Fee Review-notes | 2/23/2000 | 2/23/2000 | 3/15/2000 | | DONE |
|
|
|
|
(F) Reprint permit | | | 3/14/2000 | | DONE |
|
|
|
|
Permanent occupancy UNPAID FEE | | | 3/9/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8157 issued 3-9-00 to Williams Communications.
|
BLD-Final | 3/6/2000 | 3/8/2000 | 3/8/2000 | P | PASS |
|
|
|
signed the occ req card perm
|
Permanent Occupancy | | 3/8/2000 | 3/8/2000 | | DONE |
|
|
|
|
Code Occupancy Approval | | | 3/8/2000 | | PASS |
|
|
|
Jim S. inspected 3/3/00 - still needed 3 lights up. Site inspection revealed lighting complete. DRH98-0246 File contains "conflicting data". Site plans and etc. show efffectively what was constructed as it is on site....accompanying building elevations depict the rod-iron fence to be placed at the east side of the rear (south elevation) of the building in lieu of the west side of the rear (south elevation) of the building. Building elevations are dated rec'd/ 12/98. Plans stamped and dated approved and on site are dated 1/29/99. I read through the letter of approval and no notations/conditions had been made to clarify or indicate that "the building elevation plans dated 12/98 were specifically approved as a revision to or to supercede approved plans dated 1/29/99.....therefore, signed off the Final on this project as per approved plans on site.
|
FIRE-Final Inspection | 3/3/2000 | 3/6/2000 | 3/6/2000 | P | PASS |
Rick Jackson
|
|
|
Jim ###-####
|
BLD-Other | 11/22/1999 | 11/22/1999 | 11/22/1999 | P | PART |
|
|
|
BOND BEAM JIM ###-#### (11/26/99 eng. Shear SFNDS).
|
BLD-Footing | 11/4/1999 | 11/4/1999 | 11/4/1999 | P | PART |
|
|
|
jim--- ###-#### ft insp Ok w/sp insp. Approval
|
BLD-Footing | 10/29/1999 | 10/29/1999 | 10/29/1999 | P | PART |
|
|
|
jim-- ###-#### ft insp R-bar placed/ sp insp. Ok
|
BLD-Footing | 10/25/1999 | 10/26/1999 | 10/26/1999 | A | PART |
|
|
|
JIM-- ###-#### FT INSP East to West spread footing for shear wall
|
BLD-Footing | 10/18/1999 | 10/19/1999 | 10/19/1999 | A | PART |
|
|
|
JIM ###-#### Made ok w/sp. Insp approvals
|
BLD-Concrete | 10/1/1999 | 10/4/1999 | 10/4/1999 | P | PART |
|
|
|
AROUND 1:30 IF POSSIBLE JIM ###-#### made ok w/ sp insp approval drill dowels into exist footing
|
Routing Off Site - A.C.H.D | 8/17/1999 | | 8/17/1999 | | |
|
|
|
The brought in a certificate verifying that they paid the permit #on the certificate was 99-2339
|
Telephone call | | | 8/17/1999 | | PASS |
|
|
|
jim###-####
|
Issue PAID IN FULL permit | | | 8/17/1999 | | |
|
|
|
|
Plan assigned to (MLO) | 1/20/1999 | | 8/16/1999 | | PASS |
Mike Otto
|
|
|
|
Print Occupancy Form | | | 8/16/1999 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/16/1999 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 8/16/1999 | | |
|
|
|
|
Telephone call | 8/10/1999 | | 8/10/1999 | | |
|
|
|
Talked to Pamela Dreef at Gensler ###-#### about prep for permit issuance. Informed her that the 6 rolls of resubmittals needed to be inserted into the drawings and Mike's final signature and plan review needed to be attached prior to issuance. Pamela is sending the contractor to insert the revised drawings and to pick up a interior demolition permit. The full permit cannot be issued until Mike O. returns.
|
Routing - PLUMBING | 8/4/1999 | | 8/9/1999 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 8/3/1999 | | 8/4/1999 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 8/3/1999 | | 8/4/1999 | | PASS |
|
|
|
|
Plan resubmittals received | | | 8/3/1999 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM CARTER BURGESS, FORWARDED SAME TO MIKE OTTO. 8/3/99 DAR
|
Plan resubmittals requested | | | 7/28/1999 | | FAIL |
|
|
|
STRUCTRUAL CORRECTIONS MAIELD AND FAXED TO APPLICANT. MLO
|
Routing Off Site - STRUCTURAL | 7/6/1999 | | 7/26/1999 | | FAIL |
|
|
|
2-22-99 - RECEIVED PLANS BUT CALCULATIONS CANNOT BE COMPLETED UNITL DESIGNING ENGINEER GETS SOILS REPORT PER ARCHITECT. MLO FORWARDED STRUCTUAL PLANS TO CONSULTANT VIA PDQ. DAR 7/6/99
|
Telephone call | | | 7/20/1999 | | |
|
|
|
PAMELA DREEF REQUESTING DEMO PERMIT. I FAXED A NEW CERT. AND THERE ORIGINAL CERT. KMM
|
Routing - PUBLIC WORKS | 7/20/1999 | | 7/20/1999 | | PASS |
|
|
|
|
Plan resubmittals received | | | 7/16/1999 | | PEND |
|
|
|
Plan resubmittals received from CEI Engineering, forwarded two sets to Mike Otto and three sets to brian Murphy. DAR 7/16/99
|
Routing - PUBLIC WORKS | 7/16/1999 | | 7/16/1999 | | FAIL |
|
|
|
DRAINAGE PLAN REQUIRES ACHD APPROVAL, PER BRIAN MURPHY. DAR 7/16/99
|
Plan resubmittals received | | | 7/6/1999 | | |
|
|
|
RECEIVED THREE COPIES OF SOILS REPORT, TWO COPIES OF STRUCT. CALCS. THREE COPIES OF S0.01, S2.01, S2.02, S4.01, S4.02, S4.03, S4.04 ROUTED TO MIKE O. KMM
|
Plan resubmittals requested | | | 3/15/1999 | | FAIL |
|
|
|
SECOND REQUEST FOR STRUCTRUAL CALCULATIONS AND SOILS REPORT. MLO
|
Routing - PLAN CHECK | 2/11/1999 | | 3/15/1999 | | FAIL |
|
|
|
HAVE NOT RECEIVED STRUCTURAL CALCS OR SOILS REPORT. ARCHITECT NOTIFIED THAT PLAN REVIEW CANNOT CONTINUE WITHOUT THIS INFORMATION. MLO
|
Plan resubmittals received | | | 2/22/1999 | | |
|
|
|
RECEIVED 2 EA. CORRECTED SHEETS, ONE RESPONSE LETTER WITH 6 ATACHMENTS. ONE COPY OF ARCHITECTRUAL PLANS AND STRUCTURAL PLANS, 3 COPIES OF ALL REVISED PLANS AND WRITTEN RESPONSE LETTER FOR STRUCTURAL REVIEW. THE STRUCT. ENGINEER IS WAITING FOR THE SOILS REPORT BEFORE THEY CAN DO THE STRUCT. CALS. ROUTED TO MIKE O. KMM
|
Plan resubmittals received | | | 2/22/1999 | | PEND |
|
|
|
RECEIVED RESUBMITTALS BUT STUCTRUAL IS STILL INCOMPLETE. CALCULATIONS HAVE NOT BEEN FINISHED ACCORDING TO ARCHITECT. MLO
|
Routing - FIRE | 2/5/1999 | | 2/10/1999 | | PASS |
|
|
|
alarms approved as noted on plans
|
Plan Review Completed(1st rev) | | | 2/10/1999 | | FAIL |
|
|
|
ubc and pw fails
|
Plan resubmittals requested | | | 2/5/1999 | | FAIL |
|
|
|
CORRECTIONS MAILED AND FAXED TO ARCHITECT. MLO
|
Routing - PLAN CHECK | 1/27/1999 | | 2/5/1999 | | FAIL |
|
|
|
|
Routing - PUBLIC WORKS | 1/21/1999 | | 1/27/1999 | | FAIL |
|
|
|
REQUIRES DRAINAGE PLAN APPROVAL FROM ACHD, PER BRIAN MURPHY. DAR 1/27/99
|
Routing - PLANNING | 1/21/1999 | | 1/21/1999 | | PASS |
|
|
|
x-ref. DRH98-0246
|
Plan assigned to (MYS) | 12/29/1998 | | 1/20/1999 | | |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 1/20/1999 | | |
|
|
|
Route to PLANNING, PUBLIC WORKS, PLAN CHECK and FIRE.
|
Telephone call | | | 1/19/1999 | | |
|
|
|
RECEIVED A CALL FROM GREG LACOUR. HE IS REQUESTING A DEMO. HE WILL FAX A REVISED CERT. OF VALUE AND A CERT. OF VALUE FOR THE DEMO. KMM
|
Plans ACCEPTED BY PLAN TECH | | | 1/19/1999 | | PASS |
|
|
|
1-19-99 RECEIVED STAMPED AND SIGNED PLANS. KMM
|
Recd Pcfee & Taken To Pln CK | | | 12/29/1998 | | |
|
|
|
|
Application received | | | 12/29/1998 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 12/29/1998 | | HOLD |
|
|
|
PLANS NOT STAMPED OR SIGNED.
|
Received Certificate of Value | | | 12/29/1998 | | PASS |
|
|
|
|
Case Summary (BLD) | | | | | |
|
|
|
|