PLAN TO BEGIN PLAN REVIEW
|
Routing - PUBLIC WORKS | 11/30/1998 | | 12/2/1998 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 11/30/1998 | | |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Issue & PRINT FEE-DUE permit | | | 11/24/1998 | | |
|
|
|
|
Application received | | | 11/24/1998 | | PASS |
|
|
|
|