Fee Review-notes | 2/4/1999 | | 4/26/1999 | | |
|
|
|
|
Permanent occupancy | | | 4/15/1999 | | PASS |
|
|
|
Perm. Occ. Cert. #7741 issued 4-15-99 to Dr. Belinda Murphy in the Curtis Professional Plaza.
|
Permanent Occupancy | | 4/13/1999 | 4/13/1999 | | DONE |
|
|
|
|
Temporary occupancy | | | 4/5/1999 | | PASS |
|
|
|
Temp. Occ. Cert. #3812 issued 4-5-99 to Dr. Belinda Murphy.
|
INSP - Final | 4/2/1999 | 4/2/1999 | 4/2/1999 | P | PASS |
Carl Dependahl
|
|
|
04/02/99 340 - ###-#### MIKE//FINAL...struct & heating ok for perm. c/o.
|
INSP - Final | 3/31/1999 | 3/31/1999 | 3/31/1999 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR PERM OCC
|
INSP - Final | 3/30/1999 | 3/31/1999 | 3/31/1999 | P | FAIL |
Carl Dependahl
|
|
|
03/31/99 340 - late pm Mike ###-####, NEED PLBG OK, OK FOR T/O
|
INSP-Conference | 3/30/1999 | 3/30/1999 | 3/30/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - CONF WITH ARCH MAEK KINGHORN REG EXIT SIGN
|
INSP - Final | 3/29/1999 | 3/30/1999 | 3/30/1999 | P | FAIL |
Carl Dependahl
|
|
|
03/30/99 340 - ###-#### MIKE//FINAL has htg cn, etc. no further insp
|
INSP-Final Inspection | 3/25/1999 | 3/29/1999 | 3/29/1999 | P | PART |
Joe Tawney
|
|
|
03/29/99 406 - FINAL OK FOR TEMP OCC, BLDG SPKLR SYSTEM
|
INSP - Framing/Rough-in | 3/18/1999 | 3/18/1999 | 3/18/1999 | P | PART |
Carl Dependahl
|
|
|
03/18/99 340 - ###-#### MIKE//CEILING ok, may need sprinkler modifications.
|
INSP - Framing/Rough-in | 3/4/1999 | 3/5/1999 | 3/5/1999 | A | PART |
Carl Dependahl
|
|
|
03/05/99 340 - need to chk health dept for lead at xray, ok to continue
|
INSP - Framing/Rough-in | 3/1/1999 | 3/1/1999 | 3/1/1999 | | FAIL |
Carl Dependahl
|
|
|
02/26/99 340 - c/n, need lead lining at x-ray, etc....ok to continue
|
Issue PAID IN FULL permit | | | 2/16/1999 | | |
|
|
|
|
Print Occupancy Form | | | 2/11/1999 | | |
|
|
|
|
Inspection Record Card- Bld | | | 2/11/1999 | | |
|
|
|
|
Telephone call | | | 2/11/1999 | | |
|
|
|
called permit ready
|
Plan assigned to (ADS) | 1/8/1999 | | 2/10/1999 | | PASS |
|
|
|
02/10/99 15:48:10 ADS - this action updated by action script from <<>> in Case No. BLD99-0030
|
Routing - PLAN CHECK | 1/22/1999 | | 2/10/1999 | | |
|
|
|
to plumbing
|
Routing - PLAN CHECK | 2/10/1999 | | 2/10/1999 | | PASS |
|
|
|
|
Routing - PLUMBING | 2/10/1999 | | 2/10/1999 | | PASS |
|
|
|
|
Plan resubmittals received | | | 2/10/1999 | | PEND |
|
|
|
RECEIVED RESUBMITTALS AND FORWARDED THEM TO ARLAN SMITH. DAR 2/10/99
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/10/1999 | | PASS |
|
|
|
|
Routing - PLUMBING | 1/20/1999 | | 1/22/1999 | | FAIL |
|
|
|
requested by Lee Rice
|
Routing - PLAN CHECK | 1/12/1999 | | 1/19/1999 | | PASS |
|
|
|
|
Routing - FIRE | 1/19/1999 | | 1/19/1999 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 1/19/1999 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 1/8/1999 | | 1/12/1999 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 1/8/1999 | | |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Application received | | | 1/6/1999 | | |
|
|
|
|