Fee Review-notes | 3/16/1999 | | 1/28/2000 | | DONE |
|
|
|
|
Permanent occupancy | | | 10/18/1999 | | DONE |
|
|
|
Perm. Occ. Cert. #7955 issued 10-18-99 to C M Company.
|
BLD-Final | 9/28/1999 | 9/29/1999 | 9/30/1999 | A | PASS |
Jim Storey
|
|
|
Dan ###-#### ok for perm. Occ.
|
Permanent Occupancy | | 9/29/1999 | 9/29/1999 | | DONE |
|
|
|
|
FIRE-Final Inspection | 9/27/1999 | 9/28/1999 | 9/28/1999 | A | PASS |
Rick Jackson
|
|
|
RE-INSP FN-DAN ###-#### Occupancy approved
|
Code Occupancy Approval | | | 9/28/1999 | | PASS |
|
|
|
ALL COMPLETED ITES DONE, FINAL OCCUPANCY SIGNED OFF AND BOND RELEASED.
|
Temporary occupancy | | | 9/13/1999 | | PART |
|
|
|
Temp. Occ. Cert. #3918 issued 9/13/99 to CM Company.
|
INSP - Final | 9/10/1999 | 9/10/1999 | 9/10/1999 | P | PART |
Jim Storey
|
|
|
safety glazing not installed for sidelights
|
Code Occupancy Approval | | | 9/10/1999 | | FAIL |
|
|
|
NO LANDSCAPE IN PLACE, BONDED FOR $29,117 FOR UNCOMPLETED ITEMS, CATHY RECEIVED BOND 9-8-99, I SIGNED TEMPORARY OCCUPANCY THIS DATE, 9-10-99.
|
INSP - Final | 9/9/1999 | 9/9/1999 | 9/9/1999 | A | NR |
|
|
|
CONTRACTOR NOT READY
|
INSP-Final Inspection | 9/8/1999 | 9/9/1999 | 9/9/1999 | P | FAIL |
Rick Jackson
|
|
|
EXIT DOOR HARDWARE; EXTINGUISHERS
|
INSP - Concrete | 6/15/1999 | 6/15/1999 | 6/15/1999 | | PASS |
Jim Storey
|
|
|
06/15/99 301 - ###-#### JOEL//REBAR
|
INSP - Foundation | 6/4/1999 | 6/7/1999 | 6/7/1999 | A | PART |
Jim Storey
|
|
|
06/07/99 301 - EAST FOOTING AND NORTH BLBG FOOTING OK PENDING SPECIAL IN
|
INSP - Foundation | 6/2/1999 | 6/2/1999 | 6/2/1999 | | PASS |
Jim Storey
|
|
|
06/02/99 301 - Joel ###-####
|
INSP - Foundation | 5/18/1999 | 5/19/1999 | 5/19/1999 | P | PART |
Jim Storey
|
|
|
05/19/99 301 - ok for cover pending strata report.
|
(F) Reprint permit | | | 5/6/1999 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 5/5/1999 | | |
|
|
|
|
Print Occupancy Form | | | 5/4/1999 | | |
|
|
|
|
Routing - PLAN CHECK | 4/22/1999 | | 5/4/1999 | | PASS |
|
|
|
|
Telephone call | | | 5/4/1999 | | MESS |
|
|
|
left mess that plans are ready
|
Inspection Record Card- Bld | | | 5/4/1999 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/4/1999 | | PASS |
|
|
|
|
Plan assigned to (JCM) | 3/15/1999 | | 5/4/1999 | | PASS |
John Menard
|
|
|
|
Plan resubmittals received | | | 5/3/1999 | | PEND |
|
|
|
RECEIVED RESUBMITTALS FROM BRS ARCHITECTS,KYLE FREUTEL, FORWARDED SAME TO HOHN MENARD. DAR 5/4/99-
|
Plan resubmittals requested | | | 4/22/1999 | | PEND |
|
|
|
FAXED KYLE FREUTEL A COMMENT LIST REQUESTING ADDITIONAL RESUBMITTALS.
|
Routing - PUBLIC WORKS | 4/20/1999 | | 4/21/1999 | | PASS |
|
|
|
|
Plan resubmittals received | | | 4/20/1999 | | PENR |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM KYLE FREUTEL, BRS ARCHITECTS, FORWARDED SAME TO JOHN MENARD. DAR 4/20/99
|
Routing - PLAN CHECK | 4/15/1999 | | 4/20/1999 | | PEND |
|
|
|
|
Routing Off Site - STRUCTURAL | 4/12/1999 | | 4/20/1999 | | PASS |
|
|
|
CONTACTED PDQ TO TAKE OUT REVISED SHEETS S2.2, 2.2, AND 5.1 WITH ONE COPY OF CALCS. KMM
|
Routing - FIRE | 4/13/1999 | | 4/14/1999 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 4/14/1999 | | FAIL |
|
|
|
ubc, plumbing & public works issues
|
Routing - PLAN CHECK | 4/9/1999 | | 4/13/1999 | | PEND |
|
|
|
|
Plan resubmittals received | | | 4/13/1999 | | |
|
|
|
RECEIVED ONE COPY OF REVISED SHEETS S2.2, S.2, 5.1 AND CALCS. FROM BRS, AND ROUTED TO JOHN M. KMM
|
Plan resubmittals requested | | | 4/13/1999 | | PEND |
|
|
|
MAILED KYLE FREUTEL AT BRS A COPY OF THE COMMENT LIST REQUESTING REVISIONS.
|
Plan resubmittals received | | | 4/12/1999 | | |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEETS S2.2, 2.2, AND 5.1 WITH TWO COPIES OF CALCS. ROUTED TO JOHN M. KMM JOHN MADE THE COMENT THAT HE NEEDS ONE MORE COPY OF THE ABOVE. I CONTACTED KYLE FREUTEL OF THIS NEED (MESSAGE ON MACHINE). KMM
|
Routing - PLUMBING | 4/8/1999 | | 4/9/1999 | | PASS |
|
|
|
|
Plan resubmittals received | | | 4/7/1999 | | PEND |
|
|
|
Received resubmittals from Kyle Freutel, BRS Architects, sheets P-l & P-2 by Charles R. Paulin, included sheets in original plans and sent all to plumbing. DAR 4/8/99
|
Routing - PLAN CHECK | 4/6/1999 | | 4/7/1999 | | PEND |
|
|
|
|
Routing - PLANNING | 3/30/1999 | | 4/6/1999 | | PASS |
|
|
|
CUP98-0158 APPROVED PENDING DESIGN REVIEW APPROVAL. DR Approval 4/6/99 per DRH99-0006. tkw
|
Routing - PLUMBING | 3/25/1999 | | 3/30/1999 | | FAIL |
|
|
|
|
Routing - PUBLIC WORKS | 3/15/1999 | | 3/25/1999 | | FAIL |
|
|
|
Site plan does not comply with recorded plat and/or legal description. DAR 3/25/99
|
Plan resubmittals requested | | | 3/19/1999 | | PEND |
|
|
|
FAXED MARK KINGHORN AT BRS A COPY OF THE COMMENT LIST FROM THE CONSULTING STRUCTURAL ENGINEER REQUESTING REVISIONS.
|
Routing Off Site - STRUCTURAL | 3/17/1999 | | 3/19/1999 | | FAIL |
|
|
|
CONTACTED PDQ TO TAKE PLANS TO OUTSIDE ENG. KMM
|
Plans ACCEPTED BY PLAN TECH | | | 3/17/1999 | | PASS |
|
|
|
RECEIVED STAMPED AND SIGNED PLUMB. AND MECH. PLANS. ONE COPY OF ENG. DRAWINGS WITH SOILS REPORT. WILL ROUTE TO OUTSIDE ENG. KMM
|
Plan assigned to (MYS) | 3/12/1999 | | 3/15/1999 | | |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 3/15/1999 | | PEND |
|
|
|
REQUIRES SOILS REPORT. PLUMB. AND MECH. SHEETS NEED TO BE SIGNED. REQUIRES OUTSIDE ENG. SET. OF PLANS. CONTACTED KYLE FRUTEL OF THIS NEED. KMM WILL START ROUTING TO PW, & P&Z.
|
Received Certificate of Value | 3/15/1999 | | 3/15/1999 | | |
|
|
|
|
Plan routing begun/NEW & ADDTN | 3/15/1999 | | 3/15/1999 | | |
|
|
|
|
Application received | | | 3/12/1999 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/12/1999 | | |
|
|
|
|