Permanent Occupancy | | 3/19/1999 | 3/19/1999 | | DONE |
|
|
|
|
Permanent occupancy | | | 3/19/1999 | | PASS |
|
|
|
Perm. Occ. Cert. #7693 issued 3-19-99 to the Herrington Law Office.
|
Temporary occupancy | | | 3/11/1999 | | PASS |
|
|
|
Temp. Occ. Cert. #3794 issued 3-11-99 to the Herrington Law Office.
|
INSP - Final | 3/5/1999 | 3/5/1999 | 3/5/1999 | | PASS |
Jim Storey
|
|
|
03/05/99 301 - FNL -OK FINAL
|
INSP - Final | 3/4/1999 | 3/5/1999 | 3/5/1999 | A | CANC |
Jim Storey
|
|
|
03/05/99 301 - ###-#### Dennis
|
INSP-Final Inspection | 3/3/1999 | 3/4/1999 | 3/4/1999 | A | PASS |
Rick Jackson
|
|
|
###-#### Marva occ approved
|
INSP - Final | 3/3/1999 | 3/4/1999 | 3/4/1999 | P | FAIL |
Jim Storey
|
|
|
03/04/99 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Framing/Rough-in | 2/23/1999 | 2/23/1999 | 2/24/1999 | P | PASS |
Jim Storey
|
|
|
02/24/99 301 - FRAM-OK FRAMING
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/19/1999 | | PASS |
|
|
|
|
Plan resubmittals received | | | 2/19/1999 | | |
|
|
|
RECEIVED TWO COPIES OF SHEETS E-1 AND E-2. ROUTED TO ARLAN S. KMM
|
Inspection Record Card- Bld | | | 2/19/1999 | | |
|
|
|
|
Telephone call | | | 2/19/1999 | | |
|
|
|
talked to pat m. will get check to us
|
Plan Reviewer's activity | | | 2/19/1999 | | PASS |
|
|
|
Recieved resubmittal. These were electrical drawings. Does not change pre
|
Issue PAID IN FULL permit | | | 2/19/1999 | | |
|
|
|
|
CHANGE STATUS TO (P) | | | 2/19/1999 | | PEND |
|
|
|
as per cathy resubmittal gave to plan check.mps
|
Print Occupancy Form | | | 2/19/1999 | | |
|
|
|
|
Plan assigned to (ADS) | 2/10/1999 | | 2/19/1999 | | PASS |
|
|
|
02/19/99 07:49:32 ADS - this action updated by action script from <<>> in Case No. BLD99-0344
|
Routing - PLAN CHECK | 2/18/1999 | | 2/19/1999 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 2/18/1999 | | PASS |
|
|
|
|
Routing - FIRE | 2/16/1999 | | 2/18/1999 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 2/12/1999 | | 2/16/1999 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 2/10/1999 | | 2/12/1999 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 2/10/1999 | | |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Plan assigned to (MYS) | 2/8/1999 | | 2/10/1999 | | |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 2/9/1999 | | PASS |
|
|
|
|
Received Certificate of Value | | | 2/9/1999 | | PASS |
|
|
|
|
Application received | | | 2/8/1999 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 2/8/1999 | | |
|
|
|
|