INSP - Final | 6/17/1999 | 6/18/1999 | 6/18/1999 | A | PASS |
Alan Hauser
|
|
|
06/18/99 350 - Bob ###-####
|
INSP - Energy code compliance | 4/5/1999 | 4/6/1999 | 4/6/1999 | A | PASS |
Wes Worcester
|
|
|
04/06/99 342 - ###-####
|
INSP - Framing/Rough-in | 4/1/1999 | 4/2/1999 | 4/2/1999 | P | PASS |
Tom Arcoraci
|
|
|
04/02/99 408 - Bob ###-####
|
INSP - Framing/Rough-in | 3/15/1999 | 3/15/1999 | 3/15/1999 | P | PART |
Jim Sly
|
|
|
03/15/99 316 - Shear wall only.....OK
|
INSP - Foundation | 2/9/1999 | 2/10/1999 | 2/10/1999 | A | PART |
Jim Sly
|
|
|
02/10/99 316 - Footing only....OK
|
INSP - Foundation | 2/8/1999 | 2/9/1999 | 2/9/1999 | P | FAIL |
Jim Sly
|
|
|
02/09/99 316 - Contractor cancelled....
|
Issue PAID IN FULL permit | | | 2/3/1999 | | |
|
|
|
|
Plan resubmittals received | | | 12/30/1998 | | PASS |
|
|
|
revised plans received.
|
Inspection Record Card- Bld | | | 12/30/1998 | | |
|
|
|
|
Telephone call | | | 12/30/1998 | | |
|
|
|
CALLED PERMIT READY
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/30/1998 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 12/30/1998 | | PASS |
|
|
|
|
Plan assigned to (DJO) | 12/9/1998 | | 12/30/1998 | | PASS |
Dan Overy
|
|
|
12/30/98 10:57:58 DJO - this action updated by action script from <<>> in Case No. BLD98-3814
|
Routing - PLANNING | 12/17/1998 | | 12/17/1998 | | FAIL |
|
|
|
resubmittals required. returned to pat ellis. SUBMITTED 2 NEW PLANS PER DJO/TOOK THEM BACK TO DAN OVERY. PAT 12/29/98
|
Plan Reviewer's activity | | | 12/17/1998 | | PEND |
|
|
|
contacted designer and contractor. will pick up marked plan to be used as reference for (2)complete resubmittals.
|
Plans ACCEPTED BY PLAN CHECK | | | 12/16/1998 | | PEND |
|
|
|
|
Routing - PUBLIC WORKS | 12/9/1998 | | 12/10/1998 | | PASS |
|
|
|
|
Application received | | | 12/9/1998 | | |
|
|
|
|
Routing - PLANNING | 12/9/1998 | | 12/9/1998 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 12/10/1998 | | | | PEND |
|
|
|
|