Permit Information
Permit NumberBLD98-03960
StatusFinaled
Name MICRON TECH
Site Address 7560 S FEDERAL WAY
Project NameMICRON #32
Customer Number 
ePlanReviewNo
Description
BUILDING #32 - SIMM LINE EXPANSION AND CORRIDOR EXTENSION (32-982344) TO DEMOLISH AND AND REMOVE EXISTING INTERIOR PARTITIONS, DOORS AND CEILINGS AT EXISTING OFFICE AND PRODUCTION AREAS AND TO INSTALL NEW PARTITIONS, DOORS AND CEILINGS TO EXPAND THE SIMM LINE PRODUCTION ASSEMBLY AREA 113A; AND TO EXTEND THE EXISTING CORRIDOR 100P TO THE EAST EXTERIOR WALL AND EXIT DOOR. THIS WORK IS BETWEEN GRID LINES 1&6 AND A&B AND D&E. THIS REMODEL INVOLVES APPROXIMATELY 21,000 SQUARE FEET OF THE EXISTING BUILDING. THIS PERMIT ALSO INCLUDES THE INSTALLATION OF A NEW ELECTRICAL TRANSFORMER AND CONCRETE SUPPORT PAD AT THE EXTERIOR OF THE BUILDING ON THE WEST SIDE OF THE BUILDING. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED REQUIREMENT LIST. TPC# 902-98/JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes2/16/1999 11/10/1999 DONE
Letter of compliance  10/19/1999 DONE
Letter of Compliance #17930 issued 10-19-99.
BLD-Final10/12/199910/12/199910/12/1999PPASS
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/12/1999 at 08:26:06. Contact: ###-####.
BLD-Final10/4/199910/5/199910/5/1999AFAIL
DetailsWes Worcester
Scheduled by a contractor via Hello! on 10/04/1999 at 10:50:36. Contact: ###-####. Need fire inspection to do fire sprinkler
FIRE-Sprinkler Rough-in10/1/199910/4/199910/4/1999 PASS
DetailsJoe Tawney
Scheduled by a contractor via Hello! on 10/01/1999 at 14:06:47. Contact: ###-####. Occupancy approved
CHANGE STATUS TO (I)  9/22/1999 DONE
INSP - Final8/31/19999/3/19999/3/1999AFAIL
DetailsJim Storey
09/03/99 301 - Scheduled by Hello!. Contact phone is [3681283].
INSP-Final Inspection8/31/19999/2/19999/2/1999AFAIL
DetailsRick Jackson
need info on extinguishing system and current inspection for CO2 system
INSP - Framing/Rough-in5/3/19995/4/19995/4/1999PPART
DetailsJim Storey
05/04/99 301 - pending ele final
INSP-Alarm Testing5/3/19995/4/19995/4/1999PFAIL
DetailsRick Jackson
Scheduled by Hello!. Contact phone is [3681283]. alarms weren't complete
Receive PAYMENT IN FULL  4/7/1999
INSP - Framing/Rough-in3/24/19993/25/19993/25/1999APASS
DetailsJim Storey
03/25/99 301 - SCLG-OK SUSPENDED CEILING
INSP - Concrete3/15/19993/16/19993/16/1999APASS
DetailsJim Storey
03/16/99 301 - FRMS-OK FORMS-REBAR
Received partial PAYMENT  3/8/1999
Plan Reviewer's activity  2/12/1999 PASS
REVIEWED AND APPROVED SUBMITTAL FOR ADDITIONAL WORK, NEW ELECTRICAL TRANSFORMER AND CONCRETE SUPPORT SLAB. I GAVE LINDA H. A COPY OF THE REVISED CERTIFICATE OF VALUE TO REFLECT THE ADDITIONAL VALUE.
Issue & PRINT FEE-DUE permit  2/10/1999
Plan assigned to (JCM)1/4/1999 2/8/1999 PASS
DetailsJohn Menard
Routing - PLAN CHECK1/28/1999 2/8/1999 PASS
PLANS/APPL TAKEN TO FRONT DESK  2/8/1999 PASS
Plan Reviewer's activity  2/8/1999 PASS
REVIEWED AND APPROVED REVISED PLANS AS SUBMITTED WITH ATTACHED REQUIREMENT LIST.
Inspection Record Card- Bld  2/8/1999
Telephone call  2/8/1999 PASS
talked to tony rey to verify plans are ready
Print Occupancy Form  2/8/1999
Plan resubmittals received  2/5/1999
RECEIVED TWO COPIES OF REVISED SHEETS A3.1, FIRE & SPRINKLER DWGS., EO, E2.1.1P, E2.1.2M, E2.2.1P, M2.2 ONE COPY OF FIRE MARSHAL APPROVED LETTER. ROUTED TO JOHN M. KMM
Routing - FIRE1/22/1999 1/27/1999 PASS
Plan Review Completed(1st rev)  1/27/1999 FAIL
ubc issues
Routing - PLAN CHECK1/6/1999 1/22/1999 PEND
Plan resubmittals requested  1/22/1999 PEND
MAILED TONY RAY A COPY OF THE PLAN REVIEW COMMENT LIST REQUESTING REVISTIONS.
Routing - PUBLIC WORKS1/4/1999 1/5/1999 PASS
Plans ACCEPTED BY PLAN TECH1/4/1999 1/4/1999
Issue & PRINT FEE-DUE permit  12/31/1998
Application received  12/31/1998