Fee Review-notes | 2/9/1999 | | 2/8/2002 | | DONE |
|
|
|
|
INSP - Final | 2/11/1999 | 2/12/1999 | 2/12/1999 | P | PASS |
Carl Dependahl
|
|
|
02/12/99 340 - reinspect ###-#### Dave ok, card to cont
|
INSP - Framing/Rough-in | 2/9/1999 | 2/11/1999 | 2/12/1999 | P | FAIL |
Carl Dependahl
|
|
|
02/11/99 340 - ###-#### Dave, c/n, need elec, eng's ok or joist stif
|
INSP-Final Inspection | 2/11/1999 | 2/11/1999 | 2/11/1999 | | PASS |
Joe Tawney
|
|
|
02/11/99 406 - ###-#### Dave FINAL OK FOR PERM OCC
|
Plans ACCEPTED BY PLAN TECH | | | 2/5/1999 | | PASS |
|
|
|
ROUTED PLANS TO DAN S. PER DAN S. KMM
|
Issue PAID IN FULL permit | | | 2/5/1999 | | |
|
|
|
|
Plan resubmittals requested | | | 2/5/1999 | | |
|
|
|
Required structural engineering from the BTS original structural engineer for relocating the existing electrical transformer from the floor mount to a suspended design to hang from the bar joist & beam system. Also to provide structural engineers review for placement of a 2200 lb safe in the new tenant location to verify adequate support & load distribution. Permit being issued with conditions that the tranformer will not be relocated until said engineering is received & approved and the safe will be relocated or resuported per engineering before a final certificate of occupancy is given to the tenant to open.
|
Routing - PLAN CHECK | 2/5/1999 | | 2/5/1999 | | PASS |
|
|
|
Plan approved with conditions for not relocating the transformer until engineering is submitted and approved for installation to the roof structure and that the safe will be supported or relocate per engineering to be provided before a certificate of occupancy is provided to the tenant, Samuel's Jewelery.
|
Plan assigned to (DRS) | 2/4/1999 | | 2/5/1999 | | PASS |
Dan Stuart
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/5/1999 | | PASS |
|
|
|
PROCESSING FOR PERMIT BASED ON CONDITIONS ATTACHED TO PERMIT.
|
Inspection Record Card- Bld | | | 2/5/1999 | | |
|
|
|
|
Telephone call | | | 2/5/1999 | | |
|
|
|
Call from Dave Lemon project manager at mall for progress of permit. I informed him of agreement and conditions for issuing permit and that the permit is in progress.
|
Print Occupancy Form | | | 2/5/1999 | | |
|
|
|
|
Telephone call | | | 2/5/1999 | | |
|
|
|
Call from Dan Mullin to review what is required in letter for conditions of approval for permit. Will have letter stamped by Idaho licensed architct, D. Nels Reese.
|
Print Pending Permit.LaserJet4 | | | 2/5/1999 | | PASS |
|
|
|
APPROVED PER CONDITIONS
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/5/1999 | | PASS |
|
|
|
Approved with conditions. Taken to the front desk for processing for permit issuance.
|
Print Pending Permit.LaserJet4 | | | 2/5/1999 | | PASS |
|
|
|
Approved with conditions.
|
Additional plans submitted | | | 2/5/1999 | | |
|
|
|
Received letter from architect Dan Mullin and D. Nels Reese his partner with Idaho Stamp concerning transformer and safe engineering design requirements.
|
Telephone call | | | 2/5/1999 | | |
|
|
|
Call from Mr. Lou Menendez, contractor, Houston Texas agreeing to leace the transformer mounted on the floor as is until engineering is provided and approved for relocating to roof structure in ceiling area. Also agreed to relocate or resupport the 2200 lb safe per engineering prior to any occupancy or issuance of a CO to the tenant. A letter to be provided by the architect Dan Mullin under the Idaho license stamp prior to issuance of a permit.
|
Plan assigned to (MYS) | 2/4/1999 | | 2/4/1999 | | |
Marlene Southard
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/4/1999 | | |
|
|
|
|
Application received | | | 2/4/1999 | | |
|
|
|
|