Fee Review-notes | 6/20/2003 | 6/20/2003 | 6/20/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 1/12/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8082 issued 1-12-00 to the Vedic Temple.
|
FIRE-Final Inspection | 1/10/2000 | 1/10/2000 | 1/10/2000 | A | PASS |
Rick Jackson
|
|
|
|
BLD-Final | 1/10/2000 | 1/10/2000 | 1/10/2000 | | PASS |
Jim Storey
|
|
|
|
Permanent Occupancy | | 1/10/2000 | 1/10/2000 | | DONE |
|
|
|
|
Temporary occupancy | | | 11/22/1999 | | PART |
|
|
|
Tim extended temp. occ. #3893 thru 12-31-99 pending receipt of some custom doors being shipped. Rick and Jim Storey are holding up sign off until this occurs.
|
BLD-Final | 10/29/1999 | 11/1/1999 | 11/1/1999 | A | NR |
Jim Storey
|
|
|
Cathy has the card! Waiting for main door and hardware/owner said doors are on a ship.
|
FIRE-Final Inspection | 10/29/1999 | 11/1/1999 | 11/1/1999 | A | FAIL |
Rick Jackson
|
|
|
Cathy has the card! Awaiting lobby doors.
|
Telephone call | | | 10/29/1999 | | DONE |
|
|
|
Talked with Jim Campbell re: getting finals - will request them for 11-1-99 he said.
|
CHANGE STATUS TO (TMP) | | | 10/29/1999 | | DONE |
|
|
|
|
Code Occupancy Approval | | | 10/28/1999 | | PASS |
|
|
|
LANDSCAPE IN PLACE, ALL CONDITIONS NOW HAVE BEEN MET, FINAL SIGNED OFF AND RELEASE OF BOND SIGNED.
|
INSP-Final Inspection | 8/20/1999 | 8/20/1999 | 8/20/1999 | P | PART |
Rick Jackson
|
|
|
main exit hardware
|
INSP-Final Inspection | 8/20/1999 | 8/20/1999 | 8/20/1999 | A | FAIL |
Rick Jackson
|
|
|
emergency lights and exit lights
|
Code Occupancy Approval | | | 8/20/1999 | | FAIL |
|
|
|
NOT ALL CONDITIONS HAVE BEEN MET, SOME LAND SCAPE, SPRINKER SYSTEM AND PARKING, THEY POSTED BOND FOR THE WORK $5450, I SIGNED OFF THE TEMPORARY OCCUPANCY CARD.
|
Temporary occupancy | | | 8/20/1999 | | PASS |
|
|
|
Temp. Occ. Cert. #3893 issued 8-20-99 to the Vedaic Temple.
|
INSP-Final Inspection | 8/18/1999 | 8/19/1999 | 8/19/1999 | A | FAIL |
Rick Jackson
|
|
|
jim ###-#### exit door hardware; smoke detectors;
|
Code Occupancy Approval | | | 8/18/1999 | | |
|
|
|
Temporary Occupancy requested by Jim Campbell ###-####
|
INSP - Framing/Rough-in | 7/27/1999 | 7/28/1999 | 7/28/1999 | A | PART |
Jim Storey
|
|
|
07/28/99 301 - draft stops ok
|
INSP - Framing/Rough-in | 6/29/1999 | 6/30/1999 | 6/30/1999 | A | PASS |
Jim Storey
|
|
|
06/30/99 301 - jim ###-#### fr
|
INSP - Framing/Rough-in | 6/22/1999 | 6/22/1999 | 6/22/1999 | P | PART |
Jim Storey
|
|
|
06/22/99 301 - jim ###-####
|
SUPER- Supervisor's review | 6/11/1999 | 6/10/1999 | 6/10/1999 | | PEND |
|
|
|
Site review.
|
INSP - Foundation | 3/24/1999 | 3/24/1999 | 3/24/1999 | P | PART |
Jim Storey
|
|
|
03/24/99 301 - footing ok
|
Routing Off Site - A.C.H.D | 3/12/1999 | 3/12/1999 | 3/12/1999 | | |
|
|
|
received achd on file
|
Telephone call | | | 3/12/1999 | | PASS |
|
|
|
left mess for bruce poe that plans are ready
|
Issue PAID IN FULL permit | | | 3/12/1999 | | |
|
|
|
|
Routing - PLAN CHECK | 2/19/1999 | | 3/12/1999 | | FAIL |
|
|
|
|
Plan assigned to (R_H) | 12/22/1998 | | 3/11/1999 | | PASS |
|
|
|
03/11/99 15:03:53 RMH - this action updated by action script from <<>> in Case No. BLD98-3737
|
Inspection Record Card- Bld | | | 3/11/1999 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/11/1999 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 3/11/1999 | | PASS |
|
|
|
|
Print Occupancy Form | | | 3/11/1999 | | |
|
|
|
|
Plan resubmittals received | | | 3/10/1999 | | |
|
|
|
RECEIVED TWO COPIES OF REVISED DRAWINGS NOT STAMPED OR SIGNED. CONTACTED BRUCE POE OF THIS. ONE COPY OF LETTER RESPONDING TO PLAN REVIEW COMMENTS. COPY OF IMPACT FEE CERTIFICATE. BRUCE POE CAME IN AND STAMPED AND SIGNED RESUB. PLANS. ROUTED TO RON HILL. KMM
|
Routing - FIRE | 2/18/1999 | | 2/19/1999 | | PASS |
|
|
|
condition on fr construction as per R Hill
|
Plan Review Completed(1st rev) | | | 2/19/1999 | | FAIL |
|
|
|
ubc issues
|
Plan Reviewer's activity | | | 2/17/1999 | | FAIL |
|
|
|
Talked to architect and faxed requirements, will route to fire department
|
Routing - PLAN CHECK | 2/16/1999 | | 2/17/1999 | | FAIL |
|
|
|
|
Routing - PUBLIC WORKS | 2/12/1999 | | 2/16/1999 | | PASA |
|
|
|
|
Plan resubmittals received | | | 2/10/1999 | | |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEETS A0.0, A1.0, A2.0, A3.0, A4.0, A5.0, A6.0, A7.0, M-1, E-1. TWO COPIES OF OF STRUCTURAL CALCULATIONS. ROUTED TO RON H. KMM
|
Application received | | | 2/10/1999 | | PASS |
|
|
|
received record declaration form. kmm
|
Plan Reviewer's activity | | | 1/5/1999 | | FAIL |
|
|
|
Can not do plan complete plan check prior to receiving more information, talked to Architect and mailed requirements to Architect. I will not route to fire department until I receive additional requirements.
|
Routing - PLUMBING | 12/28/1998 | | 12/29/1998 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 12/23/1998 | | 12/28/1998 | | FAIL |
|
|
|
REQUIRES DRAINAGE PLAN PER BRIAN MURPHY. DAR 12/28/98
|
Routing - PLANNING | 12/23/1998 | | 12/23/1998 | | PASS |
|
|
|
approved per DRH98-0152.
|
Plan assigned to (MYS) | 12/1/1998 | | 12/22/1998 | | |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 12/22/1998 | | |
|
|
|
Route to PLANNING, PUBLIC WORKS, PLUMBING, PLAN CHECK and FIRE.
|
Routing - PLANNING | 12/22/1998 | | 12/22/1998 | | PASS |
|
|
|
CUP98-0092 Approved. Joint parking agreement in file. Density reduction survey complete.
|
Plans ACCEPTED BY PLAN TECH | | | 12/21/1998 | | PASS |
|
|
|
RECEIVED TWO COPIES OF ELEC. PLUMB. MECH. STAMPED PLANS. ROUTED TO MARLENE. KMM
|
Plans ACCEPTED BY PLAN TECH | | | 12/3/1998 | | HOLD |
|
|
|
12-03-98 REQUIRES ELEC. PLUMB. AND MECH. PLANS. CONTACTED BRUCE POE OF THIS NEED. KMM
|
Recd Pcfee & Taken To Pln CK | | | 12/1/1998 | | |
|
|
|
|
Application received | | | 12/1/1998 | | PEND |
|
|
|
12-03-98 REQUIRES RECORD DECL FORM. FAXED TO BRUCE POE.
|