BISHOP KELLY HIGHSCHOOL * TO CONSTRUCT A 2,973 SQ. FT. ONE STORY, TYPE VN FULLY FIRE SPRINKLERED CLASSROOM ADDITION TO THE EXISTING HIGHSCHOOL CLASSROOM WING. OTHER WORK INCLUDES ALL SITE IMPROVMENTS, PAVING AND LANDSCAPING. ALL WORK IS PER APPROVED PLANS AND ATTACHMENTS, CUP98-0130, PC#184-99. FIRE SPRINKLERS ARE USED FOR AREA INCREASE.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Expired2/7/20012/7/20012/7/2001PPASS
DetailsTom Arcoraci
Added by Inspector: 408 On 2/7/2001 5:12:21 PM
INSP - Framing/ Rough-in8/10/19998/10/19998/10/1999 PART
DetailsCarl Dependahl
/ / 340 - CONF ONLY W/ BLDR, NEED HVAC
INSP - Framing/Rough-in8/9/19998/10/19998/10/1999AFAIL
DetailsCarl Dependahl
08/10/99 340 - JIM ###-#### CEILING GRID needcomplete hard lid above ( f
INSP - Framing/Rough-in7/16/19997/16/19997/16/1999 FAIL
DetailsCarl Dependahl
07/16/99 340 - JIM; need arch's detail for complete closure of 1hr corr.
INSP - Foundation5/20/19995/20/19995/20/1999PPART
DetailsCarl Dependahl
05/20/99 340 - ###-#### PGR//REBAR & STEM WALL;mti onsite,pend specinsp
INSP - Foundation5/18/19995/19/19995/19/1999PPART
DetailsCarl Dependahl
05/19/99 340 - ###-#### PGR//REBAR**EAST SIDE OF BLDG; mti onsite, pend
Issue PAID IN FULL permit  5/13/1999
Print Occupancy Form  5/11/1999
Telephone call  5/11/1999 MESS
left mess for scott henson that plans are ready
PLANS/APPL TAKEN TO FRONT DESK  5/11/1999 PASS
Inspection Record Card- Bld  5/11/1999
Plan assigned to (MLO)3/16/1999 5/11/1999 PASS
DetailsMike Otto
Routing Off Site - STRUCTURAL5/5/1999 5/10/1999 PASS
ROUTED VIA PDQ A MEMORANDUM DATED 4-21-99 PER MIKE O. KMM
Routing - FIRE5/6/1999 5/10/1999 PASS
Routing - PLAN CHECK4/29/1999 5/5/1999 PASS
Plan resubmittals received  4/29/1999
Routing - FIRE4/15/1999 4/19/1999 FAIL
will complete review with BLD99-0682
Routing - PLAN CHECK4/1/1999 4/15/1999 FAIL
Plan resubmittals requested  4/15/1999 FAIL
CORRECTIONS MAILED AND FAXED TO ARCHITECT. MLO
Plan resubmittals requested  4/9/1999 FAIL
STRUCTURAL CORRECTIONS MAILED AND FAXED TO ARCHITECT. MLO
Routing Off Site - STRUCTURAL3/17/1999 4/7/1999 FAIL
CONTACTED PDQ TO TAKE PLANS TO OUTSIDE ENG. KMM 4-7-99 RECEIVED ONE COPY OF STRUCTURAL REVIEW LETTER BY CH2MHILL DATED 4.6.99. ROUTED TO MIKE O. KMM
Routing - PLANNING3/31/1999 4/1/1999 PASS
APPROVED PER CUP98-0130
Routing - PLUMBING3/22/1999 3/31/1999 PASS
Routing - PUBLIC WORKS3/17/1999 3/22/1999 PASS
Routing Off Site - C.D.H3/17/1999 3/17/1999 PASS
PLANS WERE SUBMITTED PRIOR TO CDH REVIEW. DEB MORAN WILL BE IN TO REVIEW PLANS FOR THE GYM. CONSESSION LOBBY ON 3-17-99. CLASSROOMS AND GYM. ON SAME SET OF PLANS.
Application received  3/16/1999 PASS
Plans ACCEPTED BY PLAN TECH  3/16/1999 PASS
Received Certificate of Value  3/16/1999 PASS
Plan routing begun/NEW & ADDTN3/16/1999 3/16/1999
Fee Review-notes3/16/1999