Information based on query as of Thursday, September 26, 2024.
Permit Information
Permit NumberBLD99-00528
StatusExpired
Name IDAHO POWER
Site Address 650 GOWEN RD
Project NameGOWEN SUBSTATION
Customer Number 
ePlanReviewNo
Description
GOWEN SUBSTATION * TO CONSTRUCT A 288 SQ. FT. MASONRY ONE STORY CONTROL BUILDING FOR AN ELECTRICAL SUBSTATION FOR IDAHO POWER. Construction is concrete foundation & floor, CMU walls, wood truss roof. PC#141-99 CUP98-0138 ads
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Framing/Rough-in5/24/19995/25/19995/25/1999APASS
DetailsJim Storey
05/25/99 301 - Maynard ###-#### rough framing
INSP - Framing/Rough-in5/19/19995/19/19995/19/1999 PART
DetailsJim Storey
05/18/99 301 - Rick ###-####
INSP - Framing/Rough-in5/19/19995/19/19995/19/1999 PART
DetailsJim Storey
05/18/99 301 - Rick ###-####
INSP - Framing/Rough-in5/12/19995/14/19995/14/1999ACANC
DetailsRuss Owen
05/14/99 407 - Rick ###-####
(F) Reprint permit  4/26/1999
INSP - Concrete4/20/19994/20/19994/21/1999PPASS
DetailsRuss Owen
04/20/99 407 - foundation wallls.
INSP - Foundation4/16/19994/19/19994/19/1999APASS
DetailsRuss Owen
04/19/99 407 - footing/gowen sub victor ###-####
Issue PAID IN FULL permit  4/16/1999
Telephone call  4/16/1999
CALLED LEFT MESSAGE W/BLAIN-TOLD HIM WE NEEDED SOMETHING FROM ACHD TO SHOW FEES PAID OR EXEMPT. GAVE PHONE NUMBERS AND NAMES OF PERSONS TO CONTACT AT ACHD.MPS
Inspection Record Card- Bld  4/16/1999
Print Occupancy Form  4/16/1999
Routing - PLANNING4/14/1999 4/15/1999 PASS
approved per DRH99-0047.
Plan assigned to (ADS)3/1/1999 4/15/1999 PASS
Details
04/15/99 13:07:50 MYS - this action updated by action script from <<>> in Case No. BLD99-0528
Routing - PLAN CHECK4/15/1999 4/15/1999 PASS
This plan approved by Arlan Smith. Taken to front desk by M. Southard for issuance.
Print Pending Permit.LaserJet4  4/15/1999
PLANS/APPL TAKEN TO FRONT DESK  4/15/1999 PASS
This plan reviewed and approved by Arlan Smith.
Routing - PLANNING3/4/1999 4/14/1999 PASS
Design Review required (condition 18), but not submitted yet. TAC 3/09/99 Information submitted showing compliance with Cup98-0138. Pass 4/14/99 TAC
Routing - PLAN CHECK3/16/1999 4/8/1999 PEND
Routing - FIRE3/11/1999 3/15/1999 PASS
Plan Review Completed(1st rev)  3/15/1999 FAIL
planning issue
Routing - PLAN CHECK3/11/1999 3/11/1999 PASS
Routing - PLUMBING3/3/1999 3/4/1999 PASS
Routing - PUBLIC WORKS3/2/1999 3/3/1999 PASS
Plan routing begun/NEW & ADDTN3/1/1999 3/2/1999 PASS
Plans ACCEPTED BY PLAN TECH  3/2/1999 PASS
MR. JOHNSTON CAME IN AND SIGNED AND STAMPED COVER SHEET, AND BROUGHT IN STRUC. CALCS. KMM
Plan assigned to (MYS)3/1/1999 3/1/1999 PASS
DetailsMarlene Southard
Application received  3/1/1999
Plans ACCEPTED BY PLAN TECH  3/1/1999 HOLD
3-2-99 CONTACTED BLAINE JOHNSTON TO LET HIM KNOW THAT THE COVER SHEET NEEDS TO BE STAMPED AND SIGNED. AND THAT STRUCTURAL CALCS. ARE REQUIRED. BLAINE WILL COME IN 3-2-99 AM TO TAKE CARE OF THESE NEEDS. KMM
Received Certificate of Value  3/1/1999 PASS
Routing Off Site - STRUCTURAL3/1/1999 3/1/1999
ENG. WILL BE DONE INHOUSE.
Recd Pcfee & Taken To Pln CK  3/1/1999