Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD99-00101
StatusFinaled
Name BRENT BROCKSOME
Site Address 10148 W EMERALD ST
Project NameMCGREGOR/BROCKSOME
Customer Number 
ePlanReviewNo
Description
MCGREGOR/BROCKSOME OFFICE BUILDING * TO CONSTRUCT A NEW 15,000 SQ. FT., ONE STORY OFFICE BUILDING AND RELATED SITE IMPROVEMENTS. THIS BUILDING IS CONSTRUCTED OF A CONCRETE SLAB FLOOR, WOOD FRAMING WITH STEEL INTERIOR COLUMNS AND A CONCRETE TILE ROOF. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED REQUIREMENT LIST. THIS BUILDING WILL HAVE FOUR SEPARATE OFFICE TENANT SUITES AND A CENTRAL CORRIDOR, RESTROOM AND MECHANICAL CORE. SUITE #1 AND THE CORE AREAS WILL BE FINISHED UNDER THIS PERMIT. A SEPARATE TENANT IMPROVEMENT PERMIT WILL BE REQUIRED TO FINISH EACH OF THE REMAINING THREE TENANT SUITES. WITH THE PROPOSED CONSTRUCTION TYPE AND OPEN YARDS, THIS BUILDING IS AT IT'S MAXIMUM ALLOWABLE AREA. BE ADVISED THAT THIS BUILDING MAY NOT BE EXPANDED AT ANY FUTURE DATE. DRH98-0191/CUP98--134/PC#030-99/JCM GRADING PERMIT BLD99-
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  11/27/2012 DONE
Fee Review-notes3/10/1999 9/17/1999 DONE
CHANGED VALUES
INSP-Final Inspection9/2/19999/3/19999/3/1999APASS
DetailsRick Jackson
tested AHU shutdown - occ approved
INSP - Final9/2/19999/3/19999/3/1999APASS
DetailsCarl Dependahl
09/03/99 340 - JOSH ###-####
Permanent Occupancy 9/3/19999/3/1999 DONE
Details
PubWorks Occupancy Approval  9/3/1999 DONE
Drainage project complete, final inspection 09/03/99. Permanent occupancy signed by B.Murphy.
Permanent occupancy  9/3/1999 PASS
Perm. Occ. Cert. #7885 issued 9-3-99 to Pro Staff.
INSP - Final9/1/19999/2/19999/2/1999PFAIL
DetailsCarl Dependahl
JOSH ###-####; CALLED, KEEP C/N. NEED FIRE
INSP-Final Inspection9/1/19999/2/19999/2/1999AFAIL
DetailsJoe Tawney
09/01/99 406 - REINSP FAIL AHU DUCT DETECTORS
Code Occupancy Approval  8/31/1999 PASS
Approved by Jim Soden 8/30/98
INSP - Final8/27/19998/27/19998/27/1999PFAIL
DetailsCarl Dependahl
08/27/99 340 - josh ###-####; c/n, fire code, etc; ok for t/o
INSP-Final Inspection8/27/19998/27/19998/27/1999PFAIL
DetailsJoe Tawney
09/01/99 406 - REINSP FAIL S/F DAMPER DETECTION
INSP - Final8/26/19998/26/19998/26/1999PFAIL
DetailsCarl Dependahl
08/26/99 340 - JOSH ###-####.; need fire, etc
INSP-Final Inspection8/25/19998/26/19998/26/1999AFAIL
DetailsJoe Tawney
09/01/99 406 - FINAL FAIL
Code Occupancy Approval  8/26/1999
Temporary Occupancy reguested by Josh ###-####
INSP-Final Inspection8/24/19998/25/19998/25/1999PFAIL
DetailsJoe Tawney
09/01/99 406 - FINAL FAIL
INSP - Framing/Rough-in8/4/19998/5/19998/5/1999APART
DetailsCarl Dependahl
08/05/99 340 - part grid ok; verbal to seal draft stops prior to tile, r
INSP - Framing/ Rough-in6/29/19996/29/19996/29/1999 PART
DetailsCarl Dependahl
/ / 340 - DRAFT STOPS INSTALLED, SEAL AS NEEDED
INSP - Framing/ Rough-in6/22/19996/22/19996/22/1999 PART
DetailsCarl Dependahl
/ / 340 - TRUSS FIX MADE OK
INSP - Framing/Rough-in6/14/19996/14/19996/14/1999 PART
DetailsCarl Dependahl
06/14/99 340 - ###-#### JOSH//FRAMING trusses ok, ok to cover corr. c/n
INSP - Framing/Rough-in5/25/19995/26/19995/26/1999AFAIL
DetailsCarl Dependahl
05/26/99 340 - ###-#### JOSH//FRAMING, c/n draft stops,trusses, shear, e
INSP - Framing/Rough-in5/25/19995/25/19995/25/1999PPART
DetailsCarl Dependahl
05/25/99 340 - Josh ###-####, COMPLETE 1HR WALL, ADD FASTENERS
INSP - Framing/Rough-in5/20/19995/21/19995/21/1999APART
DetailsCarl Dependahl
###-#### josh//framing; soffit at east 1hr wall ok, need nail off gyp 7" oc at wall both sides. ok to continue.
INSP - Framing/Rough-in5/13/19995/13/19995/13/1999PPART
DetailsCarl Dependahl
05/13/99 340 - initial insp for shear, complete nailing; fasten all memb
INSP - Framing/Rough-in5/10/19995/10/19995/10/1999 PART
DetailsCarl Dependahl
/ / 340 - CONF W/ BLDR; PENDING STEEL SPEC. INSP
INSP - Framing/Rough-in4/21/19994/22/19994/23/1999ANR
DetailsCarl Dependahl
04/22/99 340 - josh ###-####; structural framing; mst straps in at trimm
INSP - Foundation4/19/19994/19/19994/19/1999 PART
DetailsCarl Dependahl
/ / 340 - SLAB, SPEC INSP ONSITE; KEEP C/N FOR REPORTS, ETC
INSP - Foundation3/29/19993/30/19993/30/1999APART
DetailsCarl Dependahl
03/30/99 340 - ###-#### JOSH//FOOTING mti onsite, keep cn pending reports
INSP - Foundation3/26/19993/26/19993/26/1999 PART
DetailsCarl Dependahl
03/26/99 340 - josh ###-#### footing/foundation per cont, has mti onsite; pending reports...keep c/n
INSP - Foundation3/26/19993/26/19993/26/1999PPART
DetailsCarl Dependahl
mti onsite, keep c/n. pend spec insp report
INSP - Foundation3/24/19993/25/19993/25/1999APART
DetailsCarl Dependahl
03/25/99 340 - ###-#### JOSH//FOOTING mti onsite, keep c/n of 3-22
INSP - Foundation3/24/19993/24/19993/24/1999 PART
DetailsCarl Dependahl
/ / 340 - FTGS, HAS SPEC INSP...KEEP CN OF 3-23-99; PENDING REPORT& EN
INSP - Foundation3/23/19993/24/19993/24/1999AFAIL
DetailsWes Worcester
03/24/99 342 - josh ###-#### will have special inspection
(F) Reprint permit  3/11/1999
Plan assigned to (JCM)1/22/1999 3/10/1999 PASS
DetailsJohn Menard
PLAN ASSIGNED TO JOHN MENARD AFTER MIKE PHILLIPS INDICATED HE DID NOT HAVE TIME TO DO THIS PROJECT.
Issue PAID IN FULL permit  3/10/1999
Telephone call  3/10/1999 PASS
TALKED TO BEN JENSEN TO VERIFY PLANS ARE READY
Routing - PLAN CHECK3/10/1999 3/10/1999 PASS
Print Occupancy Form  3/10/1999
PLANS/APPL TAKEN TO FRONT DESK  3/10/1999 PASS
Inspection Record Card- Bld  3/10/1999
Routing - FIRE3/5/1999 3/9/1999 PASS
Routing - PLAN CHECK2/3/1999 3/5/1999
Plan Reviewer's activity  3/4/1999 PASS
PLAN RESUBMITTALS REVIEWED AND APPROVED AS SUBMITTED.
Plan resubmittals received  2/25/1999
RECEIVED TWO COPIES OF REVISED SHEETS A1.1, A4.0, A4.2, A5.1, A5.2, A5.3, A9.1, S2.1, S2.2 AND E-1 ONE COPY OF RESPONSE LETTER AND ONE COPY OF LETTER TO DAN JOHNSON. ROUTED TO JOHN M. KMM
Routing - PUBLIC WORKS2/1/1999 2/3/1999 PASS
Routing - PLANNING2/1/1999 2/1/1999 PASS
PERCUP98-0134 Land division approved by Kent Brown - Record of Survey No. 3562
Routing - PLAN CHECK2/1/1999 2/1/1999
Plan Review Completed(1st rev)  1/29/1999 FAIL
planning - PW fail
Routing - FIRE1/26/1999 1/29/1999 FAIL
DAVE ABO IS READY TO SIGN OFF. PLEASE ROUTE TO HIM AFTER FIRE. KMM
Plan resubmittals requested  1/26/1999 PEND
COPY OF PLAN REVIEW COMMENT LIST WAS MAILED TO BEN JANSEN AT BRS REQUESTING REVISIONS TO ARCHITECTURAL AND STRUCTURAL PLAN SHEETS.
Routing - PLAN CHECK1/21/1999 1/26/1999 PEND
Plan assigned to (M_P)1/13/1999 1/22/1999 PASS
DetailsMike Phillips
Routing - PLUMBING1/21/1999 1/21/1999 PASS
Routing - PLANNING1/19/1999 1/21/1999 PASS
PER DRH98-0191
Routing - PLANNING1/19/1999 1/20/1999 FAIL
PER CUP98-0134. Need to prove legal land division to Kent Brown. Also pending DR approval.
Routing - PUBLIC WORKS1/14/1999 1/19/1999 FAIL
REQUIRES DRAINAGE PLAN REVISION PER BRIAN MURPHY. DAR 1/19/99
Application received  1/15/1999 PASS
RECEIVED RECORD DECLARATION FORM. KMM
Plan routing begun/NEW & ADDTN  1/14/1999
Received Certificate of Value  1/13/1999 PEND
REQUIRES REVISED CERT. OF VALUE. APPLICANT APPLYING FOR GRADING PERMIT. KMM
Routing Off Site - STRUCTURAL1/13/1999 1/13/1999
ENG. WILL BE DONE IN HOUSE PER JOHN M. KMM
Recd Pcfee & Taken To Pln CK  1/13/1999
Plans ACCEPTED BY PLAN TECH  1/13/1999 PASS
Application received  1/12/1999 PEND
REQUIRES RECORD DECLARATION FORM. CONTACTED BEN JANSEN OF THIS NEED. HE WILL BE FAXING OVER. KMM
Plan assigned to (MYS)1/13/1999 1/13/1998 PASS
DetailsMarlene Southard