DOC - Permit Finaled | 1/12/2001 | 1/12/2001 | 1/12/2001 | A | PASS |
Jim Storey
|
|
|
Added by Inspector: 301 On 1/12/2001 9:30:47 AM finaled by 409
|
Receive PAYMENT IN FULL | | | 12/23/1999 | | DONE |
|
|
|
|
Fee Review-notes | 9/16/1999 | 9/16/1999 | 9/16/1999 | | DONE |
|
|
|
|
Permanent Occupancy | | 3/15/1999 | 3/15/1999 | | DONE |
|
|
|
|
Permanent occupancy | | | 3/15/1999 | | PASS |
|
|
|
Perm. Occ. Cert. #7685 issued 3-15-99 to Round Table Pizza at Idaho Ice World.
|
INSP - Final | 3/10/1999 | 3/11/1999 | 3/11/1999 | P | CANC |
Russ Owen
|
|
|
03/11/99 407 - trans to 301.
|
INSP-Final Inspection | 3/10/1999 | 3/11/1999 | 3/11/1999 | P | PASS |
Rick Jackson
|
|
|
MIKE PAGER 1-###-#### occ approved
|
INSP - Final | 3/9/1999 | 3/10/1999 | 3/10/1999 | P | FAIL |
Jim Storey
|
|
|
03/10/99 301 - c/n
|
INSP-Final Inspection | 3/9/1999 | 3/10/1999 | 3/10/1999 | P | FAIL |
Rick Jackson
|
|
|
AT 3 PM MIKE 1-###-#### PAGER damper not working
|
INSP-Alarm Testing | 3/4/1999 | 3/5/1999 | 3/5/1999 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by Hello!. Contact phone is [3438271]. exit sign at lobby; smoke fire damper in corridor segement; assembly permit; exit sign at main exit; strobe to within 80-96 inches in corridor; test exit/emer lights
|
INSP - Framing/Rough-in | 2/18/1999 | 2/19/1999 | 2/19/1999 | P | PASS |
Russ Owen
|
|
|
02/19/99 407 - LATE PM \\T-BAR CEILING\\1###-####
|
INSP - Framing/Rough-in | 2/17/1999 | 2/17/1999 | 2/17/1999 | P | PASS |
Jim Storey
|
|
|
02/17/99 301 - FRAM-OK FRAMING FIRE STOPPING OK AT CORRIDOR AND PART OF
|
INSP - Framing/Rough-in | 2/11/1999 | 2/12/1999 | 2/12/1999 | A | FAIL |
Jim Storey
|
|
|
02/12/99 301 - trans to russ he was in the area.
|
INSP - Framing/Rough-in | 2/1/1999 | 2/2/1999 | 2/2/1999 | P | PASS |
Jim Storey
|
|
|
02/02/99 301 - FRAM-OK FRAMING
|
INSP - Framing/Rough-in | 1/28/1999 | 1/29/1999 | 1/29/1999 | A | PART |
Jim Storey
|
|
|
01/29/99 301 - framing ok for soffits to be covered and one side walls.
|
INSP - Foundation | 1/21/1999 | 1/25/1999 | 1/25/1999 | A | FAIL |
Jim Storey
|
|
|
01/25/99 301 - trans to russ
|
INSP - Foundation | 1/22/1999 | 1/22/1999 | 1/22/1999 | P | CANC |
Russ Owen
|
|
|
01/22/99 407 - recall for monday.
|
Plan assigned to (JCM) | 12/14/1998 | | 1/20/1999 | | PASS |
John Menard
|
|
|
|
Routing - PLAN CHECK | 1/15/1999 | | 1/20/1999 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/20/1999 | | PASS |
|
|
|
|
Issue PAID IN FULL permit | | | 1/20/1999 | | |
|
|
|
|
Inspection Record Card- Bld | | | 1/20/1999 | | |
|
|
|
|
Print Occupancy Form | | | 1/20/1999 | | |
|
|
|
|
Routing - FIRE | 1/14/1999 | | 1/15/1999 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 1/15/1999 | | FAIL |
|
|
|
ubc and plumbing
|
Routing - PLUMBING | 1/13/1999 | | 1/14/1999 | | PASS |
|
|
|
|
Plan resubmittals received | | | 1/14/1999 | | PEND |
|
|
|
RECEIVED RESUBMITTALS FROM KARTCHNER ENGINEERING, FORWARDED SAME TO JOHN MENARD. DAR 1/14/99
|
Routing - PLAN CHECK | 12/30/1998 | | 1/13/1999 | | PEND |
|
|
|
|
Plan resubmittals requested | | | 1/13/1999 | | PEND |
|
|
|
FAXED THE ARCHITECT, ROBERT FORSHER, REQUESTING PLAN REVISIONS THAT WERE NOT SUBMITTED WITH THE LAST RESUBMITTAL.
|
Plan resubmittals received | | | 1/13/1999 | | |
|
|
|
RECEIVED LETTER REGARDING ATTACHMENTS TO EXISTING CEILING. ROUTED JOHN M. AND RUSS OWEN
|
Plan resubmittals received | | | 1/12/1999 | | |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEETS A1, A3, A4, A5, A6, A7, ROUTED TO JOHN. KMM
|
Plan resubmittals received | | | 1/11/1999 | | |
|
|
|
1-11-99 RECEIVED ONE COPY OF CONSTRUCTION SPECIFICATIONS AND TWO COPIES OF REVISED PLANS. HOWEVER PLANS WERE NOT SIGNED. CONTACTED MIKE GUTHRIER TO LET HIM KNOW PLANS MUST BE SIGNED. HE STATED NEW COPIES WILL BE SENT. KMM
|
Plan resubmittals received | | | 1/11/1999 | | PEND |
|
|
|
RECEIVED RECEVIED RESUBMITTALS, SHEET A-1, FORWARDED SAME TO JOHN MENARD. DAR 01/11/99
|
INSP-Conference | 1/7/1999 | 1/7/1999 | 1/7/1999 | A | PART |
Rick Jackson
|
|
|
checked status of exit path from lobby area - told them to remove temporary barricades so exit path can remain visible and unobstructed
|
Routing - PLUMBING | 12/29/1998 | | 12/30/1998 | | FAIL |
|
|
|
|
Routing - PUBLIC WORKS | 12/24/1998 | | 12/29/1998 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 12/23/1998 | | PEND |
|
|
|
COPY OF COMMENT LIST SENT TO ARCHITECT FOR REQUESTED REVISIONS.
|
Routing - PLAN CHECK | 12/14/1998 | | 12/23/1998 | | FAIL |
|
|
|
|
Plan routing begun/TENANTS | | | 12/14/1998 | | |
|
|
|
Route to PLAN CHECK, PUBLIC WORKS, PLUMBING, and FIRE.
|
Routing Off Site - C.D.H | 12/7/1998 | | 12/8/1998 | | PASS |
|
|
|
SENT PLANS TO CDH WITH REP, RETAINED APPLICATIONS, KITCHEN PLANS BOOK AND MECHANICAL PLANS.
|
Application received | | | 12/7/1998 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/7/1998 | | PEND |
|
|
|
|
Routing - PUBLIC WORKS | 1/13/1999 | | 1/13/1998 | | PASS |
|
|
|
|