Fee Review-notes | 6/20/2003 | 6/20/2003 | 6/20/2003 | | DONE |
|
|
|
Additional value from subcontractor.
|
Permanent Occupancy | | 6/29/2000 | 6/29/2000 | | DONE |
|
|
|
|
BLD-Final | 6/29/2000 | 6/29/2000 | 6/29/2000 | P | PASS |
Jim Storey
|
|
|
Central Idaho Bldg. Supply
|
Permanent occupancy | | | 6/29/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8272 issued 6-29-00 to Central Idaho Building Supply.
|
FIRE-Final Inspection | 5/11/2000 | 5/12/2000 | 5/12/2000 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 05/11/2000 at 11:41:34. Contact: ###-####.
|
FIRE-Final Inspection | 4/24/2000 | 4/25/2000 | 4/25/2000 | A | FAIL |
Rick Jackson
|
|
|
not built to plans
|
BLD-Final | 4/24/2000 | 4/25/2000 | 4/25/2000 | P | NR |
Jim Storey
|
|
|
Jeremy ###-####
|
FIRE-Final Inspection | 4/6/2000 | 4/7/2000 | 4/7/2000 | A | FAIL |
Rick Jackson
|
|
|
exit door not installed as shown on plans; exit signs not working; annual sprinkler test
|
Override - Parcel Holds | | | 4/6/2000 | | |
|
|
|
|
Override - Parcel Holds | | | 4/6/2000 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 2/25/1999 | | PEND |
|
|
|
|
INSP - Framing/Rough-in | 2/22/1999 | 2/23/1999 | 2/24/1999 | A | PASS |
Jim Storey
|
|
|
02/24/99 301 - FRAM-OK FRAMING
|
Issue PAID IN FULL permit | | | 2/8/1999 | | |
|
|
|
|
Routing - PLAN CHECK | 1/5/1999 | | 1/27/1999 | | |
|
|
|
|
Plan assigned to (R_H) | 12/8/1998 | | 1/27/1999 | | PASS |
|
|
|
01/27/99 13:44:18 R_H - this action updated by action script from <<>> in Case No. BLD98-3746
|
Telephone call | | | 1/27/1999 | | |
|
|
|
called no answering machine only got fax after a few rings
|
Print Occupancy Form | | | 1/27/1999 | | |
|
|
|
|
Plan Reviewer's activity | | | 1/27/1999 | | PASS |
|
|
|
recieved application and plans for the proposed restroom, will issue restroom plans under separate permit.
|
Inspection Record Card- Bld | | | 1/27/1999 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 1/27/1999 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/27/1999 | | PASS |
|
|
|
|
Routing - FIRE | 1/4/1999 | | 1/4/1999 | | PASS |
|
|
|
no high storage per architects letter
|
Routing - FIRE | 12/23/1998 | | 12/29/1998 | | FAIL |
|
|
|
provide UBC/UFC issues.
|
Plan resubmittals received | | | 12/24/1998 | | PEND |
|
|
|
RECEIVED RESUBMITTALS FROM LYNN BROWN.FORWARDED SAME TO RON HILL. DAR 12/24/98
|
Routing - PLAN CHECK | 12/8/1998 | | 12/22/1998 | | FAIL |
|
|
|
|
Plan Reviewer's activity | | | 12/22/1998 | | HOLD |
|
|
|
Faxed requirements to Architect. Noted that permit could not be issued until restroom plans have been submitted to the Building Department.
|
Plan Reviewer's activity | | | 12/22/1998 | | HOLD |
|
|
|
Will route to fire department.
|
Plan routing begun/TENANTS | | | 12/8/1998 | | |
|
|
|
Route to PLANNING, PLAN CHECK and FIRE.
|
Routing - PLANNING | 12/8/1998 | | 12/8/1998 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 12/2/1998 | | 12/8/1998 | | |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/4/1998 | | PEND |
|
|
|
RECEIVED PLANS AND STRUCTURAL CACULATIONS, 2 EACH. DAR 12/07/98
|
Recd Pcfee & Taken To Pln CK | | | 12/2/1998 | | |
|
|
|
|
Application received | | | 12/2/1998 | | |
|
|
|
|