Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD98-03929
StatusFinaled
Name GAIL ALLEN
Site Address 4920 W OVERLAND RD
Project NameKEY BANK OF IDAHO
Customer Number 
ePlanReviewNo
Description
KEY BANK OF IDAHO * TO CONSTRUCT A NEW, ONE STORY, 3,001 SQ.FT. WOOD FRAMED, TYPE V NONRATED, SHELL ONLY WITH INSTALLATION OF SUSPENDED CEILING AND EXTERIOR WALL WITH BRICK VENEER & EIFS FINISHES. ALL CONCTRUCTION PER THE APPROVED PLANS, ATTACHED COMMENT LIST, CABO/ANSI A117.1 AND THE 1997 EDITION OF THE UBC. THIS IS A SHELL BUILDING ONLY THERE WILL NOT BE A CERTIFICATE OF OCCUPANCY ISSUED UNDER THIS PERMIT. SEPARATE PERMITS AND PLANS REQUIRED TO FINISH THIS SPACE. A SEPARATE CERTIFICATE OF OCCUPANCY IS REQUIRED TO OCCUPY THIS SPACE. MJP DRH98-0128 (PC#892-98)
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
(F) Reprint permit  10/27/1999 DONE
Fee Review-notes4/8/1999 10/27/1999 DONE
Letter of compliance  10/22/1999 DONE
Letter of Compliance #18161 issued 10-22-99.
BLD-Final10/20/199910/21/199910/21/1999PPASS
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 10/20/1999 at 20:00:07. Contact: ###-####. L/C only, shell. Card to cont.
BLD-Final10/15/199910/18/199910/18/1999APART
DetailsCarl Dependahl
###-#### T/I ok for C/O, card to contractor
BLD-Final10/13/199910/14/199910/14/1999AFAIL
DetailsCarl Dependahl
tim--- ###-#### cell fn occ insp C/N issued occupied W/O temp. occ. Sign off
PRINT ACTIONS  10/14/1999 DONE
Print Occupancy Form  10/14/1999 DONE
FIRE-Final Inspection10/6/199910/7/199910/7/1999APASS
DetailsRick Jackson
tim ###-#### reinsp ok for cert at completion
BLD-Final10/6/199910/6/199910/6/1999PFAIL
DetailsCarl Dependahl
###-####\ keep c\n
BLD-Final9/21/19999/21/19999/21/1999AFAIL
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 09/21/1999 at 07:22:25. Contact: ###-####. C/N; safety glazing, other finals, ok for T/O card to contractor
FIRE-Final Inspection9/20/19999/20/19999/20/1999 PART
DetailsJoe Tawney
Scheduled by a contractor via Hello! on 09/20/1999 at 08:21:54. Contact: ###-####. Ok for temp. occ. On shell
Code Occupancy Approval  9/17/1999 PASS
THIS PERMIT IS FOR BOTH THE STORE AND BANK (DRH98-0128) THE DUMPSTER SCREENING IS NOT COMPLETED AND THE FRONT LANDSCAPE IS NOT COMPLETED FOR THE BANK, I AM SIGNING OFF THE BANK AS A FINAL BUT WILL HOLD UP STORE TILL ALL CONDITIONS HAVE BEEN MET FOR THE COMPLETE PROJECT. SIGNS, LANDSCAPE, REMOVE TRAILERS, AND OTHER CONDITIONS FOR BOTH BUILDINGS.
Other9/9/19999/10/19999/10/1999APART
DetailsCarl Dependahl
ok to continue ceiling, keep c/n
Other9/9/19999/9/19999/9/1999 FAIL
DetailsCarl Dependahl
ceiling grid... C/N
INSP - Framing/Rough-in7/30/19997/30/19997/30/1999PNR
DetailsJim Storey
07/30/99 301 - ROOF DRAIN EAST SIDE OF KEY BANK BOB ###-#### late insp t
INSP - Framing/Rough-in7/20/19997/20/19997/20/1999PPART
DetailsCarl Dependahl
07/20/99 340 - ok to cover restrooms; hd bolts installed ok. Contact ph
INSP - Framing/Rough-in7/14/19997/14/19997/14/1999PPART
DetailsCarl Dependahl
07/14/99 340 - complete bolts at ext wall; ok to cover at safe area.Sche
INSP - Framing/Rough-in6/30/19996/30/19996/30/1999PPART
DetailsCarl Dependahl
06/30/99 340 - roof struct ok shear wall nailing ok, fasten hd's. Conta
INSP - Framing/Rough-in6/23/19996/25/19996/28/1999PFAIL
DetailsCarl Dependahl
06/25/99 340 - NEED OTHER INSPS 1ST 06/25/99 340 - Scheduled by Hello!. Contact phone is [8502262].
INSP - Concrete6/23/19996/25/19996/25/1999APART
DetailsCarl Dependahl
06/25/99 340 - spec insp onsite. Contact phone is [8502262]. pend repor
INSP - Foundation6/24/19996/24/19996/24/1999 PART
DetailsCarl Dependahl
/ / 340 - CONF W/BLDR RE FRAME REQ'S
INSP - Framing/ Rough-in6/24/19996/24/19996/24/1999 PART
DetailsCarl Dependahl
/ / 340 - CONF ONLY W/ BLDR
INSP - Concrete6/7/19996/8/19996/8/1999APART
DetailsCarl Dependahl
06/08/99 340 - pend specinsp reports.MTI onsite Contact phone is [850226
INSP - Foundation5/27/19995/27/19995/27/1999PPART
DetailsCarl Dependahl
05/27/99 340 - mti onsite, pend report. Contact phone is [8502262].
INSP - Foundation5/26/19995/26/19995/26/1999PPART
DetailsCarl Dependahl
05/26/99 340 - Scheduled by Hello!. Contact phone is [8502262]. mti ons
INSP - Foundation5/24/19995/25/19995/25/1999PPART
DetailsCarl Dependahl
05/25/99 340 - [8502262]. MTI ONSITE
INSP - Foundation5/24/19995/24/19995/24/1999PPART
Details
05/24/99 338 - made ok for pour with sp insp approvals
(F) Reprint permit  4/14/1999
Issue PAID IN FULL permit  4/13/1999
Telephone call  4/8/1999 PASS
LEFT MESS THAT PERMIT IS READY
Print Pending Permit.LaserJet4  4/7/1999 PASS
PLANS/APPL TAKEN TO FRONT DESK  4/7/1999 PASS
Plan Reviewer's activity  4/7/1999 PASS
Print Occupancy Form  4/7/1999
Inspection Record Card- Bld  4/7/1999
Plan assigned to (M_P)1/4/1999 4/7/1999 PASS
DetailsMike Phillips
04/07/99 08:58:59 M_P - this action updated by action script from <<>> in Case No. BLD98-3929
Routing - PUBLIC WORKS4/2/1999 4/5/1999 PASS
Plan Reviewer's activity  3/30/1999 PEND
Waitin for others to approve plans and need response to structural comment.
Routing - PUBLIC WORKS3/29/1999 3/30/1999 FAIL
Routing - PLANNING3/22/1999 3/29/1999 PASS
Approved per conditions of DRH98-0128.
Routing - PUBLIC WORKS3/29/1999 3/29/1999 FAIL
REQUIRES PROOF OF LEGAL LAND DIVISION PER JIM RICH. DAR 3/29/99
Routing Off Site - STRUCTURAL3/19/1999 3/25/1999 PASS
SENT RESUBMITTALS TO CONSULTING STRUCTURAL ENGINEER. DAR 3/19/99
Plan resubmittals received  3/8/1999 PEND
RECEIVED PLAN RESUBMITTALS FROM RANDY HAVERFIELD, FORWARDED SAME TO MIKE PHILLIPS. DAR 3/8/99
Routing Off Site - STRUCTURAL12/29/1998 1/19/1999 FAIL
CONTACTED PDQ TO TAKE PLANS TO OUTSIDE ENG. Requested resubmittals and second review.
Routing - FIRE1/8/1999 1/13/1999 PASS
as noted a3 and m1
Plan Review Completed(1st rev)  1/13/1999 FAIL
ubc, planning and PW issues
Plan Reviewer's activity  1/8/1999
pARTICIAL REVIEW COMPLETED WAITING FOR COMMENTS FROM OUTSIDE ENGINEERING FIRM PRIOR TO SENDING MY COMMENT.
Routing - PLUMBING1/5/1999 1/5/1999 PASS
Plan assigned to (JCM)12/29/1998 1/4/1999 PASS
DetailsJohn Menard
Routing - PLANNING12/31/1998 12/31/1998 PASS
PER CUP
Routing - PUBLIC WORKS12/29/1998 12/31/1998 FAIL
STREET LIGHTS ARE. THIS PROJECT LIES ADJACENT TO A MAJOR COLLECTOR AS ARTIERIAL. A LIGHTING PLAN DESIGNED TO I.E.S. STANDARDS MUST BE SUBMITTED FOR APPROVAL BY THE BOISE CITY PUBLIC WORKS DEPARTMENT FOR THE FOLLOWING ROADWAY: ENTRANCE ON OVERLAND ENTRANCE ON ORCHARD. PER BILL COLSON. KMM
Plan assigned to (MYS)12/28/1998 12/29/1998
DetailsMarlene Southard
Plan routing begun/NEW & ADDTN  12/29/1998
Plans ACCEPTED BY PLAN TECH  12/29/1998 PASS
Application received  12/28/1998 PASS
Received Certificate of Value  12/28/1998 PASS
Recd Pcfee & Taken To Pln CK  12/28/1998