Permit Information
Permit NumberBLD99-00682
StatusFinaled
Name ROMAN CATHOLIC DIOCE SE
Site Address 7009 W FRANKLIN RD
Project NameBISHOP KELLY - GYM.
Customer Number 
ePlanReviewNo
Description
BISHOP KELLY HIGHSCHOOL GYMNASIUM * TO CONSTRUCT A NEW 35,117 SQ. FT. TWO STORY GYMNASIUM BUILDING. CONSTRUCTION WILL BE TYPES II-1HR WITH SPRINNKLER SUBSTIITUTION AND TYPE V-1HR WITH A TWO HOUR AREA SEPARATION WALL BETWEEN THE MAIN GYM AND THE WRESTLING ROOM. OTHER WORK INCLUDES ALL REMAINING SITE WORK, PAVING AND LANDSCAPINNG PER APPROVED PLANS AND ATTACHMENTS. CUP98-0130 PC#183-99 (GRADING UNDER PERMIT BLD99-0681 WITH ITS OWN SET OF PLANS). FIRE SPRINKLERS USED FOR ONE-HOUR SUBSTITUTION NOT AREA. BUILDING HAS 28,493 SQ. FT. ON THE FIRST FLOOR WITH 6,624 SQ. FT. ON THE SECOND FLOOR.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes6/19/20036/19/20036/19/2003 DONE
Fee Review-notes3/16/1999 10/24/2000 DONE
additional values from the subs
(F) Reprint permit  10/24/2000 DONE
Permanent occupancy  9/11/2000 DONE
Perm. Occ. Cert. #8364 issued 9-11-00 to Bishop Kelly High School for their gym.
Permanent Occupancy 9/7/20009/7/2000 DONE
Details
BLD-Final9/6/20009/7/20009/7/2000APASS
DetailsCarl Dependahl
8888018 9/7/2000 11:48:08 AM card to contractor 9/7/2000 4:06:47 PM
BLD-Final7/28/20007/31/20007/31/2000AFAIL
DetailsCarl Dependahl
Scheduled by a contractor via Hello! on 07/28/2000 at 11:11:33. Contact: .c/n, firestops, ADA at restrms (boots) S label at corr. doors, etc. ok for t/o 7/31/2000 12:02:51 PM
FIRE-Final Inspection7/27/20007/27/20007/27/2000PPASS
DetailsJoe Tawney
Scheduled by a contractor via Hello! on 07/27/2000 at 10:48:57. Contact: . Reinsp. ok for perm. occ. 7/28/00 10:04:40 AM
FIRE-Final Inspection7/26/20007/26/20007/26/2000PFAIL
DetailsJoe Tawney
Jim ###-#### Scheduled for 7/27/00 pm 7/27/00 10:41:55 AM
FIRE-Final Inspection7/20/20007/21/20007/21/2000PFAIL
DetailsJoe Tawney
Scheduled by a contractor via Hello! on 07/20/2000 at 11:57:32. Contact: . Reinsp. fail not ready to be rescheduled 7/24/00 1:04:57 PM
BLD-Conference7/3/20007/3/20006/30/2000APASS
DetailsCarl Dependahl
B.K. Gym: conf w/ bldr re: final req's
Code Occupancy Approval  6/20/2000 DONE
MEETS COMPLIANCE AND THEN SOME WITH cu - PASS
FIRE-Final Inspection6/12/20006/16/20006/16/2000AFAIL
DetailsJoe Tawney
kate ###-#### Final fail C/N issued. 6/16/00 2:14:34 PM
FIRE-Final Inspection5/12/20005/17/20005/17/2000AFAIL
DetailsJoe Tawney
Scheduled by a contractor via Hello! on 05/12/2000 at 12:46:15. Contact: . Final fail alarm submittal not on site corrections required. 5/17/00 2:05:24 PM
FIRE-Sprinkler Rough-in3/16/20003/16/20003/16/2000PPART
DetailsJoe Tawney
###-#### 2hr 200lb test Ok on underground and above ground hydro tests. 3/17/00 10:36:28 AM
BLD-Framing/Rough-in3/2/20003/2/20003/2/2000PPART
DetailsCarl Dependahl
jim ###-#### ceiling grid insp Grid @ stairs & lobby areas ok; firestop rated walls as noted at corridors & concession. 3/3/00 8:50:33 AM
BLD-Conference2/28/20002/28/20002/28/2000PPASS
DetailsCarl Dependahl
W/supt. re: corrections.
BLD-Framing/Rough-in2/17/20002/17/20002/17/2000PPART
DetailsCarl Dependahl
jim ###-#### fr Grid. 2/18/00 9:40:43 AM
BLD-Framing/Rough-in2/10/20002/11/20002/11/2000APART
DetailsCarl Dependahl
CEILING GRID\\###-####
BLD-Framing/Rough-in2/7/20002/7/20002/7/2000PPART
DetailsRuss Owen
###-#### Partial inspection of ceiling framing. 2/7/00 1:34:54 PM
BLD-Framing/Rough-in2/3/20002/3/20002/3/2000PPART
DetailsCarl Dependahl
JIM ###-#### SHEETROCK & FR; stairs and portion 1st fl corr at south side
BLD-Framing/Rough-in2/1/20002/1/20002/1/2000PPART
DetailsCarl Dependahl
###-#### 1 hr lid at stairs 1st layer ok 2/3/00 7:28:01 AM
BLD-Framing/Rough-in1/27/20001/28/20001/28/2000APART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 01/27/2000 at 13:00:12. Contact: . ceiling ok at south stairway only thing insp. 1/28/00 11:24:16 AM
BLD-Framing/Rough-in1/28/20001/28/20001/28/2000PPART
DetailsTom Arcoraci
658jim ###-#### stairway l d ok for cover 1/31/00 8:32:25 AM
BLD-Framing/Rough-in1/21/20001/21/20001/21/2000PPART
DetailsCarl Dependahl
###-#### Hard lids @ rooms off 1st floor corridor- keep C/N, need firestops @ "Gym side". 1/25/00 12:13:46 PM
BLD-Conference1/19/20001/19/20001/19/2000PPASS
DetailsCarl Dependahl
BKH's; Rec'd submittal for ceiling (rated) extension @ corridor. ok.
BLD-Framing/Rough-in1/14/20001/18/20001/18/2000AFAIL
DetailsCarl Dependahl
658--9163 C/N: need 1hr. lid detail @ south exit & corridor. 1/18/00 3:50:13 PM
BLD-Conference1/12/20001/13/20001/13/2000APASS
DetailsCarl Dependahl
Jim ###-####. Met w/supt. Onsite re HVAC @ corridor & lobby Alan Hauser present.
BLD-Framing/Rough-in1/7/20001/10/20001/10/2000PPART
DetailsCarl Dependahl
Sean ###-####. 1st layer lid @ lobby ok; install "shaft" at vestible.
BLD-Conference1/7/20001/7/20001/7/2000PPASS
DetailsCarl Dependahl
w/Mike Otto & project mngr. keep C/N re: dampers @ corridor.
BLD-Framing/Rough-in1/5/20001/6/20001/6/2000AFAIL
DetailsCarl Dependahl
###-####. Need resub. for HVAC @ corridor; ceilings @ foyer & shower rms. ok to cover.
BLD-Framing/Rough-in1/4/20001/5/20001/6/2000PPART
DetailsJim Storey
SHAWN-- ###-#### CEILING COVER. Conf. w/Arch.
FIRE-Supply Line Cover1/3/20001/3/20001/3/2000PPART
DetailsJoe Tawney
sean ###-####. Ok to cover boys & girls locker rooms hard lid areas add two braces & one sprinkler head.
BLD-Framing/Rough-in12/23/199912/23/199912/23/1999PFAIL
DetailsCarl Dependahl
Need arch's resubmittal for smoke/fire dampers...complete.
BLD-Conference12/8/199912/8/199912/8/1999APART
DetailsCarl Dependahl
reviewed eng's reports of wip...
BLD-Conference10/26/199910/28/199910/28/1999APART
DetailsCarl Dependahl
conference Jim ###-#### Need test results for ASTM E735-spray applied fire proofing. Preliminary work to begin.
Plan Reviewer's activity  10/14/1999 PASS
BLEACHER PLAN FROM MANUFACTURE APPROVED. ONLY ONE SET SUBMITTED CONTACTED TOM BROPHY AT LOMBARD CONRAD. MLO
Additional plans submitted  8/25/1999 PEND
RECEIVED ADDITIONAL PLANS ON SEATING FROM TOM BROPHY OF LOMBARD CONRAD.FORWARDED SAME TO MIKE OTTO. 8/25/99 DAR
INSP-Final Inspection8/20/19998/23/19998/23/1999PPART
DetailsJoe Tawney
09/01/99 406 - FINAL OK FOR TEMP OCC
INSP - Final8/20/19998/23/19998/23/1999PFAIL
DetailsCarl Dependahl
08/23/99 340 - TIM ###-#### need fire, p.u relocatable permits, etc.
INSP - Framing/ Rough-in7/22/19997/22/19997/22/1999 PART
DetailsCarl Dependahl
/ / 340 - NEED ADD'L PERMIT FOR RELOC. CLASSRMS PER MIKE O.
INSP - Framing/Rough-in7/21/19997/21/19997/21/1999PPART
DetailsCarl Dependahl
07/21/99 340 - Jim; ok to place 1st layer at alcove at corr. lid (classr
INSP - Framing/Rough-in7/20/19997/20/19997/20/1999PFAIL
DetailsCarl Dependahl
07/20/99 340 - WALL INSPECTION HALL JIM ###-####; wall, need clg detail
INSP-Sprinkler Rough-in/Hydro7/20/19997/20/19997/20/1999 PART
DetailsJoe Tawney
/ / 406 - OK ON ALL UNDERGROUND PIPING
INSP - Framing/Rough-in7/16/19997/19/19997/19/1999APART
DetailsCarl Dependahl
07/19/99 340 - sheetrock inspection classroom hallway Jim ###-#### anchor inspection on portables
INSP - Foundation7/16/19997/16/19997/16/1999 PART
DetailsCarl Dependahl
07/16/99 340 - gym fnd; spec insp onsite, need eng's review of all discr
INSP - Foundation6/23/19996/24/19996/24/1999PPART
DetailsCarl Dependahl
06/24/99 340 - ###-####//FOOTINGS GYMNASIUM mti onsite. conf w/ Jim, CM
(F) Reprint permit  5/18/1999
Issue PAID IN FULL permit  5/13/1999
Plan assigned to (MLO)3/16/1999 5/11/1999 PASS
DetailsMike Otto
Print Occupancy Form  5/11/1999
Inspection Record Card- Bld  5/11/1999
PLANS/APPL TAKEN TO FRONT DESK  5/11/1999 PASS
Telephone call  5/11/1999 MESS
left mess for scott henson that plans are ready
Routing Off Site - STRUCTURAL5/5/1999 5/10/1999 PASS
ROUTED A MEMORANDUM DATED 4-21-99 TO CH2MHILL. KMM
Routing - FIRE5/6/1999 5/10/1999 PASS
Routing - PLAN CHECK4/29/1999 5/5/1999 PASS
Plan resubmittals received  4/29/1999
RECEIVED TWO COPIES OF REVISED SHEETS C1.0, A2.0, AA2.1, AA2.2, AA2.3, AA2.4, AA3.1, AA3.2, AA4.1, AA4.2, AA5.1, AA6.1, AA6.2, AA7.3, AA7.5, AS1.1, AS2.1, AS3.1, BS0.1, BS1.1, M1.1, M1.2, M2.1, E1.1, E1.2, E2.1F, E2.1L, E2.1P, E2.1S, E2.2F, E2.2L, E2.2P, E2.2S, E2.3B, E4.0, E4.1, E5.0, ROUTED TO MIKE O. KMM
Routing - FIRE4/15/1999 4/19/1999 FAIL
plans are being changed to satisfy UBC issues. will review when the building stops changing
Plan Review Completed(1st rev)  4/19/1999 FAIL
ubc and ufc issues
Routing - PLAN CHECK4/1/1999 4/15/1999 FAIL
Plan resubmittals requested  4/15/1999 FAIL
CORRECTIONS MAILED AND FAXED TO ARCHITECT. MLO
Plan resubmittals requested  4/9/1999 FAIL
STRUCTRUAL CORRECTIONS MAILED AND FAXED TO ARCHITECT.
Routing Off Site - STRUCTURAL3/16/1999 4/7/1999 FAIL
CONTACTED PDQ TO TAKE PLANS TO OUTSIDE ENG. KMM 4-7-99 RECEIVED ONE COPY OF STRUCTURAL REVIEW LETTER BY CH2MHILL DATED 4-6-99. ROUTED TO MIKE O. KMM
Routing - PLANNING3/31/1999 4/1/1999 PASS
APPROVED PER CUP98-0130
Routing - PLUMBING3/22/1999 3/31/1999 PASS
Routing Off Site - A.C.H.D3/22/19993/22/19993/22/1999 PASS
NO IMPACT FEES DUE
Routing - PUBLIC WORKS3/17/1999 3/22/1999 PASS
Routing Off Site - C.D.H3/17/1999 3/17/1999 PASS
Plans were submitted before going out to CDH. Deb Moran will be in Wed. 3-17-99 to review plans with Scott Henson. kmm
Plan routing begun/NEW & ADDTN3/16/1999 3/17/1999
Received Certificate of Value  3/16/1999 PASS
Plans ACCEPTED BY PLAN TECH  3/16/1999 PASS
Plan assigned to (MYS)3/15/1999 3/16/1999
DetailsMarlene Southard
Application received  3/15/1999
Recd Pcfee & Taken To Pln CK  3/15/1999