Permanent Occupancy | | 4/9/1999 | 4/9/1999 | | DONE |
|
|
|
|
Permanent occupancy | | | 4/9/1999 | | PASS |
|
|
|
Perm. Occ. Cert. #7732 issued 4-9-99 to the New York Burrito.
|
INSP - Final | 4/7/1999 | 4/7/1999 | 4/7/1999 | P | PASS |
Carl Dependahl
|
|
|
04/07/99 340 - Darlene ###-####; ok card to owner for perm c/o
|
INSP-Final Inspection | 4/6/1999 | 4/6/1999 | 4/6/1999 | P | PASS |
Joe Tawney
|
|
|
04/06/99 406 - REINSP OK FOR PERM OCC
|
INSP - Final | 4/6/1999 | 4/6/1999 | 4/6/1999 | P | NR |
Carl Dependahl
|
|
|
04/06/99 340 - ###-#### darlene//final late pm need cdhd, fire
|
INSP-Final Inspection | 4/5/1999 | 4/5/1999 | 4/5/1999 | P | FAIL |
Joe Tawney
|
|
|
04/05/99 406 - FINAL FAIL EXIT LIGHTS, FIRE EXT, EXIT DOOR, ADDRESS
|
INSP - Final | 4/5/1999 | 4/5/1999 | 4/5/1999 | P | FAIL |
Carl Dependahl
|
|
|
04/05/99 340 - Darlene ###-####; fire c/n, no temp.
|
INSP - Framing/Rough-in | 3/17/1999 | 3/18/1999 | 3/18/1999 | A | PART |
Carl Dependahl
|
|
|
03/18/99 340 - ###-#### DARLENE//RI CEILING INSPECT WILL BE THERE AFTER COVER OR REMOVE SOUND BOARD ABOVE CLG, REST OK
|
INSP - Framing/Rough-in | 3/4/1999 | 3/5/1999 | 3/5/1999 | P | PART |
Jim Storey
|
|
|
03/05/99 301 - framing ok pending ele insp. ok to cover if ele approved.
|
INSP - Framing/Rough-in | 3/5/1999 | 3/5/1999 | 3/5/1999 | | PART |
Jim Storey
|
|
|
03/05/99 301 - ok for cover pending ele framing ok.
|
Inspection Record Card- Bld | | | 2/26/1999 | | |
|
|
|
|
Print Occupancy Form | | | 2/26/1999 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 2/17/1999 | | |
|
|
|
|
Print Occupancy Form | | | 2/17/1999 | | |
|
|
|
|
Inspection Record Card- Bld | | | 2/17/1999 | | |
|
|
|
|
Telephone call | | | 2/17/1999 | | PASS |
|
|
|
talked to darlene to verify plans are ready
|
Routing - PLAN CHECK | 1/5/1999 | | 2/16/1999 | | PASS |
|
|
|
During this time period, the drawings were in the possession of Central District Health Department, the Plumbing Division, and the Plan Review Division.
|
Plan assigned to (CJW) | 12/9/1998 | | 2/16/1999 | | PASS |
Carl Westfall
|
|
|
02/16/99 16:45:49 CJW - this action updated by action script from <<>> in Case No. BLD98-3738
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/16/1999 | | PASS |
|
|
|
|
Routing Off Site - C.D.H | 2/12/1999 | | 2/12/1999 | | PASS |
|
|
|
APPROVED RESUBS RECEIVED ON 2/12/99 DAR
|
Plan resubmittals received | | | 2/12/1999 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM OLSON AND ASSOCIATES. FORWARDED SAME TO CARL WESTFALL. 2/12/99
|
Routing - PLUMBING | | | 2/3/1999 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 1/4/1999 | | FAIL |
|
|
|
plumbing
|
Routing - FIRE | 12/30/1998 | | 1/4/1999 | | PASS |
|
|
|
|
testing condition printout | | | 12/30/1998 | | |
|
|
|
|
Print permit w/o conditions | | | 12/30/1998 | | |
|
|
|
|
Routing - PLAN CHECK | 12/21/1998 | | 12/30/1998 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 12/23/1998 | | PASS |
|
|
|
UBC plan review started December 23, 1998 and finished December 30, 1998. Drawings approved with conditions. See conditions list.
|
Routing - PLUMBING | 12/21/1998 | | 12/21/1998 | | FAIL |
|
|
|
|
Routing - PUBLIC WORKS | 12/17/1998 | | 12/18/1998 | | PASS |
|
|
|
|
Routing Off Site - C.D.H | 12/9/1998 | | 12/16/1998 | | PEND |
|
|
|
MARLENE TOOK PLANS OUT TO CDH. CALLED DARLENE TO LET HER KNOW AND THAT SHE WILL HAVE TO BRING PLANS BACK. KMM 12-16-98 DEBBIE WILL HAVE TO BE CALLED TO COME IN AND SIGN OFF ON THE OFFICE COPY BEFORE WE ISSUE PLANS. KMM
|
Plan assigned to (MYS) | 12/1/1998 | | 12/9/1998 | | |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 12/9/1998 | | |
|
|
|
Route to CENTRAL DISTRICT HEALTH, PUBLIC WORKS, PLUMBING, PLAN CHECK and FIRE.
|
Plans ACCEPTED BY PLAN TECH | | | 12/8/1998 | | PASS |
|
|
|
12-04-98 REQUIRES VICINITY MAP AND BEFORE FLOOR PLAN. SPOKE WITH STAN OLSEN OF THIS NEED. MARLENE STATED IF NOT DOING ANY CHANGES IN MECH. OR PLUMB. DO NOT NEED THOSE ADDITIONAL PLANS. STAN STATED THEY ARE NOT DOING ANY CHANGES. WILL HOLD UNTIL ITEMS RECEIVED. KMM 12-07-98 RECEIVED VICINITY MAP. PUT WITH PLANS. KMM 12-08-98 RECEIVED BEFORE FLOOR PLAN PUT WITH PLANS AND ROUTED TO MARLENE. KMM 12-11-98 SPOKE WITH DEBBIE FROM CDH. SHE STATED THEY WILL NEED TO MAKE PLUMB. CHANGES THUS THEY WILL NEED PLUMB. PLANS. KMM
|
Recd Pcfee & Taken To Pln CK | | | 12/1/1998 | | |
|
|
|
|
Application received | | | 12/1/1998 | | PASS |
|
|
|
|