FIRE-Final Inspection | 12/15/1999 | 12/16/1999 | 12/16/1999 | A | FAIL |
|
|
|
needed to call in str final
|
BLD-Final | 12/16/1999 | 12/16/1999 | 12/16/1999 | A | PASS |
|
|
|
ok to issue l/c per terry record slope protection is bonded l/c # 18262
|
BLD-Final | 12/14/1999 | 12/14/1999 | 12/14/1999 | P | FAIL |
|
|
|
Brad Barker, ###-#### Safety glazing within 18" of floor and 9 sq. ft. must be temp. must block open dumper @ FP w/gass log lighter.
|
BLD-Energy code compliance | 10/5/1999 | 10/6/1999 | 10/6/1999 | A | PASS |
Wes Worcester
|
|
|
KAREN-- ###-#### ENERGY CODE INSP
|
BLD-Framing/Rough-in | 10/1/1999 | 10/4/1999 | 10/4/1999 | A | PASS |
Wes Worcester
|
|
|
KAREN ###-#### AFTER11:00
|
INSP - Framing/Rough-in | 9/1/1999 | 9/2/1999 | 9/2/1999 | A | FAIL |
Wes Worcester
|
|
|
09/02/99 342 - KAREN ###-####. not to eng's specs
|
INSP - Framing/Rough-in | 8/26/1999 | 8/27/1999 | 8/27/1999 | P | PART |
Wes Worcester
|
|
|
08/27/99 342 - SHEER WALL. DAVE ###-####. that done is ok, ck remainder
|
INSP - Framing/Rough-in | 7/20/1999 | 7/21/1999 | 7/21/1999 | A | FAIL |
Wes Worcester
|
|
|
07/21/99 342 - SHEAR WALL DAVE ###-#### not done to engineering
|
INSP - Framing/Rough-in | 7/16/1999 | 7/19/1999 | 7/19/1999 | P | FAIL |
Wes Worcester
|
|
|
07/19/99 342 - SHEAR WALL DAVE ###-####
|
INSP - Foundation | 5/24/1999 | 5/24/1999 | 5/24/1999 | P | PASS |
Wes Worcester
|
|
|
05/24/99 342 - Steve ###-####
|
INSP - Foundation | 5/18/1999 | 5/18/1999 | 5/18/1999 | | PASS |
Wes Worcester
|
|
|
05/18/99 342 - ###-#### STEVE//FOOTING
|
INSP - Foundation | 5/17/1999 | 5/17/1999 | 5/17/1999 | | FAIL |
Wes Worcester
|
|
|
05/17/99 342 - ###-#### STEVE//FOOTING
|
INSP - Foundation | 5/14/1999 | 5/17/1999 | 5/17/1999 | P | FAIL |
Wes Worcester
|
|
|
05/17/99 342 - ###-#### STEVE//FOOTING
|
Issue PAID IN FULL permit | | | 3/29/1999 | | |
|
|
|
|
Inspection Record Card- Bld | | | 3/22/1999 | | |
|
|
|
|
Telephone call | | | 3/22/1999 | | |
|
|
|
called permit ready left message
|
Plan assigned to (DJO) | 1/7/1999 | | 3/19/1999 | | PASS |
Dan Overy
|
|
|
03/19/99 11:38:26 DJO - this action updated by action script from <<>> in Case No. BLD99-0051
|
Print Pending Permit.LaserJet4 | | | 3/19/1999 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/19/1999 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 3/19/1999 | | PASS |
|
|
|
ALL ADDITIONAL INFORMATION RECEIVED. BEAM CALCS DONE BY TOM CORY OF TRUSS JOIST. POST AND FOOTING SIZE ENLARGED AND FOUNDATION ENG. FOR COVERED FRONT PORCH. TALL WALL ENG.
|
Plan Reviewer's activity | | | 3/11/1999 | | PEND |
|
|
|
ADDITIONAL INFORMATION REQ. BEFORE ISSUANCE. BEAM CALCS, POST SIZE, BEARING VERIFICATION.
|
Plans ACCEPTED BY PLAN CHECK | | | 3/11/1999 | | PEND |
|
|
|
|
Routing - PUBLIC WORKS | 1/7/1999 | | 2/22/1999 | | PASS |
|
|
|
|
Routing - PLANNING | 1/7/1999 | | 2/22/1999 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 2/22/1999 | | 2/22/1999 | | PASS |
Rita DeYoung
|
|
|
Approved as category 3.
|
Routing - PUBLIC WORKS GRADING | 1/7/1999 | | 1/7/1999 | | PEND |
Rita DeYoung
|
|
|
No soils report was submitted with plans. Called and left message with Brad Barker that this is required before I can start my review. I also called Russ Hepworth, the engineer, and he said that that they hadn't started it yet but expected to have it done within a few days.
|
Application received | | | 1/7/1999 | | |
|
|
|
|
Routing - PLAN CHECK | 2/24/1999 | | | | PEND |
|
|
|
|