(F) Reprint permit | | | 11/3/2000 | | DONE |
|
|
|
|
(F) Reprint permit | | | 2/14/2000 | | DONE |
|
|
|
|
Receive PAYMENT IN FULL PRINT | | | 2/11/2000 | | DONE |
|
|
|
|
Fee Review-notes | 11/29/1999 | 11/29/1999 | 11/29/1999 | | DONE |
|
|
|
12/22/99-letter from tamura and asso ask to sent bill to cont. i change primary
|
(F) Reprint permit | | | 11/29/1999 | | DONE |
|
|
|
|
Fee Review-notes | 2/22/1999 | | 11/29/1999 | | DONE |
|
|
|
additional values from subs
|
Permanent occupancy | | | 9/29/1999 | | DONE |
|
|
|
Perm. Occ. Cert. #7919 issued 9-29-99 to H & W Computer Systems.
|
FIRE-Final Inspection | 9/24/1999 | 9/24/1999 | 9/24/1999 | P | PASS |
Joe Tawney
|
|
|
Buck ###-#### Reinsp. Ok for pemanent occupancy
|
BLD-Final | 9/20/1999 | 9/21/1999 | 9/21/1999 | A | CANC |
Jim Storey
|
|
|
buck ###-#### fn occ insp Done by 408
|
BLD-Final | 9/21/1999 | 9/21/1999 | 9/21/1999 | P | PART |
Tom Arcoraci
|
|
|
final occ buck ###-#### ok for temp occ
|
FIRE-Final Inspection | 9/20/1999 | 9/20/1999 | 9/20/1999 | P | PART |
Joe Tawney
|
|
|
buck-- ###-#### fn fire ok for temp. occ. C/N issued
|
FIRE-Final Inspection | 9/13/1999 | 9/15/1999 | 9/15/1999 | A | FAIL |
Joe Tawney
|
|
|
FINAL CONSTRUCTION NOT COMPLETE, TESTED SPRINKLER SYSTEM-C/N ISSUED, OK ON ABOVE GROUND HYDRO TEST
|
INSP-Final Inspection | 9/13/1999 | 9/13/1999 | 9/13/1999 | P | CANC |
Joe Tawney
|
|
|
vicki ###-####
|
INSP - Framing/Rough-in | 9/8/1999 | 9/9/1999 | 9/9/1999 | A | PART |
Jim Sly
|
|
|
CEILING grid appears ok
|
INSP-Supply line flush | 9/1/1999 | 9/1/1999 | 9/1/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON SUPPLY LINE FLUSH
|
INSP-Sprinkler Rough-in/Hydro | 6/21/1999 | 6/21/1999 | 6/21/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON SPKLR ROUGH IN 2 CORR ITEMS
|
INSP - Framing/Rough-in | 6/2/1999 | 6/3/1999 | 6/3/1999 | A | PART |
Jim Sly
|
|
|
06/03/99 316 - OK to cover interior of exterior walls...and (1) side of
|
INSP - Framing/Rough-in | 6/3/1999 | 6/3/1999 | 6/3/1999 | | PART |
Jim Sly
|
|
|
06/03/99 316 - OK to cover interior of exterior walls....1side of some w
|
INSP - Framing/Rough-in | 5/6/1999 | 5/7/1999 | 5/7/1999 | A | PART |
Jim Sly
|
|
|
05/07/99 316 - Verified draftstops (columns) and Ext. Shear wall attachm
|
INSP - Framing/Rough-in | 4/20/1999 | 4/21/1999 | 4/21/1999 | A | PART |
Jim Sly
|
|
|
04/21/99 316 - Met with Buck...conf. shear wall, draft stops, interior w
|
INSP-Sprinkler Rough-in/Hydro | 3/19/1999 | 3/19/1999 | 3/19/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON BEDDING OF SUPPLY LINE
|
INSP-Sprinkler Rough-in/Hydro | 3/19/1999 | 3/19/1999 | 3/19/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON BEDDING OF SUPPLY LINE
|
INSP-Sprinkler Rough-in/Hydro | 3/19/1999 | 3/19/1999 | 3/19/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON BEDDING OF SUPPLY LINE
|
INSP-Sprinkler Rough-in/Hydro | 3/18/1999 | 3/18/1999 | 3/18/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON UNDERGROUND RI WILL NEED TO SEE BACKFILL
|
INSP - Foundation | 3/8/1999 | 3/9/1999 | 3/9/1999 | P | PART |
Tom Arcoraci
|
|
|
03/09/99 408 - BUCK ###-#### EARLY PM
|
INSP - Foundation | 3/5/1999 | 3/5/1999 | 3/5/1999 | | PART |
Tom Arcoraci
|
|
|
03/05/99 408 - ###-#### Buck
|
INSP - Foundation | 3/2/1999 | 3/3/1999 | 3/3/1999 | A | PART |
Tom Arcoraci
|
|
|
03/03/99 408 - ###-#### Buck PART OK ON FOOTING
|
INSP - Concrete | 3/1/1999 | 3/2/1999 | 3/2/1999 | P | PART |
Jim Sly
|
|
|
03/02/99 316 - Footing......Pending special insp approval.
|
INSP - Foundation | 2/25/1999 | 2/26/1999 | 2/26/1999 | A | PART |
Tom Arcoraci
|
|
|
02/26/99 408 - special insp on site
|
Plan resubmittals received | | | 2/19/1999 | | |
|
|
|
RECEIVED TWO COPIES OF C1.0, AND C2.O ROUTED TO JIM SLY. KMM 3-10-99 JIM SLY GAVE BACK SAYING HE DID NOT WANT TO SEE. I THEN GAVE TO BRIAN M. KMM
|
(F) Reprint permit | | | 2/9/1999 | | |
|
|
|
|
Plan resubmittals received | | | 2/9/1999 | | |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEETS A2.1 & A10.0 ROUTED TO JIM SLY KMM
|
Issue PAID IN FULL permit | | | 2/8/1999 | | |
|
|
|
|
Plan assigned to (JCM) | 12/8/1998 | | 2/1/1999 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/1/1999 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 2/1/1999 | | |
|
|
|
|
Print Occupancy Form | | | 2/1/1999 | | |
|
|
|
|
Telephone Call | | | 2/1/1999 | | |
|
|
|
TALKED TO TODD/PLANS ARE READY/NEEDS ACHD APP
|
Routing - PLAN CHECK | 2/1/1999 | | 2/1/1999 | | PASS |
|
|
|
|
Print Occupancy Form | | | 2/1/1999 | | |
|
|
|
|
Routing - PUBLIC WORKS | 1/28/1999 | | 1/29/1999 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 1/14/1999 | | 1/28/1999 | | PEND |
|
|
|
|
Plan Reviewer's activity | | | 1/26/1999 | | PASS |
|
|
|
RESUBMITTALS REVIEWED AND APPROVED AS SUBMITTED WITH ATTACHED BOISE CITY COMMENT LIST.
|
Plan resubmittals received | | | 1/25/1999 | | |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEETS A2.0, A2.1, A6.0, A10.0 WITH REVISIONS PER PLAN CHECK COMMENTS. ONE COPY OF PLAN CHECK RESPONSE. ROUTED TO JOHN M. KMM
|
Routing - FIRE | 1/12/1999 | | 1/13/1999 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 1/13/1999 | | FAIL |
|
|
|
UBC, plumbing. pw fails
|
Routing - PUBLIC WORKS | 1/11/1999 | | 1/12/1999 | | FAIL |
|
|
|
RECEIVED COMMON DRIVEWAY EASEMENT ARGEEMENTS FOR SHARED DRIVEWAYS, AND ROUTED TO BW. REQUIRES CROSS LOT DRAINAGE AGREEMENT, NOT COMMON DRIVEWAY EASEMENT. PER BM. DAR 1/12/99
|
Plan resubmittals requested | | | 1/11/1999 | | PEND |
|
|
|
MAILED AND E-MAILED JOHN PRICE AT TAMURA, A COPY OF THE PLAN REVIEW COMMENT LIST REQUESTING REVISIONS.
|
Routing - PLAN CHECK | 1/6/1999 | | 1/11/1999 | | PEND |
|
|
|
|
Routing - PLAN CHECK | 12/23/1998 | | 1/4/1999 | | PEND |
|
|
|
|
Plan resubmittals received | | | 12/23/1998 | | |
|
|
|
RECEIVED 2 COPIES OF REVISED SHEETS P1.0 AND C1.0 ROUTED TO JOHN M.
|
Routing - PLUMBING | 12/16/1998 | | 12/23/1998 | | FAIL |
|
|
|
|
Routing - PLANNING | 12/11/1998 | | 12/16/1998 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 12/8/1998 | | 12/11/1998 | | FAIL |
|
|
|
REQUIRES CROSS LOT DRAINAGE EASEMENT.
|
Plan routing begun/NEW & ADDTN | | | 12/8/1998 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 12/8/1998 | | 12/8/1998 | | |
|
|
|
12-08-98 ENG. WILL BE DONE INHOUSE PER JOHN M.
|
Plans ACCEPTED BY PLAN TECH | | | 12/7/1998 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 12/4/1998 | | 12/7/1998 | | |
Marlene Southard
|
|
|
|
Application received | | | 12/4/1998 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/4/1998 | | PEND |
|
|
|
|
Received Certificate of Value | | | 12/3/1998 | | PASS |
|
|
|
|
Routing - PLUMBING | 1/4/1999 | | 1/5/1993 | | PASS |
|
|
|
|
Case Summary (BLD) | | | | | |
|
|
|
|