Letter of compliance | | | 7/27/1999 | | PASS |
|
|
|
issued l/c 7/26/99 to Asin-Erland l/c #17885
|
INSP-Final Inspection | 7/23/1999 | 7/26/1999 | 7/26/1999 | A | PASS |
Joe Tawney
|
|
|
07/26/99 406 - REINSP OK FOR CERT OF COMPLETION
|
INSP - Final | 7/23/1999 | 7/26/1999 | 7/26/1999 | A | PASS |
Carl Dependahl
|
|
|
07/26/99 340 - MIKE ###-####; ok card to contractor
|
INSP - Final | 7/23/1999 | 7/23/1999 | 7/23/1999 | P | FAIL |
Carl Dependahl
|
|
|
keep c/n, conf w/ bldr re fire c/n.
|
INSP-Final Inspection | 7/21/1999 | 7/22/1999 | 7/22/1999 | P | FAIL |
Joe Tawney
|
|
|
07/22/99 406 - FINAL FAIL DOOR HDWRE, LAVATORY TOO FAR FRM WALL
|
INSP - Final | 7/21/1999 | 7/22/1999 | 7/22/1999 | P | FAIL |
Carl Dependahl
|
|
|
07/22/99 340 - Mike ###-#### no insp . need fire, etc
|
Code Occupancy Approval | | | 7/22/1999 | | PASS |
|
|
|
ALL CONDITIONS OF DRH98-0218 & 99-0145MOD HAVE BEEN MET, FINAL OCCUPANCY SIGNED OFF.
|
Code Occupancy Approval | | | 7/21/1999 | | |
|
|
|
Final requested by Michael Ross ###-####
|
INSP - Framing/Rough-in | 5/4/1999 | 5/4/1999 | 5/4/1999 | P | PART |
Wes Worcester
|
|
|
###-#### MIKE//FRAMING
|
INSP - Framing/Rough-in | 4/28/1999 | 4/28/1999 | 4/28/1999 | P | PART |
Carl Dependahl
|
|
|
04/28/99 340 - sheet rock/ Mike ###-#### north wall ok to side
|
INSP - Framing/Rough-in | 4/23/1999 | 4/23/1999 | 4/23/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - NORTH WALL EXT. OK FOR GYP
|
INSP - Foundation | 4/22/1999 | 4/22/1999 | 4/22/1999 | | PASS |
Russ Owen
|
|
|
/ / 407 - FOOTINGS FOR PATIO COVER.
|
INSP - Framing/Rough-in | 4/22/1999 | 4/22/1999 | 4/22/1999 | P | PART |
Carl Dependahl
|
|
|
04/22/99 340 - ###-#### MIKE//SHEAR STRAPS hd42's ok
|
INSP - Framing/Rough-in | 4/21/1999 | 4/21/1999 | 4/21/1999 | P | NR |
Carl Dependahl
|
|
|
04/21/99 340 - shear straps Mike ###-####; recall
|
INSP - Foundation | 3/22/1999 | 3/23/1999 | 3/23/1999 | A | PART |
Carl Dependahl
|
|
|
03/23/99 340 - tony ###-#### steel ok, ftg only
|
INSP - Foundation | 3/22/1999 | 3/22/1999 | 3/22/1999 | P | NR |
Carl Dependahl
|
|
|
03/22/99 340 - need complete forms & bar, recall
|
INSP - Foundation | 3/22/1999 | 3/22/1999 | 3/22/1999 | P | NR |
Carl Dependahl
|
|
|
TONY ###-####, need complete forms
|
(F) Reprint permit | | | 3/12/1999 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 3/11/1999 | | |
|
|
|
|
Print Occupancy Form | | | 2/22/1999 | | |
|
|
|
|
Inspection Record Card- Bld | | | 2/22/1999 | | |
|
|
|
|
Telephone call | | | 2/22/1999 | | |
|
|
|
left message gave dollar amount needs achd
|
Plan assigned to (MLO) | 1/20/1999 | | 2/19/1999 | | PASS |
Mike Otto
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/19/1999 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 2/16/1999 | | 2/19/1999 | | PASS |
|
|
|
PLANS NOT STAMPED OR SIGNED BY ARCHITECT. 2-16-99MLO
|
Routing - PLUMBING | 2/16/1999 | | 2/16/1999 | | PASS |
|
|
|
|
Plan resubmittals received | | | 2/12/1999 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITALS FOR PLUMBING. FORWARDED SAME TO PLUMBING. DAR 1/12/99
|
Plan resubmittals received | | | 2/11/1999 | | |
|
|
|
RECEIVED THREE COPIES OF REVISED SHEETS 4,& 5. TWO COPIES OF STRUCT. CALCS. AND ONE COPY OF RESPONSE LETTER. ROUTED TO MIKE O. KMM PLANS ARE NOT STAMPED AND SIGNED .. ENGINEER CONTACTED MLO.
|
Plan resubmittals received | | | 2/8/1999 | | PEND |
|
|
|
RECEIVED RESUBMITTALS FROM MIKE FAIRCHILD, ARCHITECT, FORWARDED SAME TO MIKE OTTO. NO REVISED CIVIL ENGINEERING AT THIS TIME. MR. ERLAND STATED THAT WE WOULD RECEIVE THE ENGEENERING ON THE 18TH OF FEBRUARY. DAR 2/9/99
|
Plan Review Completed(1st rev) | | | 2/5/1999 | | FAIL |
|
|
|
plumbing and UBC
|
Routing - FIRE | 2/2/1999 | | 2/4/1999 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 2/1/1999 | | 2/2/1999 | | PASS |
|
|
|
|
Plan resubmittals requested | | | 2/1/1999 | | FAIL |
|
|
|
CORRECTIONS MAILED TO ARCHITECT. MLO
|
Routing - PLAN CHECK | 1/27/1999 | | 1/29/1999 | | FAIL |
|
|
|
CORRECTIONS MAILED TO ARCHITECT. NO FAX#. MLO
|
Routing - PLANNING | 1/26/1999 | | 1/27/1999 | | PASS |
|
|
|
PER DRH98-0218
|
Routing - PLUMBING | 1/25/1999 | | 1/26/1999 | | FAIL |
|
|
|
|
Routing - PUBLIC WORKS | 1/21/1999 | | 1/25/1999 | | FAIL |
|
|
|
REQUIRES DRAINAGE PLAN REVISIONS PER BRIAN MURPHY. DAR 01/25/99
|
Plan assigned to (MYS) | 1/19/1999 | | 1/20/1999 | | PASS |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 1/20/1999 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 1/20/1999 | | 1/20/1999 | | |
|
|
|
ENG. WILL BE DONE INHOUSE PER JOHN M.
|
Plan routing begun/NEW & ADDTN | | | 1/20/1999 | | |
|
|
|
|
Received Certificate of Value | | | 1/20/1999 | | PASS |
|
|
|
|
Application received | | | 1/19/1999 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 1/19/1999 | | |
|
|
|
|