Case Summary (BLD) | | | 6/18/2003 | | |
|
|
|
|
Letter of compliance | | | 11/13/2000 | | DONE |
|
|
|
Letter of Compliance #20013 issued 11-13-00.
|
BLD-Conference | 11/7/2000 | 11/7/2000 | 11/7/2000 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 11/7/2000 9:57:32 AM conf w/ Jordan- Wilcomb...need to recall final
|
BLD-Final | 11/7/2000 | 11/7/2000 | 11/7/2000 | P | PASS |
Carl Dependahl
|
|
|
larry smith ###-####, ok for c/o...sign at office please 11/7/2000 10:33:29 AM
|
BLD-Conference | 8/21/2000 | 8/21/2000 | 8/21/2000 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 8/21/2000 w/ Tim Jordan re final...need stamped summary
|
FIRE-Final Inspection | 11/22/1999 | 11/24/1999 | 11/24/1999 | A | PASS |
Joe Tawney
|
|
|
###-#### bob 6 a.m Reinsp. Ok for cert. Of completion.
|
BLD-Final | 11/24/1999 | 11/24/1999 | 11/24/1999 | P | FAIL |
Carl Dependahl
|
|
|
larry ###-#### C/N; ok for T/O.
|
BLD-Final | 11/16/1999 | 11/19/1999 | 11/19/1999 | P | FAIL |
Carl Dependahl
|
|
|
LARRY ###-#### FN OCC Need others ok's.
|
FIRE-Final Inspection | 11/16/1999 | 11/18/1999 | 11/18/1999 | P | FAIL |
Joe Tawney
|
|
|
BOB ###-#### Final fail; alarm test.
|
Code Occupancy Approval | | | 11/17/1999 | | PASS |
|
|
|
MEETS COMPLIANCE WITH DRH98-0162. PASS.
|
BLD-Final | 11/16/1999 | 11/17/1999 | 11/16/1999 | P | CANC |
Carl Dependahl
|
|
|
LARRY CELL ###-#### FN OCC CANCEL PER LARRY
|
FIRE-Final Inspection | 11/12/1999 | 11/16/1999 | 11/16/1999 | A | FAIL |
Rick Jackson
|
|
|
ray ###-#### No approved alarm plans; off-site monitoring.
|
BLD-Framing/Rough-in | 10/7/1999 | 10/8/1999 | 10/8/1999 | A | PART |
Carl Dependahl
|
|
|
LARRY CELL-- ###-#### FR--CEILING w.I.p. grid ok pend elec r/I
|
INSP - Framing/Rough-in | 9/9/1999 | 9/10/1999 | 9/10/1999 | A | PART |
Carl Dependahl
|
|
|
rated ceiling at corridor ok, need access for dampers
|
INSP - Framing/Rough-in | 8/13/1999 | 8/16/1999 | 8/16/1999 | A | PART |
Carl Dependahl
|
|
|
08/16/99 340 - SIZMIC CEILING. LARRY ###-#### grid & 1st layer at corr o
|
INSP - Framing/Rough-in | 7/20/1999 | 7/20/1999 | 7/20/1999 | P | PART |
Carl Dependahl
|
|
|
conf. w/ bldr, arch, mech eng'r... need to get proposal & ruling re return air at corridor; Also, discussed prior request by me for supporting calculations re canopy (w/ Bob Maxie, arch.) Awaiting opinion from George/ ICBO.
|
INSP - Framing/Rough-in | 7/16/1999 | 7/19/1999 | 7/20/1999 | A | PART |
Carl Dependahl
|
|
|
07/19/99 340 - LARRY ###-####; grid cld at east ok, need elec. Check htg
|
INSP-Conference | 7/6/1999 | 7/6/1999 | 7/6/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - CONF W/LARRY REG FIRE CODE ITEMS
|
INSP - Framing/ Rough-in | 6/28/1999 | 6/28/1999 | 6/28/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - INT PARTS, GRID OK; AWAITING CALCS FOR EXT.CANOPY; KEEP C/N
|
INSP - Framing/Rough-in | 6/17/1999 | 6/17/1999 | 6/17/1999 | P | PART |
Carl Dependahl
|
|
|
06/17/99 340 - ###-####//SEISMIC CEILING GRID; ok pend elec/htg
|
INSP - Foundation | 6/7/1999 | 6/7/1999 | 6/8/1999 | P | PART |
Carl Dependahl
|
|
|
06/07/99 340 - Larry; ftgs;pending eng's revision detail, MTI onsite
|
INSP - Framing/Rough-in | 6/7/1999 | 6/7/1999 | 6/7/1999 | P | PART |
Carl Dependahl
|
|
|
06/07/99 340 - larry ###-####, furring at office walls
|
INSP - Foundation | 6/4/1999 | 6/4/1999 | 6/4/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - SPEC INSP REQ'D? CONF W/JORDAN-WILCOMB
|
INSP - Framing/Rough-in | 5/25/1999 | 5/25/1999 | 5/25/1999 | A | FAIL |
Carl Dependahl
|
|
|
no insp; rec'd letter fom Maxey Arch's re plan modifications at elevator.
|
Plan resubmittals received | | | 4/13/1999 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM CHUCK TOOKEY, MAXEY & MAXEY ARCHITECTS, FORWARDED SAME TO CARL DEPENDAHL. DAR 4/13/99
|
Issue PAID IN FULL permit | | | 3/30/1999 | | |
|
|
|
|
Routing - PLAN CHECK | 1/8/1999 | | 3/5/1999 | | PASS |
|
|
|
Drawings approved, with conditions, after resubmittal review.
|
Plan assigned to (CJW) | 12/21/1998 | | 3/5/1999 | | PASS |
Carl Westfall
|
|
|
03/05/99 14:14:13 CJW - this action updated by action script from <<>> in Case No. BLD98-3861
|
Plan Reviewer's activity | | | 3/5/1999 | | PASS |
|
|
|
Drawings approved, with conditions, after resubmittal review.
|
Plan resubmittals received | | | 3/5/1999 | | PEND |
|
|
|
Additional resubmittals received from the architect.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/5/1999 | | PASS |
|
|
|
|
testing condition printout | | | 3/5/1999 | | |
|
|
|
|
Print permit w/o conditions | | | 3/5/1999 | | |
|
|
|
|
Telephone call | | | 3/5/1999 | | PASS |
|
|
|
LEFT MESS THAT PLANS ARE READY
|
Print Occupancy Form | | | 3/5/1999 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/5/1999 | | |
|
|
|
|
Plan resubmittals received | | | 2/18/1999 | | PEND |
|
|
|
RECEIVED RESUBMITTALS FROM BOB MAXEY, MAXEY AND MAXEY ARCHITECTS, FORWARDED SAME TO CARL WESTFALL. DAR 2/18/99
|
Plan Review Completed(1st rev) | | | 1/8/1999 | | FAIL |
|
|
|
UBC issue
|
Routing - FIRE | 1/7/1999 | | 1/8/1999 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 12/29/1998 | | 1/6/1999 | | |
|
|
|
|
Plan Reviewer's activity | | | 1/4/1999 | | |
|
|
|
UBC plan review started January 4, 1999 and finished January 6, 1999. A response from the Architect is required. See conditions list.
|
Routing - PUBLIC WORKS | 12/29/1998 | | 12/29/1998 | | PASS |
|
|
|
|
Routing - PLANNING | 12/21/1998 | | 12/29/1998 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 12/15/1998 | | 12/21/1998 | | |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 12/21/1998 | | |
|
|
|
Route to PLANNING, PUBLIC WORKS, PLAN CHECK and FIRE.
|
Recd Pcfee & Taken To Pln CK | | | 12/15/1998 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/15/1998 | | PASS |
|
|
|
|
Application received | | | 12/15/1998 | | PASS |
|
|
|
|
Case Summary (BLD) | | | | | |
|
|
|
|