Fee Review-notes | 2/16/1999 | | 11/10/1999 | | DONE |
|
|
|
|
Letter of compliance | | | 10/19/1999 | | DONE |
|
|
|
Letter of Compliance #17930 issued 10-19-99.
|
BLD-Final | 10/12/1999 | 10/12/1999 | 10/12/1999 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/12/1999 at 08:26:06. Contact: ###-####.
|
BLD-Final | 10/4/1999 | 10/5/1999 | 10/5/1999 | A | FAIL |
Wes Worcester
|
|
|
Scheduled by a contractor via Hello! on 10/04/1999 at 10:50:36. Contact: ###-####. Need fire inspection to do fire sprinkler
|
FIRE-Sprinkler Rough-in | 10/1/1999 | 10/4/1999 | 10/4/1999 | | PASS |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 10/01/1999 at 14:06:47. Contact: ###-####. Occupancy approved
|
CHANGE STATUS TO (I) | | | 9/22/1999 | | DONE |
|
|
|
|
INSP - Final | 8/31/1999 | 9/3/1999 | 9/3/1999 | A | FAIL |
Jim Storey
|
|
|
09/03/99 301 - Scheduled by Hello!. Contact phone is [3681283].
|
INSP-Final Inspection | 8/31/1999 | 9/2/1999 | 9/2/1999 | A | FAIL |
Rick Jackson
|
|
|
need info on extinguishing system and current inspection for CO2 system
|
INSP - Framing/Rough-in | 5/3/1999 | 5/4/1999 | 5/4/1999 | P | PART |
Jim Storey
|
|
|
05/04/99 301 - pending ele final
|
INSP-Alarm Testing | 5/3/1999 | 5/4/1999 | 5/4/1999 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by Hello!. Contact phone is [3681283]. alarms weren't complete
|
Receive PAYMENT IN FULL | | | 4/7/1999 | | |
|
|
|
|
INSP - Framing/Rough-in | 3/24/1999 | 3/25/1999 | 3/25/1999 | A | PASS |
Jim Storey
|
|
|
03/25/99 301 - SCLG-OK SUSPENDED CEILING
|
INSP - Concrete | 3/15/1999 | 3/16/1999 | 3/16/1999 | A | PASS |
Jim Storey
|
|
|
03/16/99 301 - FRMS-OK FORMS-REBAR
|
Received partial PAYMENT | | | 3/8/1999 | | |
|
|
|
|
Plan Reviewer's activity | | | 2/12/1999 | | PASS |
|
|
|
REVIEWED AND APPROVED SUBMITTAL FOR ADDITIONAL WORK, NEW ELECTRICAL TRANSFORMER AND CONCRETE SUPPORT SLAB. I GAVE LINDA H. A COPY OF THE REVISED CERTIFICATE OF VALUE TO REFLECT THE ADDITIONAL VALUE.
|
Issue & PRINT FEE-DUE permit | | | 2/10/1999 | | |
|
|
|
|
Plan assigned to (JCM) | 1/4/1999 | | 2/8/1999 | | PASS |
John Menard
|
|
|
|
Routing - PLAN CHECK | 1/28/1999 | | 2/8/1999 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/8/1999 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 2/8/1999 | | PASS |
|
|
|
REVIEWED AND APPROVED REVISED PLANS AS SUBMITTED WITH ATTACHED REQUIREMENT LIST.
|
Inspection Record Card- Bld | | | 2/8/1999 | | |
|
|
|
|
Telephone call | | | 2/8/1999 | | PASS |
|
|
|
talked to tony rey to verify plans are ready
|
Print Occupancy Form | | | 2/8/1999 | | |
|
|
|
|
Plan resubmittals received | | | 2/5/1999 | | |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEETS A3.1, FIRE & SPRINKLER DWGS., EO, E2.1.1P, E2.1.2M, E2.2.1P, M2.2 ONE COPY OF FIRE MARSHAL APPROVED LETTER. ROUTED TO JOHN M. KMM
|
Routing - FIRE | 1/22/1999 | | 1/27/1999 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 1/27/1999 | | FAIL |
|
|
|
ubc issues
|
Routing - PLAN CHECK | 1/6/1999 | | 1/22/1999 | | PEND |
|
|
|
|
Plan resubmittals requested | | | 1/22/1999 | | PEND |
|
|
|
MAILED TONY RAY A COPY OF THE PLAN REVIEW COMMENT LIST REQUESTING REVISTIONS.
|
Routing - PUBLIC WORKS | 1/4/1999 | | 1/5/1999 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | 1/4/1999 | | 1/4/1999 | | |
|
|
|
|
Issue & PRINT FEE-DUE permit | | | 12/31/1998 | | |
|
|
|
|
Application received | | | 12/31/1998 | | |
|
|
|
|