Plans ACCEPTED BY PLAN TECH | | | 1/19/2000 | | |
|
|
|
|
SUPER- Supervisor's review | 5/11/1999 | 5/11/1999 | 5/11/1999 | | |
|
|
|
work looks good c-o issued ok
|
Fee Review-notes | 2/22/1999 | | 4/26/1999 | | |
|
|
|
|
SUPER- Supervisor's review | 4/19/1999 | 4/19/1999 | 4/19/1999 | | |
|
|
|
finish in progress working on final sign offs
|
Permanent Occupancy | | 4/2/1999 | 4/2/1999 | | DONE |
|
|
|
|
Permanent occupancy | | | 4/2/1999 | | PASS |
|
|
|
Perm. Occ. Cert. #7718 issued 4-2-99 to Sole Outdoors at Boise Towne Square.
|
SUPER- Supervisor's review | 3/31/1999 | 3/31/1999 | 3/31/1999 | | |
|
|
|
failed frame corrections in progress carl d is handling.
|
INSP - Final | 3/29/1999 | 3/29/1999 | 3/29/1999 | P | PASS |
Carl Dependahl
|
|
|
03/29/99 340 - ok for co, card to cont.
|
Temporary occupancy | | | 3/29/1999 | | PASS |
|
|
|
Temp. Occ. Cert. #3806 issued 3-29-99 to Sole Outdoors.
|
INSP - Final | 3/26/1999 | 3/26/1999 | 3/26/1999 | P | FAIL |
Carl Dependahl
|
|
|
###-#### jan sole outdoors, nr, recall.
|
INSP - Final | 3/26/1999 | 3/26/1999 | 3/26/1999 | | NR |
Carl Dependahl
|
|
|
03/26/99 340 - ###-#### jan sole outdoors
|
INSP-Final Inspection | 3/25/1999 | 3/25/1999 | 3/25/1999 | P | PASS |
Joe Tawney
|
|
|
03/25/99 406 - FINAL OK FOR PERM OCC
|
INSP-Alarm Testing | 3/25/1999 | 3/25/1999 | 3/25/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON TEST OF SMOKE DET AND EXH DAMPER
|
INSP-Alarm Testing | 3/25/1999 | 3/25/1999 | 3/25/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON TEST OF SMOKE DET AND EXH DAMPER
|
INSP - Framing/Rough-in | 3/24/1999 | 3/24/1999 | 3/24/1999 | P | PART |
Carl Dependahl
|
|
|
03/24/99 340 - ###-#### JAN//REINSPECT CEILING GRID
|
INSP - Framing/Rough-in | 3/22/1999 | 3/23/1999 | 3/23/1999 | P | FAIL |
Carl Dependahl
|
|
|
03/23/99 340 - ###-#### JAN//CEILING GRID need seismics, n.c. backing for wood soffit at hall
|
INSP-Sprinkler Rough-in/Hydro | 3/15/1999 | 3/15/1999 | 3/15/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON SPKLR ROUGH IN
|
INSP-Sprinkler Rough-in/Hydro | 3/15/1999 | 3/15/1999 | 3/15/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON SPKLR ROUGH IN
|
INSP - Framing/Rough-in | 3/11/1999 | 3/11/1999 | 3/11/1999 | P | PART |
Carl Dependahl
|
|
|
03/11/99 340 - JAN GERDER ###-#### rec'd spec insp for welds, ok to continue, keep c/n for demising walls
|
INSP - Framing/Rough-in | 3/9/1999 | 3/10/1999 | 3/10/1999 | A | FAIL |
Carl Dependahl
|
|
|
03/10/99 340 - ###-#### JAN \\\SOLE OUTDOORS still need spec insp report
|
INSP - Framing/Rough-in | 3/9/1999 | 3/9/1999 | 3/9/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - REAR OF SPACE, SOFFITS, ETC, FRONT NR
|
INSP - Framing/Rough-in | 3/8/1999 | 3/9/1999 | 3/9/1999 | A | FAIL |
Carl Dependahl
|
|
|
03/09/99 340 - nr
|
SUPER- Supervisor's review | 3/4/1999 | 3/4/1999 | 3/4/1999 | | |
|
|
|
smoke evac system has to provide supply and return for both areas created by placing full height demisising wall in the area
|
Routing - PLAN CHECK | 2/1/1999 | | 2/19/1999 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 2/19/1999 | | PASS |
|
|
|
|
Print Occupancy Form | | | 2/19/1999 | | |
|
|
|
|
Plan Reviewer's activity | | | 2/19/1999 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/19/1999 | | PASS |
|
|
|
|
Issue PAID IN FULL permit | | | 2/19/1999 | | |
|
|
|
|
Inspection Record Card- Bld | | | 2/19/1999 | | |
|
|
|
|
Telephone call | | | 2/19/1999 | | PASS |
|
|
|
talked to dave ward at ###-#### to verify plans are ready
|
Plan resubmittals received | | | 2/18/1999 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM STEVE MICKELSON, CSHQA, FORWARDED SAME TO RON HILL. DAR 2/18/99
|
Plan resubmittals received | | | 2/16/1999 | | |
|
|
|
RECEIVED THREE COPIES OF REVISED SHEETS A1, A2, A3, A4, M1, AND E1. THREE COPIES OF STRUCTURAL CALCS. ROUTED TO RON HILL. KMM
|
Plan Reviewer's activity | | | 2/16/1999 | | FAIL |
|
|
|
Recieved engineering, still require additional information and architectual.
|
Office Staff conference/action | | | 2/4/1999 | | |
|
|
|
wrong permit building permit issued should of been demo permit linda transferred fees
|
CHANGE STATUS TO (P) | | | 2/4/1999 | | |
|
|
|
wrong permit issued should of been demo
|
Inspection Record Card- Bld | | | 2/1/1999 | | |
|
|
|
|
Telephone call | | | 2/1/1999 | | |
|
|
|
TALKED TO LILLIAN TOLD HER PLANS ARE READY & GAVE FEES
|
Plan assigned to (R_H) | 1/14/1999 | | 2/1/1999 | | PASS |
|
|
|
|
Routing - FIRE | 1/28/1999 | | 1/29/1999 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 1/28/1999 | | FAIL |
|
|
|
faxed requirements to the architect, will route to fire department.
|
Routing - PLAN CHECK | 1/15/1999 | | 1/28/1999 | | FAIL |
|
|
|
|
Routing - PUBLIC WORKS | 1/14/1999 | | 1/15/1999 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 1/12/1999 | | 1/14/1999 | | |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 1/14/1999 | | |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Recd Pcfee & Taken To Pln CK | | | 1/12/1999 | | |
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/12/1999 | | PASS |
|
|
|
|
Application received | | | 1/12/1999 | | PASS |
|
|
|
|