Permanent Occupancy | | 7/15/1999 | 7/15/1999 | | DONE |
|
|
|
|
INSP - Final | 7/14/1999 | 7/15/1999 | 7/15/1999 | A | PASS |
Carl Dependahl
|
|
|
07/15/99 340 - CARL ###-#### FINAL; ok to sign at office for c/o
|
Permanent occupancy | | | 7/15/1999 | | PASS |
|
|
|
issued Cert. of Occ. to Papa Murphy's cert. #7838
|
Temporary occupancy | | | 6/17/1999 | | PASS |
|
|
|
Temp. Occ. Cert. #3855 issued 6-17-99 to Papa Murphy's.
|
INSP-Final Inspection | 6/16/1999 | 6/16/1999 | 6/16/1999 | P | PASS |
Joe Tawney
|
|
|
06/16/99 406 - REINSP OK FOR PERM OCC
|
INSP - Final | 6/16/1999 | 6/16/1999 | 6/16/1999 | A | PART |
Carl Dependahl
|
|
|
06/16/99 340 - ok for t/o,..need cdhd final for perm. Contact phone is
|
INSP-Final Inspection | 6/11/1999 | 6/11/1999 | 6/11/1999 | P | FAIL |
Joe Tawney
|
|
|
06/11/99 406 - FINAL FAIL FIRE EXT, EXIT SIGN, DOOR HDWRE,LANDING
|
Code Occupancy Approval | | | 6/10/1999 | | |
|
|
|
Final occupancy requested by Greg Fisher ###-#### or ###-#### (cell)
|
INSP - Framing/Rough-in | 5/13/1999 | 5/14/1999 | 5/14/1999 | A | PART |
Carl Dependahl
|
|
|
05/14/99 340 - Greg ###-#### ok to rock ; has elec & htg c/n..need submi
|
INSP - Framing/Rough-in | 5/12/1999 | 5/12/1999 | 5/12/1999 | P | FAIL |
Carl Dependahl
|
|
|
05/12/99 340 - Greg ###-####...elec c/n, recall
|
INSP - Foundation | 4/28/1999 | 4/29/1999 | 4/29/1999 | A | PART |
Carl Dependahl
|
|
|
04/29/99 340 - int ftg, slab [8664338].
|
INSP - Foundation | 4/27/1999 | 4/28/1999 | 4/28/1999 | A | PART |
Carl Dependahl
|
|
|
04/28/99 340 - footing/ Greg ###-####; cell ###-####; rec'd eng'g for ad
|
Plan assigned to (R_H) | 3/16/1999 | | 4/13/1999 | | PASS |
|
|
|
04/13/99 07:41:38 RMH - this action updated by action script from <<>> in Case No. BLD99-0603
|
Print Pending Permit.LaserJet4 | | | 4/13/1999 | | PASS |
|
|
|
|
Print Occupancy Form | | | 4/13/1999 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 4/13/1999 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/13/1999 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 4/13/1999 | | |
|
|
|
|
Routing - PLAN CHECK | 4/12/1999 | | 4/13/1999 | | PASS |
|
|
|
|
Routing - PLUMBING | 4/12/1999 | | 4/12/1999 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 3/30/1999 | | FAIL |
|
|
|
plumbing fail
|
Routing - FIRE | 3/29/1999 | | 3/30/1999 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 3/29/1999 | | PASS |
|
|
|
No coorections required from buliding, still waiting for Plumbing plans. wi9ll route to fire department.
|
Routing - PLAN CHECK | 3/29/1999 | | 3/29/1999 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 3/25/1999 | | HOLD |
|
|
|
Spoke with Bill McCombs he has indicated that the owner would wish to have the floor plans reversed from what was submited. I spoke with Bill today he told me that he would submit new plans to reflect the changes, plans are on hold until new plans are submited.
|
Routing - PLAN CHECK | | | 3/25/1999 | | HOLD |
|
|
|
|
Routing - PLUMBING | 3/17/1999 | | 3/24/1999 | | FAIL |
|
|
|
|
Routing - PLANNING | 3/16/1999 | | 3/17/1999 | | PASS |
|
|
|
approved per DRH99-0020.
|
Routing - PUBLIC WORKS | 3/16/1999 | | 3/16/1999 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 3/8/1999 | | 3/16/1999 | | |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 3/16/1999 | | |
|
|
|
Route to PUBLIC WORKS, PLANNING, PLUMBING, PLAN CHECK and FIRE. Previously routed to CDH and approved by Bud Fulleton.
|
Plans ACCEPTED BY PLAN TECH | | | 3/11/1999 | | |
|
|
|
RECEIVED TWO COPIES OF SITE PLAN AND EXTERIOR ELEVATIONS. FOR REFERENCE ONLY CROSSED OUT OF E1 AND P1 SHEETS. KMM
|
Plans ACCEPTED BY PLAN TECH | | | 3/9/1999 | | FAIL |
|
|
|
P1 AND E1 SHEETS STATE FOR REFERENCE ONLY. REQUIRE KEY PLAN. CONTACTED JIM WOOD AT ###-#### OF THESE NEEDS. PLANS WERE TAKEN AND APPROVED AT CDH 1-25-99 BY BUD FULLETON
|
Application received | | | 3/8/1999 | | |
|
|
|
|
Received Certificate of Value | | | 3/8/1999 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/8/1999 | | |
|
|
|
|